3499 S CABRILLO BLVD 90066
Certificate Information: 3499 S CABRILLO BLVD 90066
- Application / Permit
- 24014-10000-01186
- Plan Check / Job No.
- B24LA05491
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN.TWO STORY ADDITION TO EXISTING SINGLE FAMILY DWELLING WITH ATTACHED GARAGE
- Permit Issued
- Issued on 6/12/2024
- Issuing Office
- Current Status
- CofO Issued on 7/26/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/27/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 3/28/2024 | MARCELA FRANQUEZ |
| Corrections Issued | 3/30/2024 | MARCELA FRANQUEZ |
| Quality Review Completed | 4/10/2024 | TU HUA |
| Applicant returned to address corrections | 5/14/2024 | MARCELA FRANQUEZ |
| Plan Check Approved | 5/30/2024 | MARCELA FRANQUEZ |
| Issued | 6/12/2024 | APPLICANT |
| Permit Finaled | 7/26/2025 | RICHARD STEINBACH |
| Permit Finaled | 7/26/2025 | RICHARD STEINBACH |
| CofO Issued | 7/26/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 4/5/2024 | ANDREA SAINT-ANTONIN |
| Sewer availability | Cleared | 4/5/2024 | ANDREA SAINT-ANTONIN |
| Grading Pre-Inspection | Cleared | 4/12/2024 | VASIL MIHALEV |
| Low Impact Development (LID) | Cleared | 4/29/2024 | SAMUEL LINN |
| Roof/Waste drainage to street | Cleared | 5/2/2024 | ANDREA SAINT-ANTONIN |
| GPI Written Notices | Cleared | 5/30/2024 | MARCELA FRANQUEZ |
Contact Information
| Architect | Driscoll,, Christopher; Lic. No.: NA36073 | , |
| Contractor | 1 Oak Remodeling; Lic. No.: 1015424-B | 6320 VAN NUYS BLVD STE 305 VAN NUYS, CA 91401 |
| Engineer | Schwartz,, Eric; Lic. No.: NA81191 | , |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 6/28/2024 | Conditional Approval | RICHARD STEINBACH |
| Footing/Foundation/Slab | 7/2/2024 | Approved | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 7/11/2024 | Partial Approval | STEPHANIE SWANSON |
| Wood Frame | 7/11/2024 | Corrections Issued | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 7/19/2024 | Partial Approval | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 8/14/2024 | Corrections Issued | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 10/2/2024 | Partial Approval | JESUS PINEDA |
| Special/Order Compliance | 10/2/2024 | Corrections Issued | JESUS PINEDA |
| Deputy Wood Construction | 10/3/2024 | Conditional Approval | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 10/4/2024 | Corrections Issued | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 11/1/2024 | Not Ready for Inspection | JESUS PINEDA |
| HVAC-Rough | 11/1/2024 | Corrections Issued | JESUS PINEDA |
| HVAC-Rough | 11/5/2024 | Not Ready for Inspection | JESUS PINEDA |
| PLUMBING-Rough | 11/5/2024 | Corrections Issued | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 11/6/2024 | Approved | JESUS PINEDA |
| HVAC-Rough | 11/6/2024 | Not Ready for Inspection | JESUS PINEDA |
| HVAC-Rough | 11/7/2024 | Corrections Issued | JESUS PINEDA |
| PLUMBING-Rough | 11/7/2024 | Approved | JESUS PINEDA |
| ELECTRICAL-Rough | 11/12/2024 | Corrections Issued | ARAM AVEDISIAN |
| HVAC-Rough | 11/12/2024 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 11/13/2024 | Corrections Issued | JESUS PINEDA |
| ELECTRICAL-Rough | 11/15/2024 | Partial Approval | MICHAEL ALLEN |
| Interior/Exterior Lathing | 11/21/2024 | Corrections Issued | REGINA MENDEZ |
| ELECTRICAL-Rough | 11/25/2024 | Corrections Issued | HERBERT GIRON |
| BUILDING-Rough-Frame | 11/26/2024 | Approved | BOBBY KEY |
| ELECTRICAL-Rough | 11/26/2024 | Approved | BOBBY KEY |
| Green Building Rough | 11/26/2024 | Approved | BOBBY KEY |
| Insulation | 11/26/2024 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 11/26/2024 | Not Ready for Inspection | BOBBY KEY |
| Drywall Nailing | 12/3/2024 | Corrections Issued | JESUS PINEDA |
| Drywall Nailing | 12/7/2024 | Off-Hour Fees Due | |
| Drywall Nailing | 12/7/2024 | Partial Approval | CHRISTOPHER WILSON |
| Final | 12/7/2024 | Corrections Issued | CHRISTOPHER WILSON |
| Interior/Exterior Lathing | 12/12/2024 | Partial Approval | JESUS PINEDA |
| Special/Order Compliance | 12/12/2024 | Corrections Issued | JESUS PINEDA |
| Interior/Exterior Lathing | 12/17/2024 | Approved | REGINA MENDEZ |
| Shower Pan | 12/17/2024 | Approved | REGINA MENDEZ |
| Special/Order Compliance | 12/17/2024 | Partial Inspection | JAYLIN GRAVITTE |
| Drywall Nailing | 2/10/2025 | Corrections Issued | JESUS PINEDA |
| Drywall Nailing | 2/12/2025 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 3/10/2025 | Not Ready for Inspection | ARAM AVEDISIAN |
| ELECTRICAL-Final | 6/10/2025 | Conditional Approval | MICHAEL ALLEN |
| Final | 6/10/2025 | Corrections Issued | MICHAEL ALLEN |
| Green Building Final | 6/10/2025 | Conditional Approval | MICHAEL ALLEN |
| HVAC-Final | 6/10/2025 | Approved | MICHAEL ALLEN |
| PLUMBING-Final | 6/10/2025 | Approved | MICHAEL ALLEN |
| SGSOV-Seismic Gas S/O Valve | 6/10/2025 | SGSOV Not Ready | MICHAEL ALLEN |
| Smoke Detectors | 6/10/2025 | Corrections Issued | MICHAEL ALLEN |
| Final | 7/2/2025 | Corrections Issued | MICHAEL ALLEN |
| Green Building Final | 7/2/2025 | Conditional Approval | MICHAEL ALLEN |
| SGSOV-Seismic Gas S/O Valve | 7/2/2025 | SGSOV Approved | MICHAEL ALLEN |
| Smoke Detectors | 7/2/2025 | Approved | MICHAEL ALLEN |
| ELECTRICAL-Final | 7/23/2025 | Approved | WILBER ROSALES |
| Final | 7/23/2025 | Conditional Approval | WILBER ROSALES |
| Green Building Final | 7/23/2025 | Approved | WILBER ROSALES |