6229 N CEDROS AVE 91411
Certificate Information: 6229 N CEDROS AVE 91411
- Application / Permit
- 24014-10000-00832
- Plan Check / Job No.
- B24LA03779
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert existing SFD to attached ADU per LAMC 12.22A.33(c) and (e) . Attach new duplex at rear of ADU. To be fully sprinklered NFPA 13D
- Permit Issued
- Issued on 1/9/2026
- Issuing Office
- Valley
- Current Status
- Issued on 1/9/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 2/29/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 3/14/2024 | MARCELA FRANQUEZ |
| Corrections Issued | 3/21/2024 | MARCELA FRANQUEZ |
| Quality Review Completed | 3/22/2024 | KEN GILL |
| Building Plans Picked Up | 3/26/2024 | APPLICANT |
| Applicant returned to address corrections | 5/23/2025 | MARCELA FRANQUEZ |
| Applicant returned to address corrections | 6/18/2025 | MARCELA FRANQUEZ |
| Plan Check Approved | 7/1/2025 | MARCELA FRANQUEZ |
| Issued | 1/9/2026 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 3/30/2024 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 4/12/2024 | CARLOS AGUILERA |
| Sewer availability | Cleared | 4/18/2024 | CARLOS AGUILERA |
| "Q" conditions | Cleared | 4/22/2024 | JAZMIN ROQUE |
| Hydrant and Access approval | Cleared | 5/21/2024 | KURT CORRAL |
| Low Impact Development (LID) | Cleared | 5/16/2025 | ERNEST TSE |
| Roof/Waste drainage to street | Cleared | 5/23/2025 | CINDY QI |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 1/14/2026 | Corrections Issued | MICHEL ABAJAN |
| ELECTRICAL-Rough | 1/14/2026 | Not Ready for Inspection | MICHEL ABAJAN |
| Green Building Rough | 1/14/2026 | Not Ready for Inspection | MICHEL ABAJAN |
| PLUMBING-Rough | 1/14/2026 | Not Ready for Inspection | MICHEL ABAJAN |
| Pre-Inspection | 1/14/2026 | Partial Inspection | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 2/2/2026 | Partial Inspection | KIRK SANDERS |
| ELECTRICAL-Rough | 2/2/2026 | Partial Inspection | KIRK SANDERS |
| Footing/Foundation/Slab | 2/2/2026 | Partial Inspection | KIRK SANDERS |
| Green Building Rough | 2/2/2026 | Partial Inspection | KIRK SANDERS |
| HVAC-Rough | 2/2/2026 | Partial Inspection | KIRK SANDERS |
| PLUMBING-Rough | 2/2/2026 | Partial Inspection | KIRK SANDERS |
| Special/Order Compliance | 2/2/2026 | Corrections Issued | KIRK SANDERS |
| BUILDING-Rough-Frame | 3/6/2026 | Not Ready for Inspection | MATTHEW NELSON |
| ELECTRICAL-Rough | 3/6/2026 | Not Ready for Inspection | MATTHEW NELSON |
| Green Building Rough | 3/6/2026 | Not Ready for Inspection | MATTHEW NELSON |
| PLUMBING-Rough | 3/6/2026 | Not Ready for Inspection | MATTHEW NELSON |