3411 S ROSEWOOD AVE 90066
Certificate Information: 3411 S ROSEWOOD AVE 90066
- Application / Permit
- 24014-10000-01174
- Plan Check / Job No.
- B24LA05424
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 17'-1" x 21'-10" ADDITION TO THE FRONT AND 10'-6" x 12'-0" ADDITION TO THE REAR OF (E) SFD. RE-ROOG GARAGE AND REPLACE THE (E) DOOR WITH A NEW DOOR. WORK DONE PER ENGINEER DESIGN.
- Permit Issued
- Issued on 6/26/2024
- Issuing Office
- Current Status
- CofO Issued on 4/21/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/3/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 4/8/2024 | MIROOSH KHACHATOORIAN |
| Corrections Issued | 4/9/2024 | MIROOSH KHACHATOORIAN |
| Applicant returned to address corrections | 5/7/2024 | MIROOSH KHACHATOORIAN |
| Plan Check Approved | 5/23/2024 | SARKIS HARABEDIAN |
| Issued | 6/26/2024 | APPLICANT |
| CofO in Progress | 4/8/2025 | MICHAEL ALLEN |
| Permit Finaled | 4/21/2025 | RICHARD STEINBACH |
| CofO Issued | 4/21/2025 | RICHARD STEINBACH |
| Permit Finaled | 4/21/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 4/15/2024 | ANTHONY MAINEZ |
| Roof/Waste drainage to street | Cleared | 4/15/2024 | ANTHONY MAINEZ |
| Grading Pre-Inspection | Cleared | 5/7/2024 | MIROOSH KHACHATOORIAN |
| Specific Plan | Cleared | 5/20/2024 | PEDRO AYALA |
Contact Information
| Contractor | Vitoli Builders Inc; Lic. No.: 1043914-B | , |
| Engineer | Phillips,, Craig; Lic. No.: C69673 | 2123 VESTAL AVE LOS ANGELES, CA 90026 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/23/2024 | Corrections Issued | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 7/29/2024 | Corrections Issued | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 8/6/2024 | Partial Approval | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 8/6/2024 | Approved | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 8/27/2024 | Approved | JESUS PINEDA |
| ELECTRICAL-Rough | 10/17/2024 | Not Ready for Inspection | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 10/17/2024 | Corrections Issued | JESUS PINEDA |
| Interior/Exterior Lathing | 10/25/2024 | Corrections Issued | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 10/28/2024 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 10/28/2024 | Partial Approval | JESUS PINEDA |
| BUILDING-Rough-Frame | 10/29/2024 | Approved | JESUS PINEDA |
| ELECTRICAL-Rough | 10/29/2024 | Approved | JESUS PINEDA |
| HVAC-Rough | 10/29/2024 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 10/29/2024 | Approved | JESUS PINEDA |
| HVAC-Rough | 11/5/2024 | Approved | JESUS PINEDA |
| Insulation | 11/5/2024 | Approved | JESUS PINEDA |
| Drywall Nailing | 11/18/2024 | Approved | BOBBY KEY |
| Final | 3/7/2025 | Corrections Issued | JESUS PINEDA |
| SGSOV-Seismic Gas S/O Valve | 3/7/2025 | SGSOV Not Ready | JESUS PINEDA |
| Smoke Detectors | 3/7/2025 | Not Ready for Inspection | JESUS PINEDA |
| ELECTRICAL-Final | 4/2/2025 | Approved | MICHAEL ALLEN |
| Final | 4/2/2025 | Corrections Issued | MICHAEL ALLEN |
| HVAC-Final | 4/2/2025 | Approved | MICHAEL ALLEN |
| PLUMBING-Final | 4/2/2025 | Approved | MICHAEL ALLEN |
| SGSOV-Seismic Gas S/O Valve | 4/2/2025 | SGSOV Approved | MICHAEL ALLEN |
| Smoke Detectors | 4/2/2025 | Approved | MICHAEL ALLEN |
| Final | 4/7/2025 | OK to Issue CofO | MICHAEL ALLEN |