6456 W 84TH PL 90045
Certificate Information: 6456 W 84TH PL 90045
- Application / Permit
- 24014-10000-01024
- Plan Check / Job No.
- B24LA04669
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan: Remodel and addition to existing single family dwelling.
- Permit Issued
- Issued on 8/26/2024
- Issuing Office
- Current Status
- CofO Issued on 12/30/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/15/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 3/20/2024 | CAROLEAN BASMA |
| Corrections Issued | 3/20/2024 | CAROLEAN BASMA |
| Applicant returned to address corrections | 5/1/2024 | CAROLEAN BASMA |
| Plan Check Approved | 5/6/2024 | CAROLEAN BASMA |
| Issued | 8/26/2024 | APPLICANT |
| CofO in Progress | 12/23/2025 | ANTHONY EGSON |
| Permit Finaled | 12/30/2025 | RICHARD STEINBACH |
| CofO Issued | 12/30/2025 | RICHARD STEINBACH |
| Permit Finaled | 12/30/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 4/11/2024 | HISASHI KOBAYAKAWA |
| Eng Process Fee Ord 176,300 | Cleared | 4/15/2024 | HISASHI KOBAYAKAWA |
| Specific Plan | Cleared | 4/22/2024 | EDUARDO HERMOSO |
Contact Information
| Contractor | Pacific Design Build Llc; Lic. No.: 1067229-B | , |
| Engineer | Minn,, Wenchung; Lic. No.: C42605 | 3358 W 157TH ST GARDENA, CA 90249 |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/10/2025 | Corrections Issued | EVAN COOPER |
| Footing/Foundation/Slab | 2/20/2025 | Approved | MICHAEL ALLEN |
| Gas Test | 3/4/2025 | Approved | MICHAEL ALLEN |
| HVAC-Rough | 3/4/2025 | Partial Approval | MICHAEL ALLEN |
| PLUMBING-Rough | 3/4/2025 | Approved | MICHAEL ALLEN |
| ELECTRICAL-Rough | 3/5/2025 | Corrections Issued | MICHAEL ALLEN |
| Special/Order Compliance | 3/5/2025 | Partial Approval | RUBEN RIVAS |
| ELECTRICAL-Rough | 3/13/2025 | Approved | RUBEN RIVAS |
| Special/Order Compliance | 3/13/2025 | Partial Inspection | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 3/14/2025 | Not Ready for Inspection | RUBEN RIVAS |
| Special/Order Compliance | 3/14/2025 | Partial Inspection | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 3/18/2025 | Corrections Issued | RUBEN RIVAS |
| Special/Order Compliance | 3/18/2025 | Corrections Issued | BOBBY KEY |
| Deputy Wood Construction | 3/19/2025 | Conditional Approval | DAVID FEILER |
| BUILDING-Rough-Frame | 3/20/2025 | Partial Approval | RUBEN RIVAS |
| Floor/Roof Diaphrgm/Shear Wall | 3/20/2025 | Approved | RUBEN RIVAS |
| Green Building Rough | 3/20/2025 | Not Ready for Inspection | RUBEN RIVAS |
| Special/Order Compliance | 3/20/2025 | Partial Inspection | TEMISTOCLES CAAL |
| BUILDING-Rough-Frame | 3/25/2025 | Corrections Issued | RUBEN RIVAS |
| Floor/Roof Diaphrgm/Shear Wall | 3/25/2025 | Corrections Issued | RUBEN RIVAS |
| Green Building Rough | 3/25/2025 | Not Ready for Inspection | RUBEN RIVAS |
| BUILDING-Rough-Frame | 3/27/2025 | Not Ready for Inspection | RUBEN RIVAS |
| Floor/Roof Diaphrgm/Shear Wall | 3/27/2025 | Partial Approval | RUBEN RIVAS |
| Shower Pan | 3/27/2025 | Approved | RUBEN RIVAS |
| Special/Order Compliance | 3/27/2025 | Partial Inspection | TEMISTOCLES CAAL |
| Interior/Exterior Lathing | 4/23/2025 | Partial Approval | RUBEN RIVAS |
| Insulation | 4/24/2025 | Approved | RUBEN RIVAS |
| Interior/Exterior Lathing | 4/30/2025 | Approved | RUBEN RIVAS |
| Drywall Nailing | 5/8/2025 | Approved | RUBEN RIVAS |
| Green Building Rough | 5/8/2025 | Approved | RUBEN RIVAS |
| HVAC-Rough | 8/28/2025 | Corrections Issued | RUBEN RIVAS |
| ELECTRICAL-Final | 9/29/2025 | Approved | RUBEN RIVAS |
| HVAC-Final | 9/29/2025 | Approved | RUBEN RIVAS |
| ELECTRICAL-Final | 10/3/2025 | Corrections Issued | RUBEN RIVAS |
| HVAC-Final | 10/3/2025 | Approved | RUBEN RIVAS |
| BUILDING-Rough-Frame | 11/10/2025 | Approved | RUBEN RIVAS |
| Final | 11/10/2025 | Corrections Issued | RUBEN RIVAS |
| Green Building Final | 11/10/2025 | Approved | RUBEN RIVAS |
| SGSOV-Seismic Gas S/O Valve | 11/10/2025 | SGSOV Approved | RUBEN RIVAS |
| Smoke Detectors | 11/10/2025 | Approved | RUBEN RIVAS |
| Final | 12/15/2025 | No Access for Inspection | ANTHONY EGSON |
| Final | 12/22/2025 | OK to Issue CofO | ANTHONY EGSON |
| PLUMBING-Final | 12/22/2025 | Approved | ANTHONY EGSON |