1548 N KINGS ROAD 90069

Certificate Information: 1548 N KINGS ROAD 90069

Application / Permit
24014-10000-00833
Plan Check / Job No.
B24LA03783
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
*EPLAN* ADDITION AND REMODEL OF (E) 2-STORY SFD WITH BASEMENT.
Permit Issued
Issued on 6/13/2024
Issuing Office
Current Status
Issued on 6/13/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/1/2024 APPLICANT
Assigned to Plan Check Engineer 3/7/2024 VIVIAN LAO
Corrections Issued 3/11/2024 VIVIAN LAO
Quality Review Completed 3/13/2024 GARO TELMI
Applicant returned to address corrections 5/15/2024 VIVIAN LAO
Plan Check Approved 6/12/2024 VIVIAN LAO
Issued 6/13/2024 APPLICANT

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 3/20/2024 CELINA MORENO
Sewer availability Cleared 3/20/2024 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 5/21/2024 CELINA MORENO
GPI Written Notices Cleared 6/12/2024 VIVIAN LAO
Grading Pre-Inspection Cleared 6/12/2024 VIVIAN LAO

Contact Information

Contractor Luxe Development Inc; Lic. No.: 993473-B       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/3/2024 No Access for Inspection RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 7/8/2024 Approved ROY SPAULDING
Pre-Inspection 7/8/2024 Not Ready for Inspection ROY SPAULDING
Deputy Drilled-In Anchors 11/27/2024 Conditional Approval NICHOLAS LOPEZ
Deputy Wood Construction 4/10/2025 Conditional Approval ROY SPAULDING
Floor/Roof Diaphrgm/Shear Wall 5/14/2025 Approved ROY SPAULDING
ELECTRICAL-Rough 5/29/2025 Not Ready for Inspection ROY SPAULDING
HVAC-Rough 5/29/2025 Approved ROY SPAULDING
PLUMBING-Rough 5/29/2025 Corrections Issued ROY SPAULDING
ELECTRICAL-Rough 6/10/2025 Corrections Issued BRENDAN MORELLI
PLUMBING-Rough 6/10/2025 Not Ready for Inspection BRENDAN MORELLI
BUILDING-Rough-Frame 6/16/2025 Approved ROY SPAULDING
ELECTRICAL-Rough 6/16/2025 Approved ROY SPAULDING
Green Building Rough 6/16/2025 Approved ROY SPAULDING
Interior/Exterior Lathing 6/16/2025 Approved ROY SPAULDING
PLUMBING-Rough 6/16/2025 Approved ROY SPAULDING
Insulation 7/2/2025 Approved ROY SPAULDING
Shower Pan 7/7/2025 Approved ROY SPAULDING
Interior/Exterior Lathing 7/11/2025 Approved ROY SPAULDING
Drywall Nailing 7/21/2025 Not Ready for Inspection ROY SPAULDING
Drywall Nailing 7/24/2025 Approved ROY SPAULDING