6201 W 78TH ST 90045
Certificate Information: 6201 W 78TH ST 90045
- Application / Permit
- 24014-10000-00942
- Plan Check / Job No.
- B24LA04294
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED 6'-0" x 3'-0" ADDITION AND 37'-4" x 20'-10" IRREGULAR SHAPED ADDITION TO THE (E) SINGLE FAMILY DWELLING TO CONNECT IT TO THE (E) DET. GARAGE AND MAJOR REMODEL. "" NFPA -13D FIRE SPRINKLERS THRU-OUT "".
- Permit Issued
- Issued on 4/26/2024
- Issuing Office
- Current Status
- CofO Issued on 3/11/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/8/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 3/12/2024 | SARKIS HARABEDIAN |
| Corrections Issued | 3/13/2024 | SARKIS HARABEDIAN |
| Plan Check Approved | 4/21/2024 | SARKIS HARABEDIAN |
| Issued | 4/26/2024 | APPLICANT |
| CofO in Progress | 3/10/2025 | JESUS PINEDA |
| CofO in Progress | 3/10/2025 | JESUS PINEDA |
| CofO in Progress | 3/10/2025 | JESUS PINEDA |
| Permit Finaled | 3/11/2025 | RICHARD STEINBACH |
| CofO Issued | 3/11/2025 | RICHARD STEINBACH |
| Permit Finaled | 3/11/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Sewer availability | Cleared | 3/18/2024 | DARIN LAM |
| Eng Process Fee Ord 176,300 | Cleared | 3/19/2024 | DARIN LAM |
| Low Impact Development (LID) | Cleared | 3/26/2024 | SHAHIN KHAZEY |
| Grading Pre-Inspection | Cleared | 3/28/2024 | VASIL MIHALEV |
| Roof/Waste drainage to street | Cleared | 3/30/2024 | BRENDEN HAWK |
| Specific Plan | Cleared | 4/17/2024 | JOSHUA JONES |
| GPI Written Notices | Cleared | 4/21/2024 | SARKIS HARABEDIAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Tamu,, O C; Lic. No.: C29787 | P O BOX 17083 LONG BEACH, CA 90807 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/16/2024 | Corrections Issued | BOBBY KEY |
| Footing/Foundation/Slab | 7/2/2024 | Approved | BOBBY KEY |
| PLUMBING-Rough | 7/15/2024 | Partial Approval | BOBBY KEY |
| Sewer | 7/15/2024 | Approved | BOBBY KEY |
| Wood Frame | 7/15/2024 | Partial Approval | BOBBY KEY |
| Insulation | 7/16/2024 | Partial Approval | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 7/17/2024 | Partial Approval | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 8/23/2024 | Approved | BOBBY KEY |
| HVAC-Rough | 8/23/2024 | Approved | BOBBY KEY |
| PLUMBING-Rough | 8/23/2024 | Corrections Issued | BOBBY KEY |
| ELECTRICAL-Rough | 9/12/2024 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 9/12/2024 | Partial Approval | BOBBY KEY |
| PLUMBING-Rough | 9/12/2024 | Approved | BOBBY KEY |
| BUILDING-Rough-Frame | 9/25/2024 | Approved | BOBBY KEY |
| Insulation | 9/25/2024 | Approved | BOBBY KEY |
| Shower Pan | 9/25/2024 | Not Ready for Inspection | BOBBY KEY |
| Verify Sprinkler Sign Off | 9/25/2024 | Approved | BOBBY KEY |
| Shower Pan | 9/26/2024 | Approved | BOBBY KEY |
| Drywall Nailing | 10/3/2024 | Approved | TEMISTOCLES CAAL |
| Interior/Exterior Lathing | 10/3/2024 | Approved | TEMISTOCLES CAAL |
| ELECTRICAL-Final | 1/29/2025 | Corrections Issued | TEMISTOCLES CAAL |
| HVAC-Final | 1/29/2025 | Not Ready for Inspection | TEMISTOCLES CAAL |
| PLUMBING-Final | 1/29/2025 | Approved | TEMISTOCLES CAAL |
| SGSOV-Seismic Gas S/O Valve | 1/29/2025 | SGSOV Approved | TEMISTOCLES CAAL |
| Smoke Detectors | 1/29/2025 | Approved | TEMISTOCLES CAAL |
| ELECTRICAL-Final | 2/19/2025 | Approved | TEMISTOCLES CAAL |
| Final | 2/19/2025 | Corrections Issued | TEMISTOCLES CAAL |
| Green Building Final | 2/19/2025 | Approved | TEMISTOCLES CAAL |
| HVAC-Final | 2/19/2025 | Approved | TEMISTOCLES CAAL |
| Final | 3/10/2025 | OK to Issue CofO | JESUS PINEDA |
| Service/Power Release | 3/10/2025 | Approved | JESUS PINEDA |