1940 W 78TH PL 90047
Certificate Information: 1940 W 78TH PL 90047
- Application / Permit
- 24014-10000-00957
- Plan Check / Job No.
- B24LA04339
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADDITION OF ADU ATTACHED TO EXISTING ONE STORY GARAGE W/ NEW PORCH PER LAMC 12.22 A.33 (c)-(d). (E) GARAGE TO REMAIN.
- Permit Issued
- Issued on 4/30/2024
- Issuing Office
- Current Status
- CofO Issued on 4/19/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/8/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 3/13/2024 | SERGIO MUNIZ |
| Corrections Issued | 3/14/2024 | SERGIO MUNIZ |
| Plan Check Approved | 4/27/2024 | SERGIO MUNIZ |
| Issued | 4/30/2024 | APPLICANT |
| CofO in Progress | 4/14/2025 | WAYNE REGESTER |
| Permit Finaled | 4/19/2025 | DEROLD HAUFF |
| CofO Issued | 4/19/2025 | DEROLD HAUFF |
| Permit Finaled | 4/19/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 3/20/2024 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 3/20/2024 | CELINA MORENO |
| Sewer availability | Cleared | 3/20/2024 | CELINA MORENO |
| Low Impact Development (LID) | Cleared | 4/24/2024 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 4/25/2024 | CELINA MORENO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Gonzalez,, Felix Bolivar; Lic. No.: NA64738 | , |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 7/10/2024 | Approved | JOSE MACIAS |
| Footing/Foundation/Slab | 7/15/2024 | Conditional Approval | JOSE MACIAS |
| BUILDING-Rough-Frame | 7/30/2024 | Corrections Issued | JOSE MACIAS |
| Green Building Rough | 7/30/2024 | Not Ready for Inspection | JOSE MACIAS |
| Deputy Wood Construction | 8/8/2024 | Conditional Approval | JOSE MACIAS |
| BUILDING-Rough-Frame | 8/27/2024 | Corrections Issued | JOSE MACIAS |
| ELECTRICAL-Rough | 8/27/2024 | Approved | JOSE MACIAS |
| Green Building Rough | 8/27/2024 | Not Ready for Inspection | JOSE MACIAS |
| HVAC-Rough | 8/27/2024 | Approved | JOSE MACIAS |
| PLUMBING-Rough | 8/27/2024 | Approved | JOSE MACIAS |
| BUILDING-Rough-Frame | 9/19/2024 | Approved | AMIR NAZARIAN |
| ELECTRICAL-Rough | 9/19/2024 | Conditional Approval | AMIR NAZARIAN |
| Green Building Rough | 9/19/2024 | Approved | AMIR NAZARIAN |
| Interior/Exterior Lathing | 9/19/2024 | Partial Approval | AMIR NAZARIAN |
| ELECTRICAL-Rough | 9/23/2024 | Approved | AMIR NAZARIAN |
| HVAC-Rough | 9/23/2024 | Approved | AMIR NAZARIAN |
| PLUMBING-Rough | 9/23/2024 | Approved | AMIR NAZARIAN |
| Insulation | 10/1/2024 | Approved | ALEX COLIN |
| Drywall Nailing | 10/15/2024 | Approved | ALEX COLIN |
| ELECTRICAL-Final | 1/17/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 1/17/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Gas Test | 1/17/2025 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Final | 1/17/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 1/17/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 2/7/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 2/7/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 2/7/2025 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 2/7/2025 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 2/25/2025 | Approved | MICHAEL LEWIS |
| Final | 4/11/2025 | OK to Issue CofO | WAYNE REGESTER |
| Footing/Foundation/Slab | 4/11/2025 | Approved | WAYNE REGESTER |
| Green Building Final | 4/11/2025 | Approved | WAYNE REGESTER |
| SGSOV-Seismic Gas S/O Valve | 4/11/2025 | SGSOV Approved | WAYNE REGESTER |
| Smoke Detectors | 4/11/2025 | Approved | WAYNE REGESTER |