1203-1203 1/2 S SPAULDING AVE 90019

Certificate Information: 1203-1203 1/2 S SPAULDING AVE 90019

Application / Permit
24014-10000-01236
Plan Check / Job No.
B24LA05701
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
[ePlan] Addition of 2nd floor above (E) 1-story SFD. Convert attached garage to be part of SFD with front one floor addition. the secound story addition will be ADU Per LAMC 12.22 A.33(c) AND (e)
Permit Issued
Issued on 12/16/2024
Issuing Office
Current Status
Issued on 12/16/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/1/2024 APPLICANT
Assigned to Plan Check Engineer 4/11/2024 GEORGE JOLAKIAN
Corrections Issued 4/24/2024 GEORGE JOLAKIAN
Quality Review Completed 5/9/2024 RODOLFO ARIAS
Plan Check Approved 10/31/2024 GEORGE JOLAKIAN
Issued 12/16/2024 APPLICANT

Permit Application Clearance Information

Construction near power lines Cleared 4/29/2024 TINA MIRANDA
Address approval Cleared 7/3/2024 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 7/9/2024 TREVOR QUAN
Sewer availability Cleared 7/9/2024 TREVOR QUAN
Trees in Parkway Cleared 8/2/2024 DYNL MIRANDA
Permit Cleared 9/21/2024 TREVOR QUAN
Roof/Waste drainage to street Cleared 9/21/2024 TREVOR QUAN

Contact Information

Contractor Owner-Builder       ,
Engineer Adzhemyan,, Arsen; Lic. No.: C89103 1010 RALEIGH ST APT 107      GLENDALE, CA 91205

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/7/2025 Approved ARTHUR NEGRETE
Sewer 1/14/2025 Approved ARTHUR NEGRETE
Deputy Drilled-In Anchors 4/21/2025 Approved ARTHUR NEGRETE
Deputy Drilled-In Anchors 6/18/2025 Conditional Approval OSVALDO PARAMO
Deputy Wood Construction 6/18/2025 Conditional Approval OSVALDO PARAMO
Footing/Foundation/Slab 6/23/2025 Approved ARTHUR NEGRETE
METHANE-Barrier 6/23/2025 Approved ARTHUR NEGRETE
METHANE-Subgrade 6/23/2025 Approved ARTHUR NEGRETE
Deputy Wood Construction 7/24/2025 Approved ARTHUR NEGRETE
Gas Test 6/25/2026 Approved HAMIK HARTOUNIAN
Service/Power Release 6/25/2026 Approved HAMIK HARTOUNIAN
BUILDING-Rough-Frame 7/24/2026 No Result Entered DAVID WILLIAMS
Drywall Nailing 7/24/2026 No Result Entered DAVID WILLIAMS
Final 7/24/2026 No Result Entered DAVID WILLIAMS
Green Building Final 7/24/2026 No Result Entered DAVID WILLIAMS
Green Building Rough 7/24/2026 No Result Entered DAVID WILLIAMS
METHANE-Final 7/24/2026 No Result Entered DAVID WILLIAMS
METHANE-Rough 7/24/2026 No Result Entered DAVID WILLIAMS
SGSOV-Seismic Gas S/O Valve 7/24/2026 No Result Entered DAVID WILLIAMS
Smoke Detectors 7/24/2026 No Result Entered DAVID WILLIAMS