4832 E TOLAND WAY 90042

Certificate Information: 4832 E TOLAND WAY 90042

Application / Permit
24014-10000-00873
Plan Check / Job No.
B24LA03954
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Eplan. Convert detached garage with addition to new detached ADU per GCS 65852.2(e)(1)(B) AND LAMC 12.22 A.33(c),(d) and (g).
Permit Issued
Issued on 3/12/2025
Issuing Office
Current Status
Issued on 3/12/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/6/2024 APPLICANT
Assigned to Plan Check Engineer 3/8/2024 NGHI SU
Corrections Issued 3/9/2024 NGHI SU
Plan Check Approved 4/25/2024 NGHI SU
Issued 3/12/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 3/18/2024 AMBER CAMPBELL
Roof/Waste drainage to street Cleared 3/18/2024 AMBER CAMPBELL
Eng Process Fee Ord 176,300 Cleared 3/20/2024 AMBER CAMPBELL
Sewer availability Cleared 3/20/2024 AMBER CAMPBELL
Hydrant and Access approval Cleared 4/11/2024 LAVEON RIDER
Grading Pre-Inspection Cleared 4/25/2024 NGHI SU

Contact Information

Architect Dimson,, Ciro Story; Lic. No.: NA39189       ,
Contractor Owner-Builder       ,

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/23/2025 Approved NICHOLAS LOPEZ
Footing/Foundation/Slab 7/23/2025 Approved NICHOLAS LOPEZ
PLUMBING-Rough 7/23/2025 Partial Approval NICHOLAS LOPEZ
ELECTRICAL-Rough 7/25/2025 Partial Approval NICHOLAS LOPEZ
PLUMBING-Rough 7/25/2025 Partial Approval NICHOLAS LOPEZ
Masonry Wall/Backfill 8/12/2025 Not Ready for Inspection DAVID WILLIAMS
Masonry Wall/Backfill 8/14/2025 Partial Approval NICHOLAS LOPEZ
BUILDING-Rough-Frame 12/8/2025 Not Ready for Inspection NICHOLAS LOPEZ
ELECTRICAL-Rough 12/8/2025 Corrections Issued NICHOLAS LOPEZ
Green Building Rough 12/8/2025 Not Ready for Inspection NICHOLAS LOPEZ
HVAC-Rough 12/8/2025 Corrections Issued NICHOLAS LOPEZ
Masonry Wall/Backfill 12/8/2025 Partial Approval NICHOLAS LOPEZ
PLUMBING-Rough 12/8/2025 Corrections Issued NICHOLAS LOPEZ
BUILDING-Rough-Frame 1/13/2026 Approved NICHOLAS LOPEZ
ELECTRICAL-Rough 1/13/2026 Approved NICHOLAS LOPEZ
Floor/Roof Diaphrgm/Shear Wall 1/13/2026 Approved NICHOLAS LOPEZ
Green Building Rough 1/13/2026 Not Ready for Inspection NICHOLAS LOPEZ
HVAC-Rough 1/13/2026 Approved NICHOLAS LOPEZ
PLUMBING-Rough 1/13/2026 Approved NICHOLAS LOPEZ
Interior/Exterior Lathing 1/15/2026 Not Ready for Inspection NICHOLAS LOPEZ
Interior/Exterior Lathing 1/20/2026 Partial Approval NICHOLAS LOPEZ
Green Building Rough 1/28/2026 Approved DAVID WILLIAMS
Interior/Exterior Lathing 1/28/2026 Partial Approval DAVID WILLIAMS
Insulation 2/2/2026 Corrections Issued NICHOLAS LOPEZ
Insulation 2/5/2026 Approved NICHOLAS LOPEZ
Drywall Nailing 2/6/2026 Approved RONNIE MEDINA
Interior/Exterior Lathing 2/6/2026 Partial Approval RONNIE MEDINA
Interior/Exterior Lathing 2/12/2026 Not Ready for Inspection RONNIE MEDINA
Special/Order Compliance 5/1/2026 Partial Inspection NICHOLAS LOPEZ