3750 N AMESBURY ROAD 90027
Certificate Information: 3750 N AMESBURY ROAD 90027
- Application / Permit
- 24014-10000-01162
- Plan Check / Job No.
- B24LA05362
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN: NEW TWO STORY (551sqft) ADDITION TO (E) TWO STORY SINGLE FAMILY DWELLING NEW(691 sqft) UNCOVERED DECK ATTACHED TO (E) SFD (AT REAR OF PROPERTY)
- Permit Issued
- Issued on 6/6/2024
- Issuing Office
- Current Status
- Issued on 6/6/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/3/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 4/4/2024 | JAD BASMA |
| Corrections Issued | 4/9/2024 | JAD BASMA |
| Quality Review Completed | 4/18/2024 | GARO TELMI |
| Applicant returned to address corrections | 5/31/2024 | JAD BASMA |
| Plan Check Approved | 6/6/2024 | JAD BASMA |
| Issued | 6/6/2024 | APPLICANT |
Permit Application Clearance Information
| Low Impact Development (LID) | Cleared | 4/19/2024 | MARTIN FRAGOSO |
| BHO/Hillside ordinance | Cleared | 4/23/2024 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 4/25/2024 | CELINA MORENO |
| Roof/Waste drainage to street | Cleared | 4/25/2024 | CELINA MORENO |
| Sewer availability | Cleared | 4/25/2024 | CELINA MORENO |
| BHO/Hillside ordinance | Cleared | 5/2/2024 | CELINA MORENO |
| BHO/Hillside ordinance | Cleared | 5/2/2024 | CELINA MORENO |
| BHO/Hillside ordinance | Cleared | 5/2/2024 | CELINA MORENO |
| BHO/Hillside ordinance | Cleared | 5/2/2024 | CELINA MORENO |
| Hydrant and Access approval | Cleared | 5/17/2024 | MATTHEW CRAIG |
| Excavation more than 5-ft deep | Cleared | 5/31/2024 | CALOSHA APPROVED |
| GPI Written Notices | Cleared | 5/31/2024 | JAD BASMA |
| Grading Pre-Inspection | Cleared | 5/31/2024 | JAD BASMA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Adzhemyan,, Arsen; Lic. No.: NA89103 | , |
Inspector Information
| ENRIQUE MIRELES, (213) 202-3438 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| Final | 6/5/2026 Time Frame: 11-1 |
Inspection Request History
| Pre-Inspection | 6/17/2024 | Approved | ENRIQUE MIRELES |
| Deputy Drilled-In Anchors | 7/29/2024 | Conditional Approval | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 8/13/2024 | Corrections Issued | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 8/14/2024 | Approved | ENRIQUE MIRELES |
| Deputy Reinf. Concrete | 8/15/2024 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 10/15/2024 | Partial Approval | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 10/15/2024 | Not Ready for Inspection | ENRIQUE MIRELES |
| Green Building Rough | 10/15/2024 | Not Ready for Inspection | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 11/27/2024 | Corrections Issued | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 11/27/2024 | Not Ready for Inspection | ENRIQUE MIRELES |
| Green Building Rough | 11/27/2024 | Not Ready for Inspection | ENRIQUE MIRELES |
| PLUMBING-Rough | 11/27/2024 | Not Ready for Inspection | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 12/6/2024 | Not Ready for Inspection | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 12/6/2024 | Approved | ENRIQUE MIRELES |
| Green Building Rough | 12/6/2024 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 12/6/2024 | Not Ready for Inspection | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 12/9/2024 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 12/9/2024 | Approved | ENRIQUE MIRELES |
| Insulation | 12/16/2024 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 1/22/2025 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 1/22/2025 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Final | 1/22/2025 | Not Ready for Inspection | ENRIQUE MIRELES |
| PLUMBING-Final | 1/22/2025 | Not Ready for Inspection | ENRIQUE MIRELES |
| Drywall Nailing | 1/24/2025 | Corrections Issued | RONNIE MINDANAO |
| Interior/Exterior Lathing | 1/28/2025 | Not Ready for Inspection | JOSH MEISTER |
| Interior/Exterior Lathing | 1/29/2025 | Corrections Issued | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 1/31/2025 | Not Ready for Inspection | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 2/3/2025 | Not Ready for Inspection | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 2/4/2025 | Approved | ENRIQUE MIRELES |
| Final | 5/30/2025 | Corrections Issued | ENRIQUE MIRELES |
| Green Building Final | 5/30/2025 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 5/30/2025 | SGSOV Approved | ENRIQUE MIRELES |
| Smoke Detectors | 5/30/2025 | Approved | ENRIQUE MIRELES |
| Final | 8/15/2025 | Not Ready for Inspection | ENRIQUE MIRELES |