1740 W 38TH PL 90062

Certificate Information: 1740 W 38TH PL 90062

Application / Permit
24014-10000-01051
Plan Check / Job No.
B24LA04828
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
PROPOSED 12' X 16' GARAGE CONVERSION WITH 294 SF ADDITION INTO ADU PER ORDINANCE.
Permit Issued
Issued on 5/13/2024
Issuing Office
Metro
Current Status
CofO Issued on 12/10/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/15/2024 APPLICANT
Assigned to Plan Check Engineer 3/18/2024 LAWRENCE QUIRANTE
Corrections Issued 3/20/2024 LAWRENCE QUIRANTE
Building Plans Picked Up 3/28/2024 APPLICANT
Plan Check Approved 5/1/2024 HUAN LE
Issued 5/13/2024 APPLICANT
CofO in Progress 12/2/2024 SABAS ALONSO
Permit Finaled 12/10/2024 DEROLD HAUFF
CofO Issued 12/10/2024 DEROLD HAUFF
Permit Finaled 12/10/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 4/1/2024 CELINA MORENO
Roof/Waste drainage to street Cleared 4/1/2024 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 4/3/2024 CELINA MORENO
Sewer availability Cleared 4/3/2024 CELINA MORENO

Contact Information

Contractor Owner-Builder       ,
Engineer Vo,, Tung Thanh; Lic. No.: C69546 11122 BIXLER CIRCLE      GARDEN GROVE, CA 92840

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/14/2024 Approved SABAS ALONSO
Footing/Foundation/Slab 6/14/2024 Approved SABAS ALONSO
Underground Mechanical 6/14/2024 Partial Approval SABAS ALONSO
Deputy Drilled-In Anchors 6/17/2024 Conditional Approval SABAS ALONSO
BUILDING-Rough-Frame 7/25/2024 Not Ready for Inspection SABAS ALONSO
ELECTRICAL-Rough 7/25/2024 Not Ready for Inspection SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 7/25/2024 Corrections Issued SABAS ALONSO
Green Building Rough 7/25/2024 Partial Approval SABAS ALONSO
HVAC-Rough 7/25/2024 Not Ready for Inspection SABAS ALONSO
PLUMBING-Rough 7/25/2024 Corrections Issued SABAS ALONSO
Sewer 7/25/2024 Corrections Issued SABAS ALONSO
BUILDING-Rough-Frame 8/2/2024 Not Ready for Inspection SABAS ALONSO
ELECTRICAL-Rough 8/2/2024 Approved SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 8/2/2024 Approved SABAS ALONSO
Green Building Rough 8/2/2024 Corrections Issued SABAS ALONSO
PLUMBING-Rough 8/2/2024 Approved SABAS ALONSO
Sewer 8/2/2024 Approved SABAS ALONSO
Interior/Exterior Lathing 8/14/2024 Corrections Issued CRAIG DAVIS
BUILDING-Rough-Frame 8/15/2024 Approved CRAIG DAVIS
Green Building Rough 8/15/2024 Approved CRAIG DAVIS
HVAC-Rough 8/15/2024 Approved CRAIG DAVIS
Insulation 8/20/2024 Approved CRAIG DAVIS
Drywall Nailing 8/30/2024 Corrections Issued ALEX COLIN
Interior/Exterior Lathing 8/30/2024 Approved ALEX COLIN
Drywall Nailing 9/4/2024 Approved SABAS ALONSO
ELECTRICAL-Final 10/28/2024 Not Ready for Inspection SABAS ALONSO
Final 10/28/2024 Corrections Issued SABAS ALONSO
Green Building Final 10/28/2024 Approved SABAS ALONSO
PLUMBING-Final 10/28/2024 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 10/28/2024 SGSOV Not Ready SABAS ALONSO
Smoke Detectors 10/28/2024 Approved SABAS ALONSO
ELECTRICAL-Final 10/30/2024 Corrections Issued SABAS ALONSO
PLUMBING-Final 10/30/2024 Approved SABAS ALONSO
ELECTRICAL-Final 11/26/2024 Approved SABAS ALONSO
Final 11/26/2024 OK to Issue CofO SABAS ALONSO
PLUMBING-Final 11/26/2024 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 11/26/2024 SGSOV Approved SABAS ALONSO