4635 N WORTSER AVE 91423

Certificate Information: 4635 N WORTSER AVE 91423

Application / Permit
24014-10000-00938
Plan Check / Job No.
B24LA04246
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Eplan. One story 171 SF additon and remodel to existing SFD.
Permit Issued
Issued on 7/12/2024
Issuing Office
Current Status
CofO Issued on 3/6/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/8/2024 APPLICANT
Assigned to Plan Check Engineer 3/12/2024 NEHEMIAS RAMOS
Corrections Issued 3/13/2024 NEHEMIAS RAMOS
Applicant returned to address corrections 5/31/2024 NEHEMIAS RAMOS
Applicant returned to address corrections 6/5/2024 NEHEMIAS RAMOS
Plan Check Approved 6/6/2024 NEHEMIAS RAMOS
Issued 7/12/2024 APPLICANT
CofO in Progress 2/13/2025 CHRISTOPHE COCHRAN
Permit Finaled 3/6/2025 RUBEN SALAS
CofO Issued 3/6/2025 RUBEN SALAS
Permit Finaled 3/6/2025 RUBEN SALAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 4/4/2024 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 4/4/2024 CARLOS AGUILERA
ZI Cleared 4/9/2024 NOAH MCCOY

Contact Information

Contractor Eyeimpact Design-Build; Lic. No.: 1073334-B       ,
Engineer Vasquez,, Luis Fernando; Lic. No.: C56232 375 LA MIRADA AVENUE      SAN MARINO, CA 91108

Inspector Information

CHRISTOPHE COCHRAN, (818) 374-1165 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/17/2024 Approved CHRISTOPHE COCHRAN
Footing/Foundation/Slab 7/17/2024 Corrections Issued CHRISTOPHE COCHRAN
Footing/Foundation/Slab 7/19/2024 Approved CHRISTOPHE COCHRAN
PLUMBING-Rough 8/1/2024 Corrections Issued CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 8/7/2024 Partial Approval CHRISTOPHE COCHRAN
Green Building Rough 8/7/2024 Not Ready for Inspection CHRISTOPHE COCHRAN
MERV13>=Rough 8/7/2024 Not Ready for Inspection CHRISTOPHE COCHRAN
PLUMBING-Rough 8/7/2024 Partial Approval CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 9/20/2024 Partial Approval CHRISTOPHE COCHRAN
Green Building Rough 9/20/2024 Approved CHRISTOPHE COCHRAN
MERV13>=Rough 9/20/2024 Approved CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 10/7/2024 Partial Approval MATTHEW NELSON
ELECTRICAL-Rough 10/7/2024 Approved MATTHEW NELSON
PLUMBING-Rough 10/7/2024 Approved MATTHEW NELSON
BUILDING-Rough-Frame 10/22/2024 Corrections Issued CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 10/29/2024 Approved CHRISTOPHE COCHRAN
HVAC-Rough 10/29/2024 Approved CHRISTOPHE COCHRAN
Interior/Exterior Lathing 10/29/2024 Partial Approval CHRISTOPHE COCHRAN
Insulation 11/1/2024 Approved CHRISTOPHE COCHRAN
Drywall Nailing 11/5/2024 Partial Approval CHRISTOPHE COCHRAN
Drywall Nailing 11/7/2024 Approved CHRISTOPHE COCHRAN
ELECTRICAL-Final 2/6/2025 Approved CHRISTOPHE COCHRAN
Final 2/6/2025 Corrections Issued CHRISTOPHE COCHRAN
Green Building Final 2/6/2025 Not Ready for Inspection CHRISTOPHE COCHRAN
HVAC-Final 2/6/2025 Approved CHRISTOPHE COCHRAN
MERV13>=Final 2/6/2025 Approved CHRISTOPHE COCHRAN
PLUMBING-Final 2/6/2025 Approved CHRISTOPHE COCHRAN
SGSOV-Seismic Gas S/O Valve 2/6/2025 SGSOV Not Ready CHRISTOPHE COCHRAN
Smoke Detectors 2/6/2025 Not Ready for Inspection CHRISTOPHE COCHRAN
Final 2/13/2025 OK to Issue CofO CHRISTOPHE COCHRAN
Green Building Final 2/13/2025 Approved CHRISTOPHE COCHRAN
SGSOV-Seismic Gas S/O Valve 2/13/2025 SGSOV Approved CHRISTOPHE COCHRAN
Smoke Detectors 2/13/2025 Approved CHRISTOPHE COCHRAN