4823 S 5TH AVE 90043

Certificate Information: 4823 S 5TH AVE 90043

Application / Permit
24014-10000-01170
Plan Check / Job No.
B24LA05408
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Eplan: Ground Floor Addition to an (E) 2-Story SFD
Permit Issued
Issued on 6/26/2024
Issuing Office
Current Status
CofO Issued on 5/7/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/26/2024 APPLICANT
Assigned to Plan Check Engineer 3/29/2024 DAVID CASTILLO
Corrections Issued 3/30/2024 DAVID CASTILLO
Applicant returned to address corrections 5/30/2024 DAVID CASTILLO
Applicant returned to address corrections 6/12/2024 DAVID CASTILLO
Plan Check Approved 6/20/2024 DAVID CASTILLO
Issued 6/26/2024 APPLICANT
CofO in Progress 5/5/2025 LUIS CASTRO
CofO Issued 5/7/2025 DEROLD HAUFF
Permit Finaled 5/7/2025 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 5/31/2024 JESSICA OPINION
Eng Process Fee Ord 176,300 Cleared 6/4/2024 WALLIE JONG
Sewer availability Cleared 6/4/2024 WALLIE JONG

Contact Information

Contractor Rickmc Construction; Lic. No.: 494953-B       ,
Engineer Cao,, Thuan; Lic. No.: C78305 17404 MADRONE ST      FONTANA, CA 92337

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 9/10/2024 Conditional Approval ANTHONY EGSON
Footing/Foundation/Slab 9/16/2024 Corrections Issued ANTHONY EGSON
Sewer 9/16/2024 Corrections Issued ANTHONY EGSON
Footing/Foundation/Slab 9/27/2024 Approved ANTHONY EGSON
Sewer 9/27/2024 Approved ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 11/18/2024 Partial Approval MICHAEL LEWIS
BUILDING-Rough-Frame 1/14/2025 Not Ready for Inspection LUIS CASTRO
ELECTRICAL-Rough 1/14/2025 Approved LUIS CASTRO
Green Building Rough 1/14/2025 Not Ready for Inspection LUIS CASTRO
HVAC-Rough 1/14/2025 Approved LUIS CASTRO
Interior/Exterior Lathing 1/14/2025 Partial Approval LUIS CASTRO
PLUMBING-Rough 1/14/2025 Corrections Issued LUIS CASTRO
BUILDING-Rough-Frame 1/16/2025 Approved LUIS CASTRO
Green Building Rough 1/16/2025 Approved LUIS CASTRO
PLUMBING-Rough 1/16/2025 Partial Approval LUIS CASTRO
Floor/Roof Diaphrgm/Shear Wall 2/4/2025 Approved LUIS CASTRO
Insulation 2/4/2025 Approved LUIS CASTRO
PLUMBING-Rough 2/4/2025 Approved LUIS CASTRO
Drywall Nailing 2/28/2025 Approved LUIS CASTRO
Interior/Exterior Lathing 2/28/2025 Approved LUIS CASTRO
ELECTRICAL-Final 4/17/2025 Approved LUIS CASTRO
Final 4/17/2025 Corrections Issued LUIS CASTRO
Green Building Final 4/17/2025 Corrections Issued LUIS CASTRO
HVAC-Final 4/17/2025 Approved LUIS CASTRO
PLUMBING-Final 4/17/2025 Approved LUIS CASTRO
SGSOV-Seismic Gas S/O Valve 4/17/2025 SGSOV Approved LUIS CASTRO
Smoke Detectors 4/17/2025 Approved LUIS CASTRO
Final 5/2/2025 OK to Issue CofO LUIS CASTRO
Green Building Final 5/2/2025 Approved LUIS CASTRO