2259-2261 N WESTRIDGE ROAD 90049
Certificate Information: 2259-2261 N WESTRIDGE ROAD 90049
- Application / Permit
- 24014-10000-00948
- Plan Check / Job No.
- B24LA04322
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan: ADDITION AND MAJOR REMODEL TO (E) SINGLE FAMILY DWELLING W/ ATT GARAGE. 2ND STORY ADU ADDITION. ATTACHED ADU PER LAMC 12.22.33 (c) and (e). TO BE EQUIPPED WITH FIRE SPRINKLERS NFPA 13D THROUGH OUT.
- Permit Issued
- Issued on 10/11/2024
- Issuing Office
- Current Status
- CofO Issued on 6/26/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/8/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 3/14/2024 | ADRIANA LOPEZ |
| Corrections Issued | 3/19/2024 | ADRIANA LOPEZ |
| Quality Review Completed | 4/5/2024 | CAROLYNN NEPOMUCENO |
| Applicant returned to address corrections | 8/7/2024 | ADRIANA LOPEZ |
| Plan Check Approved | 10/10/2024 | ADRIANA LOPEZ |
| Issued | 10/11/2024 | APPLICANT |
| CofO in Progress | 6/25/2026 | KEVIN SARGSYAN |
| Permit Finaled | 6/26/2026 | RICHARD STEINBACH |
| CofO Issued | 6/26/2026 | RICHARD STEINBACH |
| Permit Finaled | 6/26/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 4/7/2024 | BRENDEN HAWK |
| BHO/Hillside ordinance | Cleared | 4/7/2024 | BRENDEN HAWK |
| BHO/Hillside ordinance | Cleared | 4/7/2024 | BRENDEN HAWK |
| BHO/Hillside ordinance | Cleared | 4/7/2024 | BRENDEN HAWK |
| BHO/Hillside ordinance | Cleared | 4/7/2024 | BRENDEN HAWK |
| BHO/Hillside ordinance | Cleared | 4/7/2024 | BRENDEN HAWK |
| Miscellaneous | Cleared | 4/10/2024 | DARIN LAM |
| Eng Process Fee Ord 176,300 | Cleared | 4/11/2024 | BRENDEN HAWK |
| Sewer availability | Cleared | 4/11/2024 | BRENDEN HAWK |
| Grading Pre-Inspection | Cleared | 4/22/2024 | VASIL MIHALEV |
| Hydrant and Access approval | Cleared | 5/4/2024 | KURT CORRAL |
| Low Impact Development (LID) | Cleared | 9/23/2024 | ERNEST TSE |
| Roof/Waste drainage to street | Cleared | 9/29/2024 | LIAM ODONOVAN |
| GPI Written Notices | Cleared | 10/10/2024 | ADRIANA LOPEZ |
Contact Information
| Contractor | Liebobuilders; Lic. No.: 1054050-B | , |
| Engineer | Mixter,, Thomas J; Lic. No.: C51041 | 2345 COUNTY RD 630 DEL RIO, TX 78840 |
| Engineer | Zahn,, Michael; Lic. No.: NA5054 | , |
Inspector Information
| KEVIN SARGSYAN, (310) 914-3889 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 11/27/2024 | Conditional Approval | KEVIN SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 11/27/2024 | Corrections Issued | KEVIN SARGSYAN |
| Underground Mechanical | 11/27/2024 | Corrections Issued | KEVIN SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 2/21/2025 | Approved | EVAN COOPER |
| PLUMBING-Rough | 2/21/2025 | Partial Approval | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 4/2/2025 | Corrections Issued | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/7/2025 | Partial Approval | KEVIN SARGSYAN |
| Deputy Steel/Welding | 4/9/2025 | Conditional Approval | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/11/2025 | No Access for Inspection | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/12/2025 | Partial Approval | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 7/9/2025 | Corrections Issued | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/9/2025 | Approved | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 7/10/2025 | Approved | KEVIN SARGSYAN |
| PLUMBING-Rough | 7/10/2025 | Partial Approval | KEVIN SARGSYAN |
| HVAC-Rough | 7/22/2025 | Corrections Issued | KEVIN SARGSYAN |
| HVAC-Rough | 7/29/2025 | Approved | KEVIN SARGSYAN |
| PLUMBING-Rough | 7/29/2025 | Partial Approval | KEVIN SARGSYAN |
| Shower Pan | 7/29/2025 | Approved | KEVIN SARGSYAN |
| Drywall Nailing | 8/5/2025 | Partial Approval | KEVIN SARGSYAN |
| PLUMBING-Rough | 8/5/2025 | Partial Approval | KEVIN SARGSYAN |
| Drywall Nailing | 8/7/2025 | Partial Approval | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 8/12/2025 | Corrections Issued | KEVIN SARGSYAN |
| Green Building Rough | 8/12/2025 | Approved | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 8/12/2025 | Partial Approval | KEVIN SARGSYAN |
| Verify Sprinkler Sign Off | 8/12/2025 | Approved | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 8/21/2025 | Partial Approval | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 8/25/2025 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Rough | 8/25/2025 | Approved | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 8/26/2025 | Approved | KEVIN SARGSYAN |
| Insulation | 9/2/2025 | Approved | MEL KHACHATOURIAN |
| Drywall Nailing | 9/15/2025 | Approved | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 12/24/2025 | No Access for Inspection | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 1/13/2026 | Approved | KEVIN SARGSYAN |
| ELECTRICAL-Final | 5/26/2026 | Approved | KEVIN SARGSYAN |
| HVAC-Final | 5/26/2026 | Approved | KEVIN SARGSYAN |
| PLUMBING-Final | 5/26/2026 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Final | 5/29/2026 | Approved | DAVID SCANTLIN |
| Final | 6/17/2026 | Corrections Issued | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 6/17/2026 | Approved | KEVIN SARGSYAN |
| Green Building Final | 6/17/2026 | Approved | KEVIN SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 6/17/2026 | SGSOV Approved | KEVIN SARGSYAN |
| Smoke Detectors | 6/17/2026 | Approved | KEVIN SARGSYAN |
| Final | 6/25/2026 | OK to Issue CofO | KEVIN SARGSYAN |