6356 W 83RD ST 90045
Certificate Information: 6356 W 83RD ST 90045
- Application / Permit
- 24014-10000-00921
- Plan Check / Job No.
- B24LA04184
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan - REMODEL OF EXISTING SINGLE FAMILY RESIDENCE WITH ADDITION TO FRONT AND REAR. FIRE SPRINKLER NFPA-13D THROUGHOUT.
- Permit Issued
- Issued on 6/5/2024
- Issuing Office
- Current Status
- CofO Issued on 7/22/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/7/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 3/7/2024 | FARSHAD ALIMOHAMADI |
| Corrections Issued | 3/11/2024 | FARSHAD ALIMOHAMADI |
| Quality Review Completed | 3/27/2024 | CAROLYNN NEPOMUCENO |
| Plan Check Approved | 6/4/2024 | FARSHAD ALIMOHAMADI |
| Issued | 6/5/2024 | APPLICANT |
| CofO in Progress | 7/7/2025 | RUBEN RIVAS |
| Permit Finaled | 7/22/2025 | RICHARD STEINBACH |
| Permit Finaled | 7/22/2025 | RICHARD STEINBACH |
| CofO Issued | 7/22/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Permit | Cleared | 3/28/2024 | ANDREA SAINT-ANTONIN |
| Eng Process Fee Ord 176,300 | Cleared | 4/3/2024 | ANDREA SAINT-ANTONIN |
| Low Impact Development (LID) | Cleared | 4/3/2024 | SAMUEL LINN |
| Sewer availability | Cleared | 4/3/2024 | ANDREA SAINT-ANTONIN |
| Specific Plan | Cleared | 4/3/2024 | ALESSANDRO MERCURI |
| Roof/Waste drainage to street | Cleared | 4/4/2024 | LIAM ODONOVAN |
| Trees in Parkway | Cleared | 5/21/2024 | ADALBERTO VERA |
Contact Information
| Architect | Noteware,, Brian Arthur; Lic. No.: NA21514 | , |
| Contractor | Owner-Builder | , |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/3/2024 | Corrections Issued | HERBERT GIRON |
| Pre-Inspection | 7/16/2024 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 7/24/2024 | Partial Approval | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 8/8/2024 | Corrections Issued | TEMISTOCLES CAAL |
| Excavation/Setback/Form/Re-Bar | 8/30/2024 | Corrections Issued | TEMISTOCLES CAAL |
| Deputy Drilled-In Anchors | 9/3/2024 | Conditional Approval | TEMISTOCLES CAAL |
| PLUMBING-Rough | 9/25/2024 | Corrections Issued | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 9/27/2024 | Partial Approval | TEMISTOCLES CAAL |
| PLUMBING-Rough | 9/27/2024 | Partial Approval | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 10/2/2024 | Corrections Issued | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 11/12/2024 | Partial Approval | MICHAEL ALLEN |
| Sewer | 11/12/2024 | Approved | MICHAEL ALLEN |
| BUILDING-Rough-Frame | 12/9/2024 | Approved | MICHAEL ALLEN |
| ELECTRICAL-Rough | 12/9/2024 | Conditional Approval | MICHAEL ALLEN |
| Green Building Rough | 12/9/2024 | Approved | MICHAEL ALLEN |
| HVAC-Rough | 12/9/2024 | Approved | MICHAEL ALLEN |
| PLUMBING-Rough | 12/9/2024 | Corrections Issued | MICHAEL ALLEN |
| Wood Frame | 12/9/2024 | Approved | MICHAEL ALLEN |
| ELECTRICAL-Rough | 12/19/2024 | Approved | MICHAEL ALLEN |
| Insulation | 12/19/2024 | Corrections Issued | MICHAEL ALLEN |
| Interior/Exterior Lathing | 12/19/2024 | Partial Approval | MICHAEL ALLEN |
| PLUMBING-Rough | 12/19/2024 | Approved | MICHAEL ALLEN |
| Shower Pan | 12/19/2024 | Approved | MICHAEL ALLEN |
| Drywall Nailing | 12/26/2024 | Partial Approval | MICHAEL ALLEN |
| Interior/Exterior Lathing | 12/26/2024 | Partial Approval | MICHAEL ALLEN |
| Final | 6/10/2025 | Corrections Issued | RUBEN RIVAS |
| Footing/Foundation/Slab | 6/10/2025 | Corrections Issued | RUBEN RIVAS |
| Green Building Final | 6/10/2025 | Approved | RUBEN RIVAS |
| SGSOV-Seismic Gas S/O Valve | 6/10/2025 | SGSOV Not Ready | RUBEN RIVAS |
| Smoke Detectors | 6/10/2025 | Approved | RUBEN RIVAS |
| Final | 6/17/2025 | OK to Issue CofO | RUBEN RIVAS |
| Footing/Foundation/Slab | 6/17/2025 | Approved | RUBEN RIVAS |
| SGSOV-Seismic Gas S/O Valve | 6/17/2025 | SGSOV Approved | RUBEN RIVAS |
| Service/Power Release | 6/17/2025 | Approved | RUBEN RIVAS |