16548 W HAYNES ST 91406

Certificate Information: 16548 W HAYNES ST 91406

Application / Permit
24014-10000-01147
Plan Check / Job No.
B24LA05268
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION TO REAR OF HOUSE, ADD NEW PRIMARY BEDROOM, PRIMARY BATHROOM, LAUNDRY ROOM, FAMILY ROOM, AND REMODEL KITCHEN. NFPA 13D FIRE SPRINKLER SYSTEM IS REQUIRED.
Permit Issued
Issued on 7/18/2025
Issuing Office
Valley
Current Status
CofO in Progress on 3/5/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/22/2024 APPLICANT
Assigned to Plan Check Engineer 3/28/2024 NGHI SU
Corrections Issued 3/30/2024 NGHI SU
Building Plans Picked Up 4/8/2024 APPLICANT
Applicant returned to address corrections 7/17/2024 NGHI SU
Plan Check Approved 8/6/2024 ALEXANDER JOO
Issued 7/18/2025 APPLICANT
CofO in Progress 3/5/2026 KIRK SANDERS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 5/20/2024 BIAINA HARITUNIAN
ZI Cleared 5/21/2024 MATHEW QUAN
Low Impact Development (LID) Cleared 7/9/2024 LUIS LUVANO
Roof/Waste drainage to street Cleared 7/15/2024 BIAINA HARITUNIAN

Contact Information

Contractor M J W Construction & Remodeling; Lic. No.: 698247-B 16540 HAYNES STREET      VAN NUYS, CA 91406
Engineer Zhong,, Raymond Meng; Lic. No.: M27635 2416 W VALLEY BLVD      ALHAMBRA, CA 91803
Engineer Zhuang,, Wenbin; Lic. No.: S5236 205 S CHAPEL AVE #D-1      ALHAMBRA, CA 91801

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 8/4/2025 Conditional Approval JOAQUIN GREENOUGH
Footing/Foundation/Slab 8/6/2025 Approved DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 8/20/2025 Partial Approval GAREN HAYRAPETYAN
PLUMBING-Rough 8/20/2025 Partial Approval GAREN HAYRAPETYAN
Floor/Roof Diaphrgm/Shear Wall 8/25/2025 Partial Approval WILLIAM WREN
Green Building Rough 8/25/2025 Not Ready for Inspection WILLIAM WREN
Deputy Wood Construction 9/15/2025 Conditional Approval JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 9/24/2025 Partial Approval GAREN HAYRAPETYAN
Green Building Rough 9/24/2025 Not Ready for Inspection GAREN HAYRAPETYAN
PLUMBING-Rough 9/30/2025 Corrections Issued GAREN HAYRAPETYAN
HVAC-Rough 10/21/2025 Approved GAREN HAYRAPETYAN
PLUMBING-Rough 10/21/2025 Approved GAREN HAYRAPETYAN
ELECTRICAL-Rough 11/3/2025 Approved GAREN HAYRAPETYAN
Insulation 11/3/2025 Partial Approval GAREN HAYRAPETYAN
BUILDING-Rough-Frame 11/12/2025 Approved GAREN HAYRAPETYAN
Green Building Rough 11/12/2025 Approved GAREN HAYRAPETYAN
Interior/Exterior Lathing 11/12/2025 Partial Approval GAREN HAYRAPETYAN
Insulation 11/17/2025 Approved GAREN HAYRAPETYAN
Drywall Nailing 11/20/2025 Approved ROBERTO PALACIOS-LOPEZ
Shower Pan 12/9/2025 Approved MICHAEL CORTEZ
Interior/Exterior Lathing 12/11/2025 Approved LOUIS ESCOTO
ELECTRICAL-Final 2/12/2026 Approved GAREN HAYRAPETYAN
PLUMBING-Final 2/12/2026 Corrections Issued GAREN HAYRAPETYAN
HVAC-Final 2/18/2026 Approved GAREN HAYRAPETYAN
Final 2/26/2026 Corrections Issued GAREN HAYRAPETYAN
Green Building Final 2/26/2026 Approved GAREN HAYRAPETYAN
SGSOV-Seismic Gas S/O Valve 2/26/2026 SGSOV Approved GAREN HAYRAPETYAN
Smoke Detectors 2/26/2026 Approved GAREN HAYRAPETYAN
Final 3/4/2026 OK to Issue CofO KIRK SANDERS
Service/Power Release 3/4/2026 Approved KIRK SANDERS