2214 S BURNSIDE AVE 90016
Certificate Information: 2214 S BURNSIDE AVE 90016
- Application / Permit
- 24014-10000-01156
- Plan Check / Job No.
- B24LA05341
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERTING OF EXISTING DETACHED GARAGE (220 SF) AND ADDITION (220 SF) INTO ACCESSORY DWELLING UNIT (440 SF) . Work per Engineered Design .
- Permit Issued
- Issued on 6/18/2024
- Issuing Office
- Metro
- Current Status
- CofO Issued on 4/1/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/26/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 3/28/2024 | MINA HABILI |
| Corrections Issued | 3/29/2024 | MINA HABILI |
| Building Plans Picked Up | 4/4/2024 | APPLICANT |
| Applicant returned to address corrections | 5/2/2024 | LAWRENCE QUIRANTE |
| Plan Check Approved | 5/8/2024 | GEORGE ALVAREZ |
| Issued | 6/18/2024 | APPLICANT |
| CofO in Progress | 3/28/2025 | ARTHUR NEGRETE |
| Permit Finaled | 4/1/2025 | DEROLD HAUFF |
| Permit Finaled | 4/1/2025 | DEROLD HAUFF |
| CofO Issued | 4/1/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 4/11/2024 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 4/11/2024 | WALLIE JONG |
| Roof/Waste drainage to street | Cleared | 4/11/2024 | WALLIE JONG |
| Sewer availability | Cleared | 4/11/2024 | WALLIE JONG |
| Disturb/Remove Protected Trees | Cleared | 5/2/2024 | ADALBERTO VERA |
Contact Information
| Contractor | Jc Builders & Renovation Inc; Lic. No.: 1091494-B | 19384 KITTRIDGE STREET RESEDA, CA 91335 |
| Engineer | Salto,, Alvaro; Lic. No.: C83859 | 2543 E NORMAN AVE WEST COVINA, CA 91791 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/19/2024 | Approved | ARTHUR NEGRETE |
| Sewer | 7/19/2024 | Approved | ARTHUR NEGRETE |
| Rough-Elec/Plmb/HVAC | 7/23/2024 | Approved | ARTHUR NEGRETE |
| Deputy Drilled-In Anchors | 8/6/2024 | No Result Entered | RICHARD DOCKUS |
| Footing/Foundation/Slab | 8/16/2024 | Approved | ARTHUR NEGRETE |
| Floor/Roof Diaphrgm/Shear Wall | 10/1/2024 | Not Ready for Inspection | RONNIE MINDANAO |
| Wood Frame | 10/1/2024 | Corrections Issued | RONNIE MINDANAO |
| Interior/Exterior Lathing | 10/2/2024 | Not Ready for Inspection | ARTHUR NEGRETE |
| Wood Frame | 10/2/2024 | Approved | ARTHUR NEGRETE |
| ELECTRICAL-Rough | 10/11/2024 | Approved | ARTHUR NEGRETE |
| Gas Test | 10/11/2024 | Not Ready for Inspection | ARTHUR NEGRETE |
| Green Building Rough | 10/11/2024 | Approved | ARTHUR NEGRETE |
| HVAC-Rough | 10/11/2024 | Approved | ARTHUR NEGRETE |
| PLUMBING-Rough | 10/11/2024 | Approved | ARTHUR NEGRETE |
| Rough-Elec/Plmb/HVAC | 10/11/2024 | Approved | ARTHUR NEGRETE |
| Shower Pan | 10/11/2024 | Not Ready for Inspection | ARTHUR NEGRETE |
| ELECTRICAL-Rough | 10/15/2024 | Approved | ARTHUR NEGRETE |
| Gas Test | 10/15/2024 | Not Ready for Inspection | ARTHUR NEGRETE |
| HVAC-Rough | 10/15/2024 | Approved | ARTHUR NEGRETE |
| PLUMBING-Rough | 10/15/2024 | Approved | ARTHUR NEGRETE |
| Rough-Elec/Plmb/HVAC | 10/15/2024 | Approved | ARTHUR NEGRETE |
| Shower Pan | 10/15/2024 | Approved | ARTHUR NEGRETE |
| Gas Test | 10/22/2024 | Approved | JOSE MACIAS |
| Interior/Exterior Lathing | 10/22/2024 | Corrections Issued | JOSE MACIAS |
| Drywall Nailing | 10/24/2024 | Approved | ARTHUR NEGRETE |
| Interior/Exterior Lathing | 10/25/2024 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 12/12/2024 | Approved | ENRIQUE MIRELES |
| Final | 12/12/2024 | Corrections Issued | ENRIQUE MIRELES |
| Green Building Final | 12/12/2024 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 12/12/2024 | SGSOV Approved | ENRIQUE MIRELES |
| Smoke Detectors | 12/12/2024 | Approved | ENRIQUE MIRELES |
| Green Building Final | 12/23/2024 | Approved | ARTHUR NEGRETE |
| ELECTRICAL-Final | 12/24/2024 | Approved | ARTHUR NEGRETE |
| HVAC-Final | 12/24/2024 | Approved | ARTHUR NEGRETE |
| PLUMBING-Final | 12/24/2024 | Approved | ARTHUR NEGRETE |
| Final | 3/7/2025 | Partial Inspection | ARTHUR NEGRETE |
| Final | 3/12/2025 | Partial Inspection | ARTHUR NEGRETE |
| Special/Order Compliance | 3/12/2025 | Partial Inspection | ALEX COLIN |
| Final | 3/27/2025 | OK to Issue CofO | ARTHUR NEGRETE |