3628 S 10TH AVE 90018
Certificate Information: 3628 S 10TH AVE 90018
- Application / Permit
- 24014-10000-01025
- Plan Check / Job No.
- B24LA04675
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 12'-4" X 20'-1" ADDITION TO EXISTING SINGLE FAMILY DWELLING - PER ENGINEER *** "COMPLY WITH DEPARTMENT ORDER effective date 03/07/2019. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
- Permit Issued
- Issued on 5/20/2024
- Issuing Office
- Current Status
- CofO Issued on 2/26/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/14/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 3/19/2024 | DANIEL ABRAMYAN |
| Corrections Issued | 3/20/2024 | DANIEL ABRAMYAN |
| Applicant returned to address corrections | 4/16/2024 | ISIS ARGUETA |
| Applicant returned to address corrections | 4/24/2024 | KAMYAR EMAMI |
| Plan Check Approved | 4/27/2024 | GIOVANNY CHAVEZ |
| Issued | 5/20/2024 | APPLICANT |
| Permit Finaled | 2/26/2025 | CLAUDIO MORENO |
| CofO Issued | 2/26/2025 | CLAUDIO MORENO |
| Permit Finaled | 2/26/2025 | CLAUDIO MORENO |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 4/17/2024 | ADRIAN SANCHEZ |
| Sewer availability | Cleared | 4/17/2024 | ADRIAN SANCHEZ |
| Eng Process Fee Ord 176,300 | Cleared | 4/20/2024 | ADRIAN SANCHEZ |
Contact Information
| Contractor | Green Design Home Services Inc; Lic. No.: 1020792-B | 12400 VENTURA BLVD UNIT 725 STUDIO CITY, CA 91604 |
| Engineer | Shahbaz,, Shant Pierre; Lic. No.: C93079 | 15445 VENTURA BLVD #63 SHERMAN OAKS, CA 91403 |
Inspector Information
| LUIS CORRAL, (213) 252-3964 | Office Hours: 7:00-8:00 AM MON-FRI |
| DONALD WONG, (213) 252-3964 | Office Hours: 7:00-8:00 AM MON-FRI |
| KIM DOEPPING, (213) 252-3964 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM MICHALAK, (213) 252-3964 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/3/2024 | Corrections Issued | ENRIQUE PREZA |
| Deputy Drilled-In Anchors | 7/24/2024 | Partial Approval | ENRIQUE PREZA |
| Footing/Foundation/Slab | 7/24/2024 | Approved | ENRIQUE PREZA |
| Wood Frame | 7/29/2024 | Corrections Issued | WILLIAM MICHALAK |
| Wood Frame | 7/30/2024 | Partial Approval | WILLIAM MICHALAK |
| Floor/Roof Diaphrgm/Shear Wall | 7/31/2024 | Partial Approval | WILLIAM MICHALAK |
| Floor/Roof Diaphrgm/Shear Wall | 8/7/2024 | Not Ready for Inspection | WILLIAM MICHALAK |
| Floor/Roof Diaphrgm/Shear Wall | 8/15/2024 | Approved | WILLIAM MICHALAK |
| Shower Pan | 9/3/2024 | Approved | WILLIAM MICHALAK |
| Interior/Exterior Lathing | 9/5/2024 | Approved | WILLIAM MICHALAK |
| ELECTRICAL-Rough | 9/18/2024 | Corrections Issued | WILLIAM MICHALAK |
| PLUMBING-Rough | 9/18/2024 | Approved | WILLIAM MICHALAK |
| ELECTRICAL-Rough | 10/9/2024 | Approved | WILLIAM MICHALAK |
| Interior/Exterior Lathing | 10/29/2024 | Approved | WILLIAM MICHALAK |
| Insulation | 11/21/2024 | Partial Approval | WILLIAM MICHALAK |
| Drywall Nailing | 12/20/2024 | Corrections Issued | WILLIAM MICHALAK |
| Green Building Rough | 12/20/2024 | Corrections Issued | WILLIAM MICHALAK |
| BUILDING-Rough-Frame | 1/7/2025 | Approved | LUIS CORRAL |
| Drywall Nailing | 1/7/2025 | Corrections Issued | LUIS CORRAL |
| Final | 1/7/2025 | Not Ready for Inspection | LUIS CORRAL |
| Green Building Final | 1/7/2025 | Not Ready for Inspection | LUIS CORRAL |
| Green Building Rough | 1/7/2025 | Approved | LUIS CORRAL |
| SGSOV-Seismic Gas S/O Valve | 1/7/2025 | SGSOV Approved | LUIS CORRAL |
| Smoke Detectors | 1/7/2025 | Approved | LUIS CORRAL |
| Drywall Nailing | 1/28/2025 | Approved | LUIS CORRAL |
| Final | 1/28/2025 | Conditional Approval | LUIS CORRAL |
| Green Building Final | 1/28/2025 | Approved | LUIS CORRAL |