5260-5260 1/2 E CONEY ROAD 90032
Certificate Information: 5260-5260 1/2 E CONEY ROAD 90032
- Application / Permit
- 24014-10000-01058
- Plan Check / Job No.
- B24LA04862
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Convert storage attatched to (E) 3-story single family dwelling to JADU per State Law R3/U occupancy
- Permit Issued
- Issued on 8/6/2024
- Issuing Office
- Metro
- Current Status
- CofO Issued on 9/5/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/15/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 3/21/2024 | ALEXANDER JOO |
| Corrections Issued | 3/25/2024 | ALEXANDER JOO |
| Building Plans Picked Up | 3/27/2024 | APPLICANT |
| Applicant returned to address corrections | 6/7/2024 | NGHI SU |
| Plan Check Approved | 7/10/2024 | KELVIN CHUONG |
| Issued | 8/6/2024 | APPLICANT |
| CofO in Progress | 9/4/2025 | LILIANA PORTILLO |
| Permit Finaled | 9/5/2025 | DEROLD HAUFF |
| CofO Issued | 9/5/2025 | DEROLD HAUFF |
| Permit Finaled | 9/5/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 5/4/2024 | CELINA MORENO |
| Sewer availability | Cleared | 5/4/2024 | CELINA MORENO |
| "D" conditions | Cleared | 5/14/2024 | RUBEN VASQUEZ |
| "Q" conditions | Cleared | 5/14/2024 | RUBEN VASQUEZ |
| Eng Process Fee Ord 176,300 | Cleared | 6/7/2024 | CELINA MORENO |
| Hold | Cleared | 9/24/2024 | MARIA VENDIVIL |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Bartelle,, Kristofer Grimm; Lic. No.: C84617 | 22910 BURBANK BLVD WOODLAND HILLS, CA 91367 |
| Engineer | Zhong,, Raymond Meng; Lic. No.: M27635 | 2416 W VALLEY BLVD ALHAMBRA, CA 91803 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 9/26/2024 | Partial Approval | BRENDAN MORELLI |
| Pre-Inspection | 9/26/2024 | Partial Inspection | BRENDAN MORELLI |
| Excavation/Setback/Form/Re-Bar | 10/18/2024 | Approved | LILIANA PORTILLO |
| Deputy Drilled-In Anchors | 1/7/2025 | Conditional Approval | JOSH MEISTER |
| Wood Frame | 1/15/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| ELECTRICAL-Rough | 2/18/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| HVAC-Rough | 2/18/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| PLUMBING-Rough | 2/18/2025 | Corrections Issued | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 2/28/2025 | Conditional Approval | LILIANA PORTILLO |
| ELECTRICAL-Rough | 2/28/2025 | Approved | LILIANA PORTILLO |
| HVAC-Rough | 2/28/2025 | Approved | LILIANA PORTILLO |
| PLUMBING-Rough | 2/28/2025 | Approved | LILIANA PORTILLO |
| Insulation | 3/12/2025 | Corrections Issued | LILIANA PORTILLO |
| Drywall Nailing | 5/12/2025 | Approved | REGINA MENDEZ |
| Interior/Exterior Lathing | 5/12/2025 | Approved | REGINA MENDEZ |
| Shower Pan | 5/12/2025 | Approved | REGINA MENDEZ |
| BUILDING-Rough-Frame | 8/21/2025 | Approved | LILIANA PORTILLO |
| Final | 8/21/2025 | Corrections Issued | LILIANA PORTILLO |
| Footing/Foundation/Slab | 8/21/2025 | Approved | LILIANA PORTILLO |
| Green Building Final | 8/21/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| Green Building Rough | 8/21/2025 | Approved | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 8/21/2025 | SGSOV Approved | LILIANA PORTILLO |
| Smoke Detectors | 8/21/2025 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Final | 8/29/2025 | Approved | LILIANA PORTILLO |
| Final | 8/29/2025 | OK to Issue CofO | LILIANA PORTILLO |
| Green Building Final | 8/29/2025 | Approved | LILIANA PORTILLO |
| HVAC-Final | 8/29/2025 | Approved | LILIANA PORTILLO |
| PLUMBING-Final | 8/29/2025 | Approved | LILIANA PORTILLO |