1409 E OPP ST 90744
Certificate Information: 1409 E OPP ST 90744
- Application / Permit
- 24014-10000-01175
- Plan Check / Job No.
- B24LA05429
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- GROUND FLOOR ADDITION OF LAUNDRY AREA (330 SF) TO (E) 2-CAR DETACHED GARAGE AND SECOND STORY ADU ADDITION PER LAMC 12.22A.33(c)-(d)
- Permit Issued
- Issued on 11/5/2024
- Issuing Office
- South Los Angeles
- Current Status
- Issued on 11/5/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/26/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 4/4/2024 | VIVIAN LAO |
| Corrections Issued | 4/11/2024 | VIVIAN LAO |
| Quality Review Completed | 4/12/2024 | KEN GILL |
| Building Plans Picked Up | 4/17/2024 | APPLICANT |
| Applicant returned to address corrections | 5/15/2024 | VIVIAN LAO |
| Applicant returned to address corrections | 8/19/2024 | VIVIAN LAO |
| Plan Check Approved | 10/30/2024 | VIVIAN LAO |
| Issued | 11/5/2024 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 5/21/2024 | KHAING AYE |
| Eng Process Fee Ord 176,300 | Cleared | 5/21/2024 | KHAING AYE |
| Roof/Waste drainage to street | Cleared | 5/21/2024 | KHAING AYE |
| Sewer availability | Cleared | 5/21/2024 | KHAING AYE |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| EUGENE CASSIDY, (310) 548-2508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 1/23/2025 | Partial Approval | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 1/24/2025 | Approved | JOSEPH MCGARRY |
| Excavation/Setback/Form/Re-Bar | 1/24/2025 | Corrections Issued | JOSEPH MCGARRY |
| METHANE-Barrier | 1/24/2025 | Approved | JOSEPH MCGARRY |
| METHANE-Subgrade | 1/24/2025 | Approved | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 2/19/2025 | Partial Approval | EUGENE CASSIDY |
| Footing/Foundation/Slab | 2/19/2025 | Conditional Approval | EUGENE CASSIDY |
| Order to Comply | 2/19/2025 | Not Required | EUGENE CASSIDY |
| Wood Frame | 2/19/2025 | Partial Approval | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 3/11/2025 | Corrections Issued | EUGENE CASSIDY |
| Green Building Rough | 3/11/2025 | No Access for Inspection | EUGENE CASSIDY |
| METHANE-Rough | 3/11/2025 | No Access for Inspection | EUGENE CASSIDY |
| PLUMBING-Rough | 3/11/2025 | Approved | EUGENE CASSIDY |
| Wood Frame | 3/11/2025 | Not Ready for Inspection | EUGENE CASSIDY |
| PLUMBING-Rough | 3/12/2025 | No Access for Inspection | EUGENE CASSIDY |
| Wood Frame | 3/12/2025 | No Access for Inspection | EUGENE CASSIDY |
| PLUMBING-Rough | 3/14/2025 | Corrections Issued | EUGENE CASSIDY |
| Wood Frame | 3/14/2025 | Partial Approval | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 3/18/2025 | Corrections Issued | EUGENE CASSIDY |
| Green Building Rough | 3/18/2025 | Not Ready for Inspection | EUGENE CASSIDY |
| METHANE-Rough | 3/18/2025 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 3/18/2025 | Approved | EUGENE CASSIDY |
| Wood Frame | 3/18/2025 | Partial Approval | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 5/9/2025 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Rough | 5/9/2025 | Approved | EUGENE CASSIDY |
| Green Building Rough | 5/9/2025 | Approved | EUGENE CASSIDY |
| HVAC-Rough | 5/9/2025 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 5/9/2025 | Partial Approval | EUGENE CASSIDY |
| Insulation | 5/29/2025 | Approved | EUGENE CASSIDY |
| Drywall Nailing | 7/16/2025 | Conditional Approval | JOSEPH MCGARRY |
| PLUMBING-Rough | 10/29/2025 | Partial Approval | EUGENE CASSIDY |
| Sewer | 10/29/2025 | Approved | EUGENE CASSIDY |
| Gas Test | 11/12/2025 | Partial Approval | JOSEPH MCGARRY |
| Shower Pan | 11/12/2025 | Approved | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 2/18/2026 | Not Ready for Inspection | EUGENE CASSIDY |
| Interior/Exterior Lathing | 2/18/2026 | Approved | EUGENE CASSIDY |