10503 W TENNESSEE AVE 90064
Certificate Information: 10503 W TENNESSEE AVE 90064
- Application / Permit
- 24014-10000-01083
- Plan Check / Job No.
- B24LA04965
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan: Addition to existing S.F.D.
- Permit Issued
- Issued on 7/17/2024
- Issuing Office
- Current Status
- CofO Issued on 6/11/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/21/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 3/28/2024 | CAROLEAN BASMA |
| Corrections Issued | 3/29/2024 | CAROLEAN BASMA |
| Applicant returned to address corrections | 7/4/2024 | CAROLEAN BASMA |
| Plan Check Approved | 7/14/2024 | CAROLEAN BASMA |
| Issued | 7/17/2024 | APPLICANT |
| CofO in Progress | 5/30/2025 | DANIEL VERA |
| Permit Finaled | 6/11/2025 | RICHARD STEINBACH |
| CofO Issued | 6/11/2025 | RICHARD STEINBACH |
| Permit Finaled | 6/11/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| ZA Case | Cleared | 5/28/2024 | YINGSHI HUANG |
| Specific Plan | Cleared | 6/4/2024 | FREDDY GARCIA |
| Eng Process Fee Ord 176,300 | Cleared | 6/27/2024 | BRENDEN HAWK |
| Roof/Waste drainage to street | Cleared | 7/2/2024 | BRENDEN HAWK |
| Grading Pre-Inspection | Cleared | 7/5/2024 | CAROLEAN BASMA |
Contact Information
| Contractor | Martinko Construction Inc; Lic. No.: 990964-B | , |
| Engineer | Soleymani,, Habib; Lic. No.: S2575 | 1917 PARNELL AVE LOS ANGELES, CA 90025 |
Inspector Information
| DAVID SCANTLIN, (310) 914-3863 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/7/2025 | Not Ready for Inspection | STEPHANIE SWANSON |
| Pre-Inspection | 1/7/2025 | Partial Inspection | STEPHANIE SWANSON |
| Deputy Drilled-In Anchors | 1/14/2025 | Conditional Approval | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 1/15/2025 | Approved | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 2/3/2025 | Partial Approval | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 2/12/2025 | Corrections Issued | KIRK SANDERS |
| Underground Mechanical | 2/12/2025 | Approved | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 2/19/2025 | Approved | STEPHANIE SWANSON |
| PLUMBING-Rough | 2/19/2025 | Approved | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 2/28/2025 | Approved | STEPHANIE SWANSON |
| HVAC-Rough | 2/28/2025 | Corrections Issued | STEPHANIE SWANSON |
| HVAC-Rough | 3/11/2025 | Approved | DANIEL VERA |
| Interior/Exterior Lathing | 3/11/2025 | Partial Approval | DANIEL VERA |
| Insulation | 3/12/2025 | Approved | DANIEL VERA |
| Drywall Nailing | 3/14/2025 | Approved | DANIEL VERA |
| Shower Pan | 3/21/2025 | Approved | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 3/24/2025 | Approved | DANIEL VERA |
| BUILDING-Rough-Frame | 4/22/2025 | Approved | DANIEL VERA |
| ELECTRICAL-Final | 4/22/2025 | Approved | DANIEL VERA |
| Final | 4/22/2025 | Corrections Issued | DANIEL VERA |
| HVAC-Final | 4/22/2025 | Corrections Issued | DANIEL VERA |
| PLUMBING-Final | 4/22/2025 | Approved | DANIEL VERA |
| SGSOV-Seismic Gas S/O Valve | 4/22/2025 | SGSOV Approved | DANIEL VERA |
| Smoke Detectors | 4/22/2025 | Approved | DANIEL VERA |
| Final | 5/29/2025 | OK to Issue CofO | DANIEL VERA |
| HVAC-Final | 5/29/2025 | Approved | DANIEL VERA |