11162 W RICHLAND AVE 90064

Certificate Information: 11162 W RICHLAND AVE 90064

Application / Permit
24014-10000-01279
Plan Check / Job No.
B24LA05835
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
New 2-story ADU attached to existing garage in rear yard
Permit Issued
Issued on 5/27/2024
Issuing Office
Current Status
Issued on 5/27/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/2/2024 APPLICANT
Assigned to Plan Check Engineer 4/4/2024 JOE VO
Corrections Issued 4/6/2024 JOE VO
Quality Review Completed 4/10/2024 PRANITA SHAH
Applicant returned to address corrections 5/9/2024 JOE VO
Plan Check Approved 5/21/2024 JOE VO
Issued 5/27/2024 APPLICANT

Permit Application Clearance Information

Address approval Cleared 4/11/2024 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 4/15/2024 DINAH GARIN
Sewer availability Cleared 4/15/2024 DINAH GARIN
Low Impact Development (LID) Cleared 4/16/2024 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 4/17/2024 DINAH GARIN
Specific Plan Cleared 5/1/2024 JOSHUA JONES
Grading Pre-Inspection Cleared 5/2/2024 VASIL MIHALEV
Hydrant and Access approval Cleared 5/11/2024 KURT CORRAL

Contact Information

Contractor Owner-Builder       ,
Engineer Kaballo,, Amir; Lic. No.: C90707 152 S SWALL DR      BEVERLY HILLS, CA 90211

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/25/2024 Partial Approval TEMISTOCLES CAAL
Footing/Foundation/Slab 8/19/2024 Approved JESUS PINEDA
PLUMBING-Rough 8/19/2024 Partial Approval JESUS PINEDA
ELECTRICAL-Rough 2/27/2025 Corrections Issued EVAN COOPER
HVAC-Rough 2/27/2025 Approved EVAN COOPER
PLUMBING-Rough 2/27/2025 Corrections Issued EVAN COOPER
PLUMBING-Rough 5/13/2025 Corrections Issued WILBER ROSALES
Shower Pan 5/13/2025 Approved WILBER ROSALES
ELECTRICAL-Rough 7/15/2025 No Access for Inspection ARAM AVEDISIAN
PLUMBING-Rough 7/18/2025 Approved MEL KHACHATOURIAN
BUILDING-Rough-Frame 7/22/2025 Not Ready for Inspection BOBBY KEY
ELECTRICAL-Rough 7/22/2025 Approved BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 7/22/2025 Corrections Issued BOBBY KEY
MERV13>=Rough 7/22/2025 Approved BOBBY KEY
PLUMBING-Rough 7/22/2025 Corrections Issued BOBBY KEY
BUILDING-Rough-Frame 8/8/2025 Approved MEL KHACHATOURIAN
Green Building Rough 8/8/2025 Approved MEL KHACHATOURIAN
Interior/Exterior Lathing 8/8/2025 Partial Approval MEL KHACHATOURIAN
PLUMBING-Rough 8/8/2025 Approved MEL KHACHATOURIAN
Insulation 8/14/2025 Corrections Issued ARAM AVEDISIAN
Drywall Nailing 8/26/2025 Approved DANIEL VERA
ELECTRICAL-Final 2/2/2026 Approved WILBER ROSALES
Final 2/2/2026 Corrections Issued WILBER ROSALES
Green Building Final 2/2/2026 Not Ready for Inspection WILBER ROSALES
HVAC-Final 2/2/2026 Corrections Issued WILBER ROSALES
MERV13>=Final 2/2/2026 Approved WILBER ROSALES
PLUMBING-Final 2/2/2026 Approved WILBER ROSALES
SGSOV-Seismic Gas S/O Valve 2/2/2026 SGSOV Approved WILBER ROSALES
Smoke Detectors 2/2/2026 Approved WILBER ROSALES