439 W 109TH ST 90061
Certificate Information: 439 W 109TH ST 90061
- Application / Permit
- 24014-10000-01055
- Plan Check / Job No.
- B24LA04848
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN: PROPOSED ADDITION AT REAR OF (E) SFD, ALL WORK PER ENG.
- Permit Issued
- Issued on 11/19/2024
- Issuing Office
- Current Status
- CofO Issued on 8/28/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/20/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 3/21/2024 | SERGIO MUNIZ |
| Corrections Issued | 3/21/2024 | SERGIO MUNIZ |
| Applicant returned to address corrections | 9/12/2024 | LUISANGEL VALENZUELA |
| Plan Check Approved | 10/3/2024 | LUISANGEL VALENZUELA |
| Issued | 11/19/2024 | APPLICANT |
| CofO in Progress | 8/27/2025 | BEN MOLSTAD |
| Permit Finaled | 8/28/2025 | ANSON MAGLASANG |
| CofO Issued | 8/28/2025 | ANSON MAGLASANG |
| Permit Finaled | 8/28/2025 | ANSON MAGLASANG |
Permit Application Clearance Information
| Low Impact Development (LID) | Cleared | 9/9/2024 | ERNEST TSE |
| Eng Process Fee Ord 176,300 | Cleared | 9/11/2024 | JESSICA OPINION |
| Roof/Waste drainage to street | Cleared | 9/11/2024 | JESSICA OPINION |
| Sewer availability | Cleared | 9/11/2024 | JESSICA OPINION |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Hoerner,, John Brent; Lic. No.: S2145 | 24024 VIA CANDELA VALENCIA, CA 91355 |
Inspector Information
| BEN MOLSTAD, (310) 732-4557 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/8/2025 | Corrections Issued | BEN MOLSTAD |
| Footing/Foundation/Slab | 1/10/2025 | Partial Approval | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 1/16/2025 | Partial Approval | BEN MOLSTAD |
| BUILDING-Rough-Frame | 1/28/2025 | Corrections Issued | BEN MOLSTAD |
| Green Building Rough | 1/28/2025 | Approved | BEN MOLSTAD |
| MERV13>=Rough | 1/28/2025 | Approved | BEN MOLSTAD |
| Wood Frame | 1/28/2025 | Not Ready for Inspection | BEN MOLSTAD |
| BUILDING-Rough-Frame | 1/30/2025 | Approved | BEN MOLSTAD |
| ELECTRICAL-Rough | 1/30/2025 | Approved | BEN MOLSTAD |
| Wood Frame | 1/30/2025 | Approved | BEN MOLSTAD |
| Drywall Nailing | 2/10/2025 | Corrections Issued | BEN MOLSTAD |
| Floor/Roof Diaphrgm/Shear Wall | 2/20/2025 | Approved | BEN MOLSTAD |
| Drywall Nailing | 2/25/2025 | Approved | BEN MOLSTAD |
| Final | 4/1/2025 | Corrections Issued | BEN MOLSTAD |
| Footing/Foundation/Slab | 4/1/2025 | Approved | BEN MOLSTAD |
| Green Building Final | 4/1/2025 | Not Ready for Inspection | BEN MOLSTAD |
| MERV13>=Final | 4/1/2025 | Approved | BEN MOLSTAD |
| SGSOV-Seismic Gas S/O Valve | 4/1/2025 | SGSOV Not Ready | BEN MOLSTAD |
| Smoke Detectors | 4/1/2025 | Corrections Issued | BEN MOLSTAD |
| Final | 4/22/2025 | Corrections Issued | BEN MOLSTAD |
| Green Building Final | 4/22/2025 | Approved | BEN MOLSTAD |
| SGSOV-Seismic Gas S/O Valve | 4/22/2025 | SGSOV Approved | BEN MOLSTAD |
| Smoke Detectors | 4/22/2025 | Approved | BEN MOLSTAD |
| ELECTRICAL-Final | 8/27/2025 | Approved | BEN MOLSTAD |
| Final | 8/27/2025 | OK to Issue CofO | BEN MOLSTAD |
| HVAC-Final | 8/27/2025 | Approved | BEN MOLSTAD |
| PLUMBING-Final | 8/27/2025 | Approved | BEN MOLSTAD |