4882 N WIOTA ST 90041
Certificate Information: 4882 N WIOTA ST 90041
- Application / Permit
- 24014-10000-01183
- Plan Check / Job No.
- B24LA05467
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan: ADD 220 SF AND REMODEL TO EXISTING SFD. ADDITION OF ATTACHED WOOD DECK AT THE REAR.
- Permit Issued
- Issued on 7/24/2024
- Issuing Office
- Current Status
- CofO Issued on 9/13/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/28/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 4/11/2024 | CRYSTEL MAALOUF |
| Corrections Issued | 4/15/2024 | CRYSTEL MAALOUF |
| Quality Review Completed | 5/7/2024 | CAROLYNN NEPOMUCENO |
| Applicant returned to address corrections | 7/10/2024 | CRYSTEL MAALOUF |
| Plan Check Approved | 7/15/2024 | CRYSTEL MAALOUF |
| Issued | 7/24/2024 | APPLICANT |
| CofO in Progress | 9/11/2025 | LILIANA PORTILLO |
| Permit Finaled | 9/13/2025 | DEROLD HAUFF |
| CofO Issued | 9/13/2025 | DEROLD HAUFF |
| Permit Finaled | 9/13/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 5/13/2024 | MICHAEL TEMPLE |
| Roof/Waste drainage to street | Cleared | 5/14/2024 | AMBER CAMPBELL |
| Sewer availability | Cleared | 5/14/2024 | AMBER CAMPBELL |
| Eng Process Fee Ord 176,300 | Cleared | 5/16/2024 | AMBER CAMPBELL |
Contact Information
| Contractor | Gossett Construction Inc; Lic. No.: 880012-B | , |
| Engineer | Tuna,, Suleyman; Lic. No.: C73294 | 3332 BENNETT DRIVE LOS ANGELES, CA 90068 |
| Engineer | Tuna,, Suleyman; Lic. No.: NA73294 | , |
Inspector Information
| RONNIE MEDINA, (213) 469-5852 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/6/2024 | Not Ready for Inspection | CRAIG VAUGHAN |
| Pre-Inspection | 8/6/2024 | Approved | CRAIG VAUGHAN |
| Deputy Drilled-In Anchors | 8/23/2024 | Conditional Approval | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 8/26/2024 | Not Ready for Inspection | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 8/28/2024 | Approved | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/18/2024 | Approved | ROY SPAULDING |
| ELECTRICAL-Rough | 12/10/2024 | Approved | ROY SPAULDING |
| Floor/Roof Diaphrgm/Shear Wall | 12/10/2024 | Not Ready for Inspection | ROY SPAULDING |
| HVAC-Rough | 12/10/2024 | Corrections Issued | ROY SPAULDING |
| Interior/Exterior Lathing | 12/10/2024 | Not Ready for Inspection | ROY SPAULDING |
| PLUMBING-Rough | 12/10/2024 | Corrections Issued | ROY SPAULDING |
| ELECTRICAL-Rough | 12/13/2024 | Approved | ROY SPAULDING |
| Floor/Roof Diaphrgm/Shear Wall | 12/13/2024 | Partial Approval | ROY SPAULDING |
| HVAC-Rough | 12/13/2024 | Partial Approval | ROY SPAULDING |
| Interior/Exterior Lathing | 12/13/2024 | Partial Approval | ROY SPAULDING |
| PLUMBING-Rough | 12/13/2024 | Approved | ROY SPAULDING |
| BUILDING-Rough-Frame | 12/31/2024 | Approved | BRENDAN MORELLI |
| Green Building Rough | 12/31/2024 | Approved | BRENDAN MORELLI |
| HVAC-Rough | 12/31/2024 | Approved | BRENDAN MORELLI |
| Insulation | 1/14/2025 | Approved | ALEX COLIN |
| Drywall Nailing | 1/21/2025 | Approved | ALEX COLIN |
| Shower Pan | 3/4/2025 | Approved | DAVID WILLIAMS |
| Interior/Exterior Lathing | 3/11/2025 | Approved | JOSH MEISTER |
| Final | 6/18/2025 | Corrections Issued | DAVID WILLIAMS |
| Green Building Final | 6/18/2025 | Approved | DAVID WILLIAMS |
| SGSOV-Seismic Gas S/O Valve | 6/18/2025 | SGSOV Approved | DAVID WILLIAMS |
| Smoke Detectors | 6/18/2025 | Approved | DAVID WILLIAMS |
| Final | 9/10/2025 | OK to Issue CofO | LILIANA PORTILLO |