1053 W 81ST PL 90044

Certificate Information: 1053 W 81ST PL 90044

Application / Permit
24014-10000-01220
Plan Check / Job No.
B24LA05651
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING DETACHED GARAGE WITH ADDITION TO ACCESSORY DWELLING UNIT PER ORDINANCE . WORK PER WOOD FRAME PRESCRIPTIVE PROVISIONS .
Permit Issued
Issued on 12/13/2024
Issuing Office
Metro
Current Status
CofO Issued on 8/3/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/29/2024 APPLICANT
Assigned to Plan Check Engineer 4/2/2024 NEHEMIAS RAMOS
Corrections Issued 4/2/2024 NEHEMIAS RAMOS
Building Plans Picked Up 4/3/2024 APPLICANT
Applicant returned to address corrections 4/18/2024 ALEXANDER JOO
Applicant returned to address corrections 8/12/2024 SUNMIN LEE
Applicant returned to address corrections 8/21/2024 CARLOS MONTES
Applicant returned to address corrections 9/19/2024 JOSE VELAZQUEZ
Applicant returned to address corrections 9/26/2024 GEORGE ALVAREZ
Plan Check Approved 10/21/2024 JOSE VELAZQUEZ
Issued 12/13/2024 APPLICANT
CofO in Progress 7/31/2025 JOHN QUINTANILLA
Permit Finaled 8/3/2025 DEROLD HAUFF
CofO Issued 8/3/2025 DEROLD HAUFF
Permit Finaled 8/3/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 4/23/2024 ADRIAN SANCHEZ
Roof/Waste drainage to street Cleared 4/23/2024 ADRIAN SANCHEZ
Eng Process Fee Ord 176,300 Cleared 4/24/2024 ADRIAN SANCHEZ
Sewer availability Cleared 4/24/2024 ADRIAN SANCHEZ
ZI Cleared 5/14/2024 MANERI ROMAN
Construction near power lines Cleared 8/6/2024 RIDWAN HARDY
Construction within easement Cleared 8/6/2024 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/20/2024 Partial Inspection JOHN QUINTANILLA
Underground Mechanical 1/2/2025 Approved JOHN QUINTANILLA
Footing/Foundation/Slab 1/16/2025 Approved JOHN QUINTANILLA
Floor/Roof Diaphrgm/Shear Wall 2/10/2025 Partial Approval JOHN QUINTANILLA
ELECTRICAL-Rough 3/3/2025 Approved JOHN QUINTANILLA
HVAC-Rough 3/3/2025 Partial Approval JOHN QUINTANILLA
PLUMBING-Rough 3/3/2025 Approved JOHN QUINTANILLA
BUILDING-Rough-Frame 3/6/2025 Approved JOHN QUINTANILLA
ELECTRICAL-Rough 3/6/2025 Approved JOHN QUINTANILLA
HVAC-Rough 3/6/2025 Approved JOHN QUINTANILLA
Insulation 3/13/2025 Not Ready for Inspection JOHN QUINTANILLA
Interior/Exterior Lathing 3/13/2025 Approved JOHN QUINTANILLA
PLUMBING-Rough 3/13/2025 Not Ready for Inspection JOHN QUINTANILLA
PLUMBING-Rough 3/19/2025 Approved JOHN QUINTANILLA
Drywall Nailing 3/25/2025 Partial Approval ANTHONY RAMOS
Drywall Nailing 4/22/2025 Approved ANTHONY RAMOS
Insulation 4/22/2025 Approved ANTHONY RAMOS
Interior/Exterior Lathing 4/22/2025 Approved ANTHONY RAMOS
Sewer 4/25/2025 Approved ANTHONY RAMOS
ELECTRICAL-Final 5/16/2025 Not Ready for Inspection JOHN QUINTANILLA
Service/Power Release 5/16/2025 Not Ready for Inspection JOHN QUINTANILLA
BUILDING-Rough-Frame 5/30/2025 Approved JOHN QUINTANILLA
Final 5/30/2025 Not Ready for Inspection JOHN QUINTANILLA
Green Building Final 5/30/2025 Not Ready for Inspection JOHN QUINTANILLA
Green Building Rough 5/30/2025 Approved JOHN QUINTANILLA
SGSOV-Seismic Gas S/O Valve 5/30/2025 SGSOV Not Required JOHN QUINTANILLA
Service/Power Release 5/30/2025 Not Ready for Inspection JOHN QUINTANILLA
Smoke Detectors 5/30/2025 Approved JOHN QUINTANILLA
ELECTRICAL-Final 6/4/2025 Approved JOHN QUINTANILLA
HVAC-Final 6/4/2025 Approved JOHN QUINTANILLA
PLUMBING-Final 6/4/2025 Approved JOHN QUINTANILLA
Service/Power Release 6/4/2025 Approved JOHN QUINTANILLA
Final 6/9/2025 Conditional Approval JOHN QUINTANILLA
Green Building Final 6/9/2025 Approved JOHN QUINTANILLA
Final 6/27/2025 OK to Issue CofO JOHN QUINTANILLA