5525 N WORTSER AVE sfd 91401
Certificate Information: 5525 N WORTSER AVE sfd 91401
- Application / Permit
- 24014-10000-00926
- Plan Check / Job No.
- B24LA04193
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan: Addition and remodel to existing S.F.D. New attached covered patio at rear of S.F.D.
- Permit Issued
- Issued on 7/12/2024
- Issuing Office
- Current Status
- Issued on 7/12/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/9/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 4/12/2024 | CAROLEAN BASMA |
| Corrections Issued | 4/15/2024 | CAROLEAN BASMA |
| Applicant returned to address corrections | 6/20/2024 | CAROLEAN BASMA |
| Applicant returned to address corrections | 6/25/2024 | CAROLEAN BASMA |
| Plan Check Approved | 6/27/2024 | CAROLEAN BASMA |
| Issued | 7/12/2024 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 4/24/2024 | CARLOS RAMIREZ |
| Sewer availability | Cleared | 4/24/2024 | CARLOS RAMIREZ |
| Eng Process Fee Ord 176,300 | Cleared | 5/6/2024 | CARLOS RAMIREZ |
| Hold | Cleared | 8/27/2024 | ALEXIS SCHULTZ |
Contact Information
| Contractor | B C Design And Development Inc; Lic. No.: 1022562-B | , |
| Contractor | Bc Design & Development Inc; Lic. No.: 1022562-B | , |
| Engineer | Nazari,, Arthur; Lic. No.: C53497 | 23300 POMPANO STREET MALIBU, CA 90265 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| PLUMBING-Final | 7/27/2026 |
| HVAC-Final | 7/27/2026 |
| ELECTRICAL-Final | 7/27/2026 |
Inspection Request History
| Deputy Drilled-In Anchors | 7/16/2024 | Approved | VINCENT HANLEY |
| Excavation/Setback/Form/Re-Bar | 7/16/2024 | Approved | VINCENT HANLEY |
| Footing/Foundation/Slab | 7/16/2024 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 8/28/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Green Building Rough | 8/28/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 9/3/2024 | Corrections Issued | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/3/2024 | Partial Approval | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/17/2024 | Corrections Issued | OGANES TARAKHCHYAN |
| Deputy Drilled-In Anchors | 11/15/2024 | Conditional Approval | RAUL OLAGI |
| Deputy Wood Construction | 11/20/2024 | Conditional Approval | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 11/21/2024 | Partial Approval | OGANES TARAKHCHYAN |
| HVAC-Rough | 11/21/2024 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 11/21/2024 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 11/27/2024 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 11/27/2024 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/27/2024 | Corrections Issued | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 11/27/2024 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 12/9/2024 | Conditional Approval | GAREN HAYRAPETYAN |
| ELECTRICAL-Rough | 12/9/2024 | Approved | GAREN HAYRAPETYAN |
| HVAC-Rough | 12/9/2024 | Approved | GAREN HAYRAPETYAN |
| PLUMBING-Rough | 12/9/2024 | Approved | GAREN HAYRAPETYAN |
| Insulation | 12/12/2024 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 12/12/2024 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Drywall Nailing | 12/20/2024 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Green Building Rough | 12/20/2024 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 12/20/2024 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 8/18/2025 | No Access for Inspection | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 9/10/2025 | Partial Approval | LOUIS ESCOTO |