3499 S CABRILLO BLVD 90066

Certificate Information: 3499 S CABRILLO BLVD 90066

Application / Permit
24014-10000-01186
Plan Check / Job No.
B24LA05491
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN.TWO STORY ADDITION TO EXISTING SINGLE FAMILY DWELLING WITH ATTACHED GARAGE
Permit Issued
Issued on 6/12/2024
Issuing Office
Current Status
CofO Issued on 7/26/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/27/2024 APPLICANT
Assigned to Plan Check Engineer 3/28/2024 MARCELA FRANQUEZ
Corrections Issued 3/30/2024 MARCELA FRANQUEZ
Quality Review Completed 4/10/2024 TU HUA
Applicant returned to address corrections 5/14/2024 MARCELA FRANQUEZ
Plan Check Approved 5/30/2024 MARCELA FRANQUEZ
Issued 6/12/2024 APPLICANT
Permit Finaled 7/26/2025 RICHARD STEINBACH
Permit Finaled 7/26/2025 RICHARD STEINBACH
CofO Issued 7/26/2025 RICHARD STEINBACH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 4/5/2024 ANDREA SAINT-ANTONIN
Sewer availability Cleared 4/5/2024 ANDREA SAINT-ANTONIN
Grading Pre-Inspection Cleared 4/12/2024 VASIL MIHALEV
Low Impact Development (LID) Cleared 4/29/2024 SAMUEL LINN
Roof/Waste drainage to street Cleared 5/2/2024 ANDREA SAINT-ANTONIN
GPI Written Notices Cleared 5/30/2024 MARCELA FRANQUEZ

Contact Information

Architect Driscoll,, Christopher; Lic. No.: NA36073       ,
Contractor 1 Oak Remodeling; Lic. No.: 1015424-B 6320 VAN NUYS BLVD STE 305      VAN NUYS, CA 91401
Engineer Schwartz,, Eric; Lic. No.: NA81191       ,

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 6/28/2024 Conditional Approval RICHARD STEINBACH
Footing/Foundation/Slab 7/2/2024 Approved JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 7/11/2024 Partial Approval STEPHANIE SWANSON
Wood Frame 7/11/2024 Corrections Issued STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 7/19/2024 Partial Approval JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 8/14/2024 Corrections Issued JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 10/2/2024 Partial Approval JESUS PINEDA
Special/Order Compliance 10/2/2024 Corrections Issued JESUS PINEDA
Deputy Wood Construction 10/3/2024 Conditional Approval HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 10/4/2024 Corrections Issued JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 11/1/2024 Not Ready for Inspection JESUS PINEDA
HVAC-Rough 11/1/2024 Corrections Issued JESUS PINEDA
HVAC-Rough 11/5/2024 Not Ready for Inspection JESUS PINEDA
PLUMBING-Rough 11/5/2024 Corrections Issued JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 11/6/2024 Approved JESUS PINEDA
HVAC-Rough 11/6/2024 Not Ready for Inspection JESUS PINEDA
HVAC-Rough 11/7/2024 Corrections Issued JESUS PINEDA
PLUMBING-Rough 11/7/2024 Approved JESUS PINEDA
ELECTRICAL-Rough 11/12/2024 Corrections Issued ARAM AVEDISIAN
HVAC-Rough 11/12/2024 Approved ARAM AVEDISIAN
ELECTRICAL-Rough 11/13/2024 Corrections Issued JESUS PINEDA
ELECTRICAL-Rough 11/15/2024 Partial Approval MICHAEL ALLEN
Interior/Exterior Lathing 11/21/2024 Corrections Issued REGINA MENDEZ
ELECTRICAL-Rough 11/25/2024 Corrections Issued HERBERT GIRON
BUILDING-Rough-Frame 11/26/2024 Approved BOBBY KEY
ELECTRICAL-Rough 11/26/2024 Approved BOBBY KEY
Green Building Rough 11/26/2024 Approved BOBBY KEY
Insulation 11/26/2024 Approved BOBBY KEY
Interior/Exterior Lathing 11/26/2024 Not Ready for Inspection BOBBY KEY
Drywall Nailing 12/3/2024 Corrections Issued JESUS PINEDA
Drywall Nailing 12/7/2024 Off-Hour Fees Due
Drywall Nailing 12/7/2024 Partial Approval CHRISTOPHER WILSON
Final 12/7/2024 Corrections Issued CHRISTOPHER WILSON
Interior/Exterior Lathing 12/12/2024 Partial Approval JESUS PINEDA
Special/Order Compliance 12/12/2024 Corrections Issued JESUS PINEDA
Interior/Exterior Lathing 12/17/2024 Approved REGINA MENDEZ
Shower Pan 12/17/2024 Approved REGINA MENDEZ
Special/Order Compliance 12/17/2024 Partial Inspection JAYLIN GRAVITTE
Drywall Nailing 2/10/2025 Corrections Issued JESUS PINEDA
Drywall Nailing 2/12/2025 Approved JESUS PINEDA
Interior/Exterior Lathing 3/10/2025 Not Ready for Inspection ARAM AVEDISIAN
ELECTRICAL-Final 6/10/2025 Conditional Approval MICHAEL ALLEN
Final 6/10/2025 Corrections Issued MICHAEL ALLEN
Green Building Final 6/10/2025 Conditional Approval MICHAEL ALLEN
HVAC-Final 6/10/2025 Approved MICHAEL ALLEN
PLUMBING-Final 6/10/2025 Approved MICHAEL ALLEN
SGSOV-Seismic Gas S/O Valve 6/10/2025 SGSOV Not Ready MICHAEL ALLEN
Smoke Detectors 6/10/2025 Corrections Issued MICHAEL ALLEN
Final 7/2/2025 Corrections Issued MICHAEL ALLEN
Green Building Final 7/2/2025 Conditional Approval MICHAEL ALLEN
SGSOV-Seismic Gas S/O Valve 7/2/2025 SGSOV Approved MICHAEL ALLEN
Smoke Detectors 7/2/2025 Approved MICHAEL ALLEN
ELECTRICAL-Final 7/23/2025 Approved WILBER ROSALES
Final 7/23/2025 Conditional Approval WILBER ROSALES
Green Building Final 7/23/2025 Approved WILBER ROSALES