6201 W 78TH ST 90045

Certificate Information: 6201 W 78TH ST 90045

Application / Permit
24014-10000-00942
Plan Check / Job No.
B24LA04294
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED 6'-0" x 3'-0" ADDITION AND 37'-4" x 20'-10" IRREGULAR SHAPED ADDITION TO THE (E) SINGLE FAMILY DWELLING TO CONNECT IT TO THE (E) DET. GARAGE AND MAJOR REMODEL. "" NFPA -13D FIRE SPRINKLERS THRU-OUT "".
Permit Issued
Issued on 4/26/2024
Issuing Office
Current Status
CofO Issued on 3/11/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/8/2024 APPLICANT
Assigned to Plan Check Engineer 3/12/2024 SARKIS HARABEDIAN
Corrections Issued 3/13/2024 SARKIS HARABEDIAN
Plan Check Approved 4/21/2024 SARKIS HARABEDIAN
Issued 4/26/2024 APPLICANT
CofO in Progress 3/10/2025 JESUS PINEDA
CofO in Progress 3/10/2025 JESUS PINEDA
CofO in Progress 3/10/2025 JESUS PINEDA
Permit Finaled 3/11/2025 RICHARD STEINBACH
CofO Issued 3/11/2025 RICHARD STEINBACH
Permit Finaled 3/11/2025 RICHARD STEINBACH

Permit Application Clearance Information

Sewer availability Cleared 3/18/2024 DARIN LAM
Eng Process Fee Ord 176,300 Cleared 3/19/2024 DARIN LAM
Low Impact Development (LID) Cleared 3/26/2024 SHAHIN KHAZEY
Grading Pre-Inspection Cleared 3/28/2024 VASIL MIHALEV
Roof/Waste drainage to street Cleared 3/30/2024 BRENDEN HAWK
Specific Plan Cleared 4/17/2024 JOSHUA JONES
GPI Written Notices Cleared 4/21/2024 SARKIS HARABEDIAN

Contact Information

Contractor Owner-Builder       ,
Engineer Tamu,, O C; Lic. No.: C29787 P O BOX 17083      LONG BEACH, CA 90807

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/16/2024 Corrections Issued BOBBY KEY
Footing/Foundation/Slab 7/2/2024 Approved BOBBY KEY
PLUMBING-Rough 7/15/2024 Partial Approval BOBBY KEY
Sewer 7/15/2024 Approved BOBBY KEY
Wood Frame 7/15/2024 Partial Approval BOBBY KEY
Insulation 7/16/2024 Partial Approval BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 7/17/2024 Partial Approval BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 8/23/2024 Approved BOBBY KEY
HVAC-Rough 8/23/2024 Approved BOBBY KEY
PLUMBING-Rough 8/23/2024 Corrections Issued BOBBY KEY
ELECTRICAL-Rough 9/12/2024 Approved BOBBY KEY
Interior/Exterior Lathing 9/12/2024 Partial Approval BOBBY KEY
PLUMBING-Rough 9/12/2024 Approved BOBBY KEY
BUILDING-Rough-Frame 9/25/2024 Approved BOBBY KEY
Insulation 9/25/2024 Approved BOBBY KEY
Shower Pan 9/25/2024 Not Ready for Inspection BOBBY KEY
Verify Sprinkler Sign Off 9/25/2024 Approved BOBBY KEY
Shower Pan 9/26/2024 Approved BOBBY KEY
Drywall Nailing 10/3/2024 Approved TEMISTOCLES CAAL
Interior/Exterior Lathing 10/3/2024 Approved TEMISTOCLES CAAL
ELECTRICAL-Final 1/29/2025 Corrections Issued TEMISTOCLES CAAL
HVAC-Final 1/29/2025 Not Ready for Inspection TEMISTOCLES CAAL
PLUMBING-Final 1/29/2025 Approved TEMISTOCLES CAAL
SGSOV-Seismic Gas S/O Valve 1/29/2025 SGSOV Approved TEMISTOCLES CAAL
Smoke Detectors 1/29/2025 Approved TEMISTOCLES CAAL
ELECTRICAL-Final 2/19/2025 Approved TEMISTOCLES CAAL
Final 2/19/2025 Corrections Issued TEMISTOCLES CAAL
Green Building Final 2/19/2025 Approved TEMISTOCLES CAAL
HVAC-Final 2/19/2025 Approved TEMISTOCLES CAAL
Final 3/10/2025 OK to Issue CofO JESUS PINEDA
Service/Power Release 3/10/2025 Approved JESUS PINEDA