1110 N AVENUE 52 90042
Certificate Information: 1110 N AVENUE 52 90042
- Application / Permit
- 24014-10000-01158
- Plan Check / Job No.
- B24LA05353
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan:CONVERT EXISTING DETACHED STORAGE ROOM AND CARPORT TO DETACHED TWO STORY ADU PER LAMC 12.22 A.33(c) AND (d)
- Permit Issued
- Issued on 2/5/2026
- Issuing Office
- Current Status
- Issued on 2/5/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/29/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 4/11/2024 | CRYSTEL MAALOUF |
| Corrections Issued | 4/15/2024 | CRYSTEL MAALOUF |
| Quality Review Completed | 5/7/2024 | CAROLYNN NEPOMUCENO |
| Applicant returned to address corrections | 2/12/2025 | CRYSTEL MAALOUF |
| Applicant returned to address corrections | 8/11/2025 | CRYSTEL MAALOUF |
| Plan Check Approved | 8/21/2025 | CRYSTEL MAALOUF |
| Issued | 2/5/2026 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 9/25/2024 | WALLIE JONG |
| Roof/Waste drainage to street | Cleared | 9/25/2024 | WALLIE JONG |
| Sewer availability | Cleared | 9/25/2024 | WALLIE JONG |
| Grading Pre-Inspection | Cleared | 9/25/2024 | MICHAEL TEMPLE |
| Eng Process Fee Ord 176,300 | Cleared | 9/30/2024 | WALLIE JONG |
| Construction near power lines | Cleared | 11/5/2024 | RIDWAN HARDY |
| Miscellaneous | Cleared | 11/26/2024 | ALBERT TAM |
| GPI Written Notices | Cleared | 8/21/2025 | RUSSELL BONVOULOIR |
Contact Information
| Contractor | Src Builders Inc; Lic. No.: 1084946-B | , |
| Engineer | Basma,, Ali J; Lic. No.: C53080 | 5140 YOLANDA AVE TARZANA, CA 91356 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/20/2026 | Partial Approval | RONNIE MEDINA |
| Pre-Inspection | 3/20/2026 | Approved | RONNIE MEDINA |
| Underground Mechanical | 3/20/2026 | Approved | RONNIE MEDINA |
| Excavation/Setback/Form/Re-Bar | 3/26/2026 | Approved | RONNIE MEDINA |
| Footing/Foundation/Slab | 3/26/2026 | Approved | RONNIE MEDINA |
| Floor/Roof Diaphrgm/Shear Wall | 4/28/2026 | Partial Approval | LILIANA PORTILLO |
| ELECTRICAL-Rough | 6/23/2026 | Corrections Issued | RONNIE MEDINA |
| Floor/Roof Diaphrgm/Shear Wall | 6/23/2026 | Partial Approval | RONNIE MEDINA |
| Gas Test | 6/23/2026 | Approved | RONNIE MEDINA |
| HVAC-Rough | 6/23/2026 | Not Ready for Inspection | RONNIE MEDINA |
| PLUMBING-Rough | 6/23/2026 | Approved | RONNIE MEDINA |
| Shower Pan | 6/23/2026 | Not Ready for Inspection | RONNIE MEDINA |
| Underground Mechanical | 6/23/2026 | Approved | RONNIE MEDINA |