14322 W OSBORNE ST 91402
Certificate Information: 14322 W OSBORNE ST 91402
- Application / Permit
- 24014-10000-01214
- Plan Check / Job No.
- B24LA05621
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) 1-STORY ADU ADDITION TO (E) 2-CAR GARAGE
- Permit Issued
- Issued on 4/25/2024
- Issuing Office
- Current Status
- CofO Issued on 9/5/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/28/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 4/1/2024 | NEHEMIAS RAMOS |
| Corrections Issued | 4/2/2024 | NEHEMIAS RAMOS |
| Building Plans Picked Up | 4/4/2024 | APPLICANT |
| Plan Check Approved | 4/24/2024 | SAMUEL GONZALEZ |
| Issued | 4/25/2024 | APPLICANT |
| CofO in Progress | 8/28/2024 | VINCENT HANLEY |
| Permit Finaled | 9/5/2024 | DANIEL ORRANTE |
| CofO Issued | 9/5/2024 | DANIEL ORRANTE |
| Permit Finaled | 9/5/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 4/3/2024 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 4/4/2024 | WALLIE JONG |
| Sewer availability | Cleared | 4/4/2024 | WALLIE JONG |
| Low Impact Development (LID) | Cleared | 4/18/2024 | MELINEH AGHAKHABIAN |
| Roof/Waste drainage to street | Cleared | 4/18/2024 | EDGAR ALCARAZ |
Contact Information
| Contractor | Arrow Construction Co; Lic. No.: 573067-B | 18729 CLARK DALE AVE #C ARTESIA, CA 90701 |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/14/2024 | Partial Approval | VINCENT HANLEY |
| PLUMBING-Rough | 5/14/2024 | Partial Approval | VINCENT HANLEY |
| Excavation/Setback/Form/Re-Bar | 5/17/2024 | Approved | VINCENT HANLEY |
| Footing/Foundation/Slab | 5/17/2024 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 6/13/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| HVAC-Final | 6/13/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| PLUMBING-Rough | 6/13/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 6/14/2024 | Partial Approval | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 6/14/2024 | Approved | VINCENT HANLEY |
| Green Building Rough | 6/14/2024 | Not Ready for Inspection | VINCENT HANLEY |
| ELECTRICAL-Rough | 6/17/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| HVAC-Rough | 6/17/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| PLUMBING-Rough | 6/17/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 6/24/2024 | Corrections Issued | GREGG CUMMINGS |
| ELECTRICAL-Rough | 6/24/2024 | Corrections Issued | GREGG CUMMINGS |
| Green Building Rough | 6/24/2024 | Approved | GREGG CUMMINGS |
| HVAC-Rough | 6/24/2024 | Corrections Issued | GREGG CUMMINGS |
| Interior/Exterior Lathing | 6/24/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| PLUMBING-Rough | 6/24/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 6/26/2024 | Approved | VINCENT HANLEY |
| ELECTRICAL-Rough | 6/26/2024 | Approved | VINCENT HANLEY |
| Green Building Rough | 6/26/2024 | Approved | VINCENT HANLEY |
| HVAC-Rough | 6/26/2024 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 6/26/2024 | Approved | VINCENT HANLEY |
| Insulation | 6/28/2024 | Approved | VINCENT HANLEY |
| Drywall Nailing | 7/2/2024 | Approved | GREGG CUMMINGS |
| Interior/Exterior Lathing | 7/2/2024 | Partial Approval | GREGG CUMMINGS |
| ELECTRICAL-Final | 8/13/2024 | Not Ready for Inspection | JACK KARGODORIAN |
| Final | 8/13/2024 | Corrections Issued | JACK KARGODORIAN |
| Gas Test | 8/13/2024 | Not Ready for Inspection | JACK KARGODORIAN |
| Green Building Final | 8/13/2024 | Not Ready for Inspection | JACK KARGODORIAN |
| HVAC-Final | 8/13/2024 | Not Ready for Inspection | JACK KARGODORIAN |
| PLUMBING-Final | 8/13/2024 | Not Ready for Inspection | JACK KARGODORIAN |
| Pre-Inspection | 8/13/2024 | Not Ready for Inspection | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 8/13/2024 | SGSOV Not Ready | JACK KARGODORIAN |
| Service/Power Release | 8/13/2024 | Not Ready for Inspection | JACK KARGODORIAN |
| Smoke Detectors | 8/13/2024 | Not Ready for Inspection | JACK KARGODORIAN |
| ELECTRICAL-Final | 8/20/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| Final | 8/20/2024 | Corrections Issued | GREGG CUMMINGS |
| Green Building Final | 8/20/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| HVAC-Final | 8/20/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| PLUMBING-Final | 8/20/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 8/20/2024 | SGSOV Not Ready | GREGG CUMMINGS |
| Service/Power Release | 8/20/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| Smoke Detectors | 8/20/2024 | Approved | GREGG CUMMINGS |
| Pre-Inspection | 8/23/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| Service/Power Release | 8/23/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| ELECTRICAL-Final | 8/27/2024 | Approved | VINCENT HANLEY |
| Final | 8/27/2024 | OK to Issue CofO | VINCENT HANLEY |
| Green Building Final | 8/27/2024 | Approved | VINCENT HANLEY |
| HVAC-Final | 8/27/2024 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 8/27/2024 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 8/27/2024 | SGSOV Approved | VINCENT HANLEY |
| Service/Power Release | 8/27/2024 | Approved | VINCENT HANLEY |