3927 S ALBRIGHT AVE 90066

Certificate Information: 3927 S ALBRIGHT AVE 90066

Application / Permit
24014-10000-00951
Plan Check / Job No.
B24LA04329
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan. SINGLE STORY ADDITION (438 SF) TO EXISTING SINGLE FAMILY DWELLING, ADD NEW DECK AT REAR- ALL WORK PER WFPP
Permit Issued
Issued on 8/9/2025
Issuing Office
Current Status
Issued on 8/9/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/11/2024 APPLICANT
Assigned to Plan Check Engineer 3/15/2024 SERGIO MUNIZ
Corrections Issued 3/18/2024 SERGIO MUNIZ
Applicant returned to address corrections 4/18/2024 SERGIO MUNIZ
Applicant returned to address corrections 5/29/2024 SERGIO MUNIZ
Applicant returned to address corrections 6/3/2024 SERGIO MUNIZ
Applicant returned to address corrections 7/2/2024 SERGIO MUNIZ
Applicant returned to address corrections 7/12/2024 SERGIO MUNIZ
Applicant returned to address corrections 7/19/2024 MINA HABILI
Applicant returned to address corrections 7/23/2024 NEHEMIAS RAMOS
Applicant returned to address corrections 7/25/2024 NEHEMIAS RAMOS
Applicant returned to address corrections 8/6/2024 NEHEMIAS RAMOS
Plan Check Approved 9/4/2024 DANIEL SMILEY
Issued 8/9/2025 APPLICANT

Permit Application Clearance Information

Sewer availability Cleared 4/24/2024 DARIN LAM
Roof/Waste drainage to street Cleared 5/1/2024 DARIN LAM
Eng Process Fee Ord 176,300 Cleared 5/2/2024 DARIN LAM
Specific Plan Cleared 5/21/2024 FREDDY GARCIA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/29/2025 Approved WILBER ROSALES
Floor/Roof Diaphrgm/Shear Wall 10/6/2025 Corrections Issued RUBEN RIVAS
Insulation 10/6/2025 Partial Approval RUBEN RIVAS
Underground Mechanical 10/6/2025 Partial Approval RUBEN RIVAS
Floor/Roof Diaphrgm/Shear Wall 10/8/2025 Partial Approval MICHAEL ALLEN
Green Building Rough 10/8/2025 Not Ready for Inspection MICHAEL ALLEN
Floor/Roof Diaphrgm/Shear Wall 10/17/2025 Approved WILBER ROSALES
Green Building Rough 10/17/2025 Not Ready for Inspection WILBER ROSALES
BUILDING-Rough-Frame 10/28/2025 Partial Approval WILBER ROSALES
ELECTRICAL-Rough 10/28/2025 Approved WILBER ROSALES
Green Building Rough 10/28/2025 Not Ready for Inspection WILBER ROSALES
HVAC-Rough 10/28/2025 Approved WILBER ROSALES
PLUMBING-Rough 10/28/2025 Approved WILBER ROSALES
BUILDING-Rough-Frame 11/10/2025 Approved WILBER ROSALES
Green Building Rough 11/10/2025 Approved WILBER ROSALES
Insulation 11/10/2025 Approved WILBER ROSALES
Interior/Exterior Lathing 11/10/2025 Partial Approval WILBER ROSALES
Drywall Nailing 11/14/2025 Approved WILBER ROSALES
Interior/Exterior Lathing 11/25/2025 Approved WILBER ROSALES
Shower Pan 11/25/2025 Approved WILBER ROSALES
ELECTRICAL-Final 1/7/2026 Approved WILBER ROSALES
Final 1/7/2026 Corrections Issued WILBER ROSALES
HVAC-Final 1/7/2026 Approved WILBER ROSALES
PLUMBING-Final 1/7/2026 Approved WILBER ROSALES
Pre-Inspection 2/24/2026 Partial Inspection DAKOTA LOW