8800 W HOLLYWOOD BLVD 90069

Certificate Information: 8800 W HOLLYWOOD BLVD 90069

Application / Permit
24014-10000-00944
Plan Check / Job No.
B24LA04314
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT LOWER LEVEL STORAGE SPACE INTO BEDROOM, BATHROOM & SITTING ROOM W/ (E) LAUNDRY & CRAWL SPACE TO REMAIN TO (E) 2-STORY SFD W/ ATTACHED GARAGE CREATING A 3-STORY SFD W/ ATTACHED GARAGE; ADD BALCONIES TO ALL LEVELS; INTERIOR REMODEL (ALL WORK PER ENG'R DESIGN) **ePlan**
Permit Issued
Issued on 6/5/2024
Issuing Office
Current Status
Issued on 6/5/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/8/2024 APPLICANT
Assigned to Plan Check Engineer 3/21/2024 NILOOFAR MEHRAIN
Corrections Issued 4/10/2024 NILOOFAR MEHRAIN
Quality Review Completed 4/16/2024 JASON HEALEY
Applicant returned to address corrections 5/11/2024 NILOOFAR MEHRAIN
Applicant returned to address corrections 5/20/2024 NILOOFAR MEHRAIN
Plan Check Approved 5/29/2024 NILOOFAR MEHRAIN
Issued 6/5/2024 APPLICANT

Permit Application Clearance Information

Sewer availability Cleared 4/20/2024 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 4/23/2024 TREVOR QUAN
Grading Pre-Inspection Cleared 5/12/2024 NILOOFAR MEHRAIN

Contact Information

Contractor Elite Remodeling & Construction Inc Dba Absolute Remodeling; Lic. No.: 823311-B 6351 WILSHIRE BLVD STE 101      LOS ANGELES, CA 90048
Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21243 VENTURA BLVD SUITE 119      WOODLAND HILLS, CA 91364

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/27/2024 Corrections Issued RAUL BARAJAS
Footing/Foundation/Slab 7/30/2024 Partial Approval RAUL BARAJAS
Footing/Foundation/Slab 8/19/2024 Corrections Issued RAUL BARAJAS
Footing/Foundation/Slab 8/21/2024 Partial Approval RAUL BARAJAS
Deputy Drilled-In Anchors 8/30/2024 Conditional Approval RAUL BARAJAS
Deputy Steel/Welding 9/13/2024 Conditional Approval RAUL BARAJAS
Deputy Drilled-In Anchors 10/9/2024 Conditional Approval BRENDAN MORELLI
Deputy Wood Construction 10/18/2024 Conditional Approval BRIAN SULLIVAN
BUILDING-Rough-Frame 10/28/2024 Corrections Issued RAUL BARAJAS
ELECTRICAL-Rough 10/28/2024 Not Ready for Inspection RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 10/28/2024 Not Ready for Inspection RAUL BARAJAS
PLUMBING-Rough 10/28/2024 Partial Approval RAUL BARAJAS
Insulation 11/4/2024 Approved RAUL BARAJAS
Shower Pan 11/4/2024 Approved RAUL BARAJAS
Drywall Nailing 11/14/2024 Approved LUIS CASTRO
Interior/Exterior Lathing 11/14/2024 Approved LUIS CASTRO
BUILDING-Rough-Frame 9/2/2025 Approved ROY SPAULDING
Final 9/2/2025 Corrections Issued ROY SPAULDING
Footing/Foundation/Slab 9/2/2025 Approved ROY SPAULDING
Reinforced Concrete Frame 9/2/2025 Approved ROY SPAULDING
SGSOV-Seismic Gas S/O Valve 9/2/2025 SGSOV Not Ready ROY SPAULDING
Smoke Detectors 9/2/2025 Approved ROY SPAULDING
Floor/Roof Diaphrgm/Shear Wall 9/8/2025 Approved ROY SPAULDING
Insulation 9/8/2025 Approved ROY SPAULDING
Drywall Nailing 9/10/2025 Approved ROY SPAULDING