2206 N DUVALL ST 90031
Certificate Information: 2206 N DUVALL ST 90031
- Application / Permit
- 24014-10000-00872
- Plan Check / Job No.
- B24LA03953
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Convert 1-story duplex into single family story with second story addition to existing 1-story single family to create 2-story single family dwelling with an attached 2-car garage. All work per engineering details.
- Permit Issued
- Issued on 8/27/2024
- Issuing Office
- Current Status
- CofO Issued on 7/13/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/4/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 3/7/2024 | VICTOR CHEN |
| Corrections Issued | 3/15/2024 | VICTOR CHEN |
| Quality Review Completed | 3/27/2024 | HAMID REZAEI |
| Building Plans Picked Up | 3/27/2024 | APPLICANT |
| Applicant returned to address corrections | 4/12/2024 | VICTOR CHEN |
| Applicant returned to address corrections | 4/15/2024 | VICTOR CHEN |
| Plan Check Approved | 4/15/2024 | VICTOR CHEN |
| No Progress | 4/15/2024 | VICTOR CHEN |
| Plan Check Approved | 8/27/2024 | VICTOR CHEN |
| Issued | 8/27/2024 | APPLICANT |
| CofO in Progress | 7/10/2025 | HAMIK HARTOUNIAN |
| Permit Finaled | 7/13/2025 | DEROLD HAUFF |
| CofO Issued | 7/13/2025 | DEROLD HAUFF |
| Permit Finaled | 7/13/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 3/18/2024 | JILVER MAZARIEGOS |
| Permit | Cleared | 3/18/2024 | JILVER MAZARIEGOS |
| Sewer availability | Cleared | 3/18/2024 | JILVER MAZARIEGOS |
| Tenant Habitability Plan | Cleared | 3/19/2024 | RICARDO BOHORQUEZ |
| Low Impact Development (LID) | Cleared | 4/2/2024 | TOMMY YIN |
| Roof/Waste drainage to street | Cleared | 4/3/2024 | ERIK BEASLEY |
| ZI | Cleared | 4/8/2024 | MAYELA VILLA |
| Demo/Removal of Rental Units | Cleared | 7/25/2024 | DIEGO ROCHA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Salto,, Alvaro; Lic. No.: C83859 | 2543 E NORMAN AVE WEST COVINA, CA 91791 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 9/4/2024 | Partial Approval | HAMIK HARTOUNIAN |
| Excavation/Setback/Form/Re-Bar | 9/13/2024 | Not Ready for Inspection | ROY SPAULDING |
| Deputy Drilled-In Anchors | 9/16/2024 | Conditional Approval | HAMIK HARTOUNIAN |
| Excavation/Setback/Form/Re-Bar | 9/16/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| Excavation/Setback/Form/Re-Bar | 9/19/2024 | Approved | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 9/19/2024 | Approved | HAMIK HARTOUNIAN |
| Deputy Reinf. Concrete | 9/23/2024 | Conditional Approval | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/13/2024 | Partial Approval | LUIS CASTRO |
| Floor/Roof Diaphrgm/Shear Wall | 11/15/2024 | Not Ready for Inspection | LUIS CASTRO |
| Floor/Roof Diaphrgm/Shear Wall | 12/6/2024 | Partial Approval | HAMIK HARTOUNIAN |
| Underground Mechanical | 12/16/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 12/19/2024 | Approved | WILLIAM SIERRA |
| Underground Mechanical | 12/19/2024 | Approved | WILLIAM SIERRA |
| Rough-Elec/Plmb/HVAC | 1/3/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| ELECTRICAL-Rough | 1/14/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| HVAC-Rough | 1/14/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 1/17/2025 | Corrections Issued | WILLIAM SIERRA |
| HVAC-Rough | 1/17/2025 | Corrections Issued | WILLIAM SIERRA |
| ELECTRICAL-Rough | 1/22/2025 | Partial Approval | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/22/2025 | Partial Approval | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 2/3/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Green Building Rough | 2/3/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| HVAC-Rough | 2/3/2025 | Approved | HAMIK HARTOUNIAN |
| MERV13>=Rough | 2/3/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 2/11/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 2/11/2025 | Approved | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 2/11/2025 | Approved | HAMIK HARTOUNIAN |
| MERV13>=Rough | 2/11/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 2/13/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| Green Building Rough | 2/13/2025 | Approved | HAMIK HARTOUNIAN |
| MERV13>=Rough | 2/13/2025 | Approved | HAMIK HARTOUNIAN |
| Insulation | 2/18/2025 | Not Ready for Inspection | JOSH MEISTER |
| BUILDING-Rough-Frame | 2/20/2025 | Approved | WILLIAM SIERRA |
| Insulation | 2/20/2025 | Approved | WILLIAM SIERRA |
| Shower Pan | 2/20/2025 | Approved | WILLIAM SIERRA |
| Deputy Drilled-In Anchors | 2/21/2025 | Approved | HAMIK HARTOUNIAN |
| Drywall Nailing | 2/21/2025 | Approved | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 3/7/2025 | Approved | ANTHONY RAMOS |
| Final | 5/19/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| Green Building Final | 5/19/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| MERV13>=Final | 5/19/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 5/19/2025 | SGSOV Not Ready | HAMIK HARTOUNIAN |
| Smoke Detectors | 5/19/2025 | Approved | HAMIK HARTOUNIAN |
| Final | 5/30/2025 | Corrections Issued | OSVALDO PARAMO |
| Green Building Final | 5/30/2025 | Not Ready for Inspection | OSVALDO PARAMO |
| MERV13>=Final | 5/30/2025 | Not Ready for Inspection | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 5/30/2025 | SGSOV Approved | OSVALDO PARAMO |
| Final | 6/9/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Green Building Final | 6/9/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| MERV13>=Final | 6/9/2025 | Approved | HAMIK HARTOUNIAN |
| Final | 6/26/2025 | Corrections Issued | OSVALDO PARAMO |
| Green Building Final | 6/26/2025 | Not Ready for Inspection | OSVALDO PARAMO |
| Final | 7/3/2025 | Partial Inspection | HAMIK HARTOUNIAN |
| Green Building Final | 7/3/2025 | Approved | HAMIK HARTOUNIAN |
| Final | 7/10/2025 | OK to Issue CofO | HAMIK HARTOUNIAN |