1928 N WESTERN AVE 90027
Certificate Information: 1928 N WESTERN AVE 90027
- Application / Permit
- 24014-10000-00866
- Plan Check / Job No.
- B24LA03905
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan: Remodel and addition to existing S.F.D. Removal of existing porte cochere.
- Permit Issued
- Issued on 5/10/2024
- Issuing Office
- Current Status
- CofO Issued on 9/2/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/4/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 3/7/2024 | CAROLEAN BASMA |
| Corrections Issued | 3/7/2024 | CAROLEAN BASMA |
| Applicant returned to address corrections | 4/24/2024 | REZA HAGHIGHAT |
| Applicant returned to address corrections | 5/3/2024 | CAROLEAN BASMA |
| Plan Check Approved | 5/7/2024 | CAROLEAN BASMA |
| Issued | 5/10/2024 | APPLICANT |
| CofO in Progress | 8/29/2025 | CRAIG VAUGHAN |
| Permit Finaled | 9/2/2025 | DEROLD HAUFF |
| CofO Issued | 9/2/2025 | DEROLD HAUFF |
| Permit Finaled | 9/2/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 4/25/2024 | CAROLEAN BASMA |
| Roof/Waste drainage to street | Cleared | 4/26/2024 | CHRISTINA BRACO |
| Eng Process Fee Ord 176,300 | Cleared | 4/30/2024 | DAVID LOPEZ |
| Sewer availability | Cleared | 4/30/2024 | DAVID LOPEZ |
Contact Information
| Contractor | Home Front Build Inc; Lic. No.: 962293-B | 715 CYPRESS AVE LOS ANGELES, CA 90065 |
| Engineer | Phillips,, Craig; Lic. No.: C69673 | 2123 VESTAL AVE LOS ANGELES, CA 90026 |
Inspector Information
| CRAIG VAUGHAN, (213) 202-3250 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/17/2024 | Approved | RAUL BARAJAS |
| ELECTRICAL-Rough | 7/3/2024 | Partial Approval | DAVID FEILER |
| PLUMBING-Rough | 7/3/2024 | Corrections Issued | DAVID FEILER |
| ELECTRICAL-Rough | 7/12/2024 | Partial Approval | ROY SPAULDING |
| PLUMBING-Rough | 7/12/2024 | Partial Approval | ROY SPAULDING |
| Wood Frame | 7/12/2024 | Corrections Issued | ROY SPAULDING |
| ELECTRICAL-Rough | 7/22/2024 | Approved | ROY SPAULDING |
| HVAC-Rough | 7/22/2024 | Approved | ROY SPAULDING |
| Wood Frame | 7/22/2024 | Approved | ROY SPAULDING |
| Insulation | 7/25/2024 | Approved | ROY SPAULDING |
| Drywall Nailing | 8/14/2024 | Approved | JOSH MEISTER |
| Interior/Exterior Lathing | 8/14/2024 | Approved | JOSH MEISTER |
| ELECTRICAL-Final | 12/16/2024 | Approved | JEFFREY MEAD |
| PLUMBING-Final | 12/16/2024 | Approved | JEFFREY MEAD |
| HVAC-Final | 2/5/2025 | Corrections Issued | ENRIQUE MIRELES |
| HVAC-Final | 2/19/2025 | Approved | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 8/13/2025 | Approved | SCOTT FINNILA |
| Final | 8/13/2025 | Not Ready for Inspection | SCOTT FINNILA |
| SGSOV-Seismic Gas S/O Valve | 8/13/2025 | SGSOV Approved | SCOTT FINNILA |
| Smoke Detectors | 8/13/2025 | Approved | SCOTT FINNILA |
| Final | 8/14/2025 | Not Ready for Inspection | BRENDAN MORELLI |
| Final | 8/28/2025 | OK to Issue CofO | CRAIG VAUGHAN |