639 S JUNE ST 90005
Certificate Information: 639 S JUNE ST 90005
- Application / Permit
- 24014-10000-00945
- Plan Check / Job No.
- B24LA04315
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN: NEW 15'-10" x 13'-7" ADDITION TO (E) SFD. WORK DONE PER ENGINEER DESING.
- Permit Issued
- Issued on 6/23/2024
- Issuing Office
- Current Status
- CofO Issued on 9/27/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/8/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 3/13/2024 | MIROOSH KHACHATOORIAN |
| Corrections Issued | 3/14/2024 | MIROOSH KHACHATOORIAN |
| Applicant returned to address corrections | 4/4/2024 | MIROOSH KHACHATOORIAN |
| Applicant returned to address corrections | 4/18/2024 | MOHAMMAD ESMAILI |
| Applicant returned to address corrections | 5/16/2024 | MOHAMMAD ESMAILI |
| Plan Check Approved | 5/29/2024 | PINANK PATEL |
| Issued | 6/23/2024 | APPLICANT |
| CofO in Progress | 9/23/2025 | RONNIE MINDANAO |
| Permit Finaled | 9/27/2025 | DEROLD HAUFF |
| CofO Issued | 9/27/2025 | DEROLD HAUFF |
| Permit Finaled | 9/27/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 4/3/2024 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 4/4/2024 | TREVOR QUAN |
| CPC | Cleared | 4/18/2024 | SPENCER WEJROWSKI |
| CPC | Cleared | 4/18/2024 | SPENCER WEJROWSKI |
| HPOZ | Cleared | 5/14/2024 | SUKI GERSHENHORN |
| Specific Plan | Cleared | 5/16/2024 | MIROOSH KHACHATOORIAN |
Contact Information
| Architect | Smalley,, Jeffrey Marc; Lic. No.: C19163 | , |
| Contractor | Bulson & Company Inc; Lic. No.: 980611-B | , |
| Contractor | Capegray; Lic. No.: 980611-B | , |
| Engineer | Mina,, Joseph; Lic. No.: C53465 | , |
Inspector Information
| RONNIE MINDANAO, (213) 202-3252 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/19/2024 | Partial Inspection | RONNIE MINDANAO |
| Excavation/Setback/Form/Re-Bar | 11/25/2024 | Partial Approval | RONNIE MINDANAO |
| Excavation/Setback/Form/Re-Bar | 3/4/2025 | Partial Approval | RONNIE MINDANAO |
| Footing/Foundation/Slab | 3/4/2025 | Partial Approval | RONNIE MINDANAO |
| METHANE-Barrier | 3/4/2025 | Approved | RONNIE MINDANAO |
| METHANE-Subgrade | 3/4/2025 | Approved | RONNIE MINDANAO |
| Footing/Foundation/Slab | 3/24/2025 | Approved | RONNIE MINDANAO |
| BUILDING-Rough-Frame | 5/6/2025 | Corrections Issued | RONNIE MINDANAO |
| METHANE-Rough | 5/6/2025 | Approved | RONNIE MINDANAO |
| Floor/Roof Diaphrgm/Shear Wall | 5/8/2025 | Corrections Issued | RONNIE MINDANAO |
| ELECTRICAL-Rough | 6/6/2025 | Approved | RONNIE MINDANAO |
| BUILDING-Rough-Frame | 6/9/2025 | Corrections Issued | RONNIE MINDANAO |
| HVAC-Rough | 6/9/2025 | Approved | RONNIE MINDANAO |
| PLUMBING-Rough | 6/9/2025 | Approved | RONNIE MINDANAO |
| Insulation | 6/18/2025 | Approved | JOSE MACIAS |
| Interior/Exterior Lathing | 6/18/2025 | Approved | JOSE MACIAS |
| Drywall Nailing | 7/14/2025 | Approved | ANTHONY RAMOS |
| BUILDING-Rough-Frame | 9/10/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| Final | 9/10/2025 | Corrections Issued | RONNIE MINDANAO |
| SGSOV-Seismic Gas S/O Valve | 9/10/2025 | SGSOV Approved | RONNIE MINDANAO |
| Smoke Detectors | 9/10/2025 | Corrections Issued | RONNIE MINDANAO |
| BUILDING-Rough-Frame | 9/12/2025 | Approved | RONNIE MINDANAO |
| Final | 9/12/2025 | Corrections Issued | RONNIE MINDANAO |
| Smoke Detectors | 9/12/2025 | Approved | RONNIE MINDANAO |
| Final | 9/22/2025 | OK to Issue CofO | RONNIE MINDANAO |