4823 S 5TH AVE 90043
Certificate Information: 4823 S 5TH AVE 90043
- Application / Permit
- 24014-10000-01170
- Plan Check / Job No.
- B24LA05408
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Eplan: Ground Floor Addition to an (E) 2-Story SFD
- Permit Issued
- Issued on 6/26/2024
- Issuing Office
- Current Status
- CofO Issued on 5/7/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/26/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 3/29/2024 | DAVID CASTILLO |
| Corrections Issued | 3/30/2024 | DAVID CASTILLO |
| Applicant returned to address corrections | 5/30/2024 | DAVID CASTILLO |
| Applicant returned to address corrections | 6/12/2024 | DAVID CASTILLO |
| Plan Check Approved | 6/20/2024 | DAVID CASTILLO |
| Issued | 6/26/2024 | APPLICANT |
| CofO in Progress | 5/5/2025 | LUIS CASTRO |
| CofO Issued | 5/7/2025 | DEROLD HAUFF |
| Permit Finaled | 5/7/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 5/31/2024 | JESSICA OPINION |
| Eng Process Fee Ord 176,300 | Cleared | 6/4/2024 | WALLIE JONG |
| Sewer availability | Cleared | 6/4/2024 | WALLIE JONG |
Contact Information
| Contractor | Rickmc Construction; Lic. No.: 494953-B | , |
| Engineer | Cao,, Thuan; Lic. No.: C78305 | 17404 MADRONE ST FONTANA, CA 92337 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 9/10/2024 | Conditional Approval | ANTHONY EGSON |
| Footing/Foundation/Slab | 9/16/2024 | Corrections Issued | ANTHONY EGSON |
| Sewer | 9/16/2024 | Corrections Issued | ANTHONY EGSON |
| Footing/Foundation/Slab | 9/27/2024 | Approved | ANTHONY EGSON |
| Sewer | 9/27/2024 | Approved | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 11/18/2024 | Partial Approval | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 1/14/2025 | Not Ready for Inspection | LUIS CASTRO |
| ELECTRICAL-Rough | 1/14/2025 | Approved | LUIS CASTRO |
| Green Building Rough | 1/14/2025 | Not Ready for Inspection | LUIS CASTRO |
| HVAC-Rough | 1/14/2025 | Approved | LUIS CASTRO |
| Interior/Exterior Lathing | 1/14/2025 | Partial Approval | LUIS CASTRO |
| PLUMBING-Rough | 1/14/2025 | Corrections Issued | LUIS CASTRO |
| BUILDING-Rough-Frame | 1/16/2025 | Approved | LUIS CASTRO |
| Green Building Rough | 1/16/2025 | Approved | LUIS CASTRO |
| PLUMBING-Rough | 1/16/2025 | Partial Approval | LUIS CASTRO |
| Floor/Roof Diaphrgm/Shear Wall | 2/4/2025 | Approved | LUIS CASTRO |
| Insulation | 2/4/2025 | Approved | LUIS CASTRO |
| PLUMBING-Rough | 2/4/2025 | Approved | LUIS CASTRO |
| Drywall Nailing | 2/28/2025 | Approved | LUIS CASTRO |
| Interior/Exterior Lathing | 2/28/2025 | Approved | LUIS CASTRO |
| ELECTRICAL-Final | 4/17/2025 | Approved | LUIS CASTRO |
| Final | 4/17/2025 | Corrections Issued | LUIS CASTRO |
| Green Building Final | 4/17/2025 | Corrections Issued | LUIS CASTRO |
| HVAC-Final | 4/17/2025 | Approved | LUIS CASTRO |
| PLUMBING-Final | 4/17/2025 | Approved | LUIS CASTRO |
| SGSOV-Seismic Gas S/O Valve | 4/17/2025 | SGSOV Approved | LUIS CASTRO |
| Smoke Detectors | 4/17/2025 | Approved | LUIS CASTRO |
| Final | 5/2/2025 | OK to Issue CofO | LUIS CASTRO |
| Green Building Final | 5/2/2025 | Approved | LUIS CASTRO |