3763 E YORK BLVD 90065
Certificate Information: 3763 E YORK BLVD 90065
- Application / Permit
- 24014-10000-00865
- Plan Check / Job No.
- B24LA03900
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) 2ND STORY ADDITION TO (E) ACCESSORY DWELLING UNIT
- Permit Issued
- Issued on 12/19/2024
- Issuing Office
- Metro
- Current Status
- CofO Issued on 9/26/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/4/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 3/14/2024 | DANIEL YIP |
| Corrections Issued | 4/30/2024 | DANIEL YIP |
| Quality Review Completed | 5/3/2024 | KEN GILL |
| Building Plans Picked Up | 5/6/2024 | APPLICANT |
| Plan Check Approved | 12/18/2024 | DANIEL YIP |
| Issued | 12/19/2024 | APPLICANT |
| CofO in Progress | 9/25/2025 | DAVID WILLIAMS |
| Permit Finaled | 9/26/2025 | DEROLD HAUFF |
| CofO Issued | 9/26/2025 | DEROLD HAUFF |
| Permit Finaled | 9/26/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Hold | Cleared | 4/4/2024 | CARMEN MERAZ |
| Roof/Waste drainage to street | Cleared | 6/1/2024 | ERIK BEASLEY |
| Eng Process Fee Ord 176,300 | Cleared | 6/20/2024 | ERIK BEASLEY |
| Sewer availability | Cleared | 6/20/2024 | ERIK BEASLEY |
| ZI | Cleared | 9/3/2024 | ANDREA MAGANA-WITHERS |
| Grading Pre-Inspection | Cleared | 9/23/2024 | DANIEL YIP |
| Street Frontage | Cleared | 9/26/2024 | DAVID LOPEZ |
| Hydrant and Access approval | Cleared | 12/13/2024 | PATRICK PEREZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Jalalpour,, Mohammad; Lic. No.: S6696 | 2610 VISTA DEL ORO NEWPORT BEACH, CA 92660 |
Inspector Information
| RONNIE MEDINA, (213) 469-5852 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/11/2025 | Partial Approval | BRENDAN MORELLI |
| Deputy Drilled-In Anchors | 2/19/2025 | Conditional Approval | ALIZAH MAYAGOITIA |
| Excavation/Setback/Form/Re-Bar | 2/20/2025 | Corrections Issued | BRENDAN MORELLI |
| Footing/Foundation/Slab | 2/20/2025 | Not Ready for Inspection | BRENDAN MORELLI |
| Excavation/Setback/Form/Re-Bar | 3/3/2025 | Corrections Issued | JEFFREY MEAD |
| Footing/Foundation/Slab | 3/3/2025 | Not Ready for Inspection | JEFFREY MEAD |
| Excavation/Setback/Form/Re-Bar | 3/10/2025 | Approved | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 3/10/2025 | Approved | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 4/18/2025 | Corrections Issued | DAVID WILLIAMS |
| Green Building Rough | 4/18/2025 | Not Ready for Inspection | DAVID WILLIAMS |
| BUILDING-Rough-Frame | 5/1/2025 | Not Ready for Inspection | DAVID WILLIAMS |
| ELECTRICAL-Rough | 5/1/2025 | Approved | DAVID WILLIAMS |
| Green Building Rough | 5/1/2025 | Approved | DAVID WILLIAMS |
| PLUMBING-Rough | 5/1/2025 | Approved | DAVID WILLIAMS |
| BUILDING-Rough-Frame | 5/14/2025 | Approved | DAVID WILLIAMS |
| Floor/Roof Diaphrgm/Shear Wall | 5/14/2025 | Approved | DAVID WILLIAMS |
| Insulation | 5/14/2025 | Approved | DAVID WILLIAMS |
| Drywall Nailing | 5/27/2025 | Approved | REGINA MENDEZ |
| Interior/Exterior Lathing | 5/27/2025 | Approved | REGINA MENDEZ |
| Shower Pan | 5/27/2025 | Approved | REGINA MENDEZ |
| Final | 7/30/2025 | Corrections Issued | DAVID WILLIAMS |
| Green Building Final | 7/30/2025 | Approved | DAVID WILLIAMS |
| SGSOV-Seismic Gas S/O Valve | 7/30/2025 | SGSOV Approved | DAVID WILLIAMS |
| Smoke Detectors | 7/30/2025 | Approved | DAVID WILLIAMS |
| Final | 9/24/2025 | OK to Issue CofO | DAVID WILLIAMS |