8800 W HOLLYWOOD BLVD 90069
Certificate Information: 8800 W HOLLYWOOD BLVD 90069
- Application / Permit
- 24014-10000-00944
- Plan Check / Job No.
- B24LA04314
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT LOWER LEVEL STORAGE SPACE INTO BEDROOM, BATHROOM & SITTING ROOM W/ (E) LAUNDRY & CRAWL SPACE TO REMAIN TO (E) 2-STORY SFD W/ ATTACHED GARAGE CREATING A 3-STORY SFD W/ ATTACHED GARAGE; ADD BALCONIES TO ALL LEVELS; INTERIOR REMODEL (ALL WORK PER ENG'R DESIGN) **ePlan**
- Permit Issued
- Issued on 6/5/2024
- Issuing Office
- Current Status
- Issued on 6/5/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/8/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 3/21/2024 | NILOOFAR MEHRAIN |
| Corrections Issued | 4/10/2024 | NILOOFAR MEHRAIN |
| Quality Review Completed | 4/16/2024 | JASON HEALEY |
| Applicant returned to address corrections | 5/11/2024 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 5/20/2024 | NILOOFAR MEHRAIN |
| Plan Check Approved | 5/29/2024 | NILOOFAR MEHRAIN |
| Issued | 6/5/2024 | APPLICANT |
Permit Application Clearance Information
| Sewer availability | Cleared | 4/20/2024 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 4/23/2024 | TREVOR QUAN |
| Grading Pre-Inspection | Cleared | 5/12/2024 | NILOOFAR MEHRAIN |
Contact Information
| Contractor | Elite Remodeling & Construction Inc Dba Absolute Remodeling; Lic. No.: 823311-B | 6351 WILSHIRE BLVD STE 101 LOS ANGELES, CA 90048 |
| Engineer | Melchor,, Oscar Elias; Lic. No.: C76828 | 21243 VENTURA BLVD SUITE 119 WOODLAND HILLS, CA 91364 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/27/2024 | Corrections Issued | RAUL BARAJAS |
| Footing/Foundation/Slab | 7/30/2024 | Partial Approval | RAUL BARAJAS |
| Footing/Foundation/Slab | 8/19/2024 | Corrections Issued | RAUL BARAJAS |
| Footing/Foundation/Slab | 8/21/2024 | Partial Approval | RAUL BARAJAS |
| Deputy Drilled-In Anchors | 8/30/2024 | Conditional Approval | RAUL BARAJAS |
| Deputy Steel/Welding | 9/13/2024 | Conditional Approval | RAUL BARAJAS |
| Deputy Drilled-In Anchors | 10/9/2024 | Conditional Approval | BRENDAN MORELLI |
| Deputy Wood Construction | 10/18/2024 | Conditional Approval | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 10/28/2024 | Corrections Issued | RAUL BARAJAS |
| ELECTRICAL-Rough | 10/28/2024 | Not Ready for Inspection | RAUL BARAJAS |
| Floor/Roof Diaphrgm/Shear Wall | 10/28/2024 | Not Ready for Inspection | RAUL BARAJAS |
| PLUMBING-Rough | 10/28/2024 | Partial Approval | RAUL BARAJAS |
| Insulation | 11/4/2024 | Approved | RAUL BARAJAS |
| Shower Pan | 11/4/2024 | Approved | RAUL BARAJAS |
| Drywall Nailing | 11/14/2024 | Approved | LUIS CASTRO |
| Interior/Exterior Lathing | 11/14/2024 | Approved | LUIS CASTRO |
| BUILDING-Rough-Frame | 9/2/2025 | Approved | ROY SPAULDING |
| Final | 9/2/2025 | Corrections Issued | ROY SPAULDING |
| Footing/Foundation/Slab | 9/2/2025 | Approved | ROY SPAULDING |
| Reinforced Concrete Frame | 9/2/2025 | Approved | ROY SPAULDING |
| SGSOV-Seismic Gas S/O Valve | 9/2/2025 | SGSOV Not Ready | ROY SPAULDING |
| Smoke Detectors | 9/2/2025 | Approved | ROY SPAULDING |
| Floor/Roof Diaphrgm/Shear Wall | 9/8/2025 | Approved | ROY SPAULDING |
| Insulation | 9/8/2025 | Approved | ROY SPAULDING |
| Drywall Nailing | 9/10/2025 | Approved | ROY SPAULDING |