2420 E SHOREDALE AVE 90031

Certificate Information: 2420 E SHOREDALE AVE 90031

Application / Permit
24014-10000-00826
Plan Check / Job No.
B24LA03728
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN: 31' X 31'2" IRREGULAR SHAPED ADDITION TO AND CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d). WORK PER ENGINEERED DESIGN.
Permit Issued
Issued on 8/10/2024
Issuing Office
Current Status
CofO Issued on 1/9/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/15/2024 APPLICANT
Assigned to Plan Check Engineer 3/20/2024 OMAR GARNICA
Corrections Issued 3/21/2024 OMAR GARNICA
Plan Check Approved 8/7/2024 OMAR GARNICA
Issued 8/10/2024 APPLICANT
CofO in Progress 1/7/2026 HAMIK HARTOUNIAN
Permit Finaled 1/9/2026 DEROLD HAUFF
CofO Issued 1/9/2026 DEROLD HAUFF
Permit Finaled 1/9/2026 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 3/29/2024 DAVID VO
ZI Cleared 4/8/2024 NATHAN ROMINE
Eng Process Fee Ord 176,300 Cleared 4/12/2024 DAVID VO
Sewer availability Cleared 4/12/2024 DAVID VO
Public Works-Sewers Cleared 4/12/2024 DAVID VO
Low Impact Development (LID) Cleared 6/6/2024 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 6/11/2024 DAVID VO
Construction near power lines Cleared 8/2/2024 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Kazemi,, Milad; Lic. No.: C92143 28025 DOROTHY DR STE 202      AGOURA HILLS, CA 91301

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 1/28/2025 Not Ready for Inspection HAMIK HARTOUNIAN
Underground Mechanical 1/31/2025 Approved JEFFREY MEAD
Footing/Foundation/Slab 2/24/2025 Approved HAMIK HARTOUNIAN
Deputy Wood Construction 4/18/2025 Conditional Approval HAMIK HARTOUNIAN
ELECTRICAL-Rough 4/18/2025 Approved HAMIK HARTOUNIAN
PLUMBING-Rough 4/18/2025 Corrections Issued HAMIK HARTOUNIAN
BUILDING-Rough-Frame 5/5/2025 Approved ALIZAH MAYAGOITIA
HVAC-Rough 5/5/2025 Approved ALIZAH MAYAGOITIA
PLUMBING-Rough 5/5/2025 Approved ALIZAH MAYAGOITIA
Interior/Exterior Lathing 5/14/2025 Partial Approval ALEX COLIN
Insulation 5/20/2025 Corrections Issued HAMIK HARTOUNIAN
Insulation 5/30/2025 Approved ALEX COLIN
Drywall Nailing 6/11/2025 Approved HAMIK HARTOUNIAN
Underground Mechanical 8/8/2025 Approved HAMIK HARTOUNIAN
Shower Pan 8/11/2025 Approved ALEX COLIN
Sewer 8/19/2025 Approved HAMIK HARTOUNIAN
Interior/Exterior Lathing 8/28/2025 Approved HAMIK HARTOUNIAN
ELECTRICAL-Final 12/8/2025 Corrections Issued NICHOLAS LOPEZ
HVAC-Final 12/8/2025 Corrections Issued NICHOLAS LOPEZ
PLUMBING-Final 12/8/2025 Corrections Issued NICHOLAS LOPEZ
BUILDING-Rough-Frame 12/29/2025 Not Ready for Inspection BRENDAN MORELLI
Final 12/29/2025 Not Ready for Inspection BRENDAN MORELLI
Green Building Final 12/29/2025 Not Ready for Inspection BRENDAN MORELLI
Green Building Rough 12/29/2025 Not Ready for Inspection BRENDAN MORELLI
SGSOV-Seismic Gas S/O Valve 12/29/2025 SGSOV Not Ready BRENDAN MORELLI
Smoke Detectors 12/29/2025 Not Ready for Inspection BRENDAN MORELLI
BUILDING-Rough-Frame 1/5/2026 Approved HAMIK HARTOUNIAN
Final 1/5/2026 OK to Issue CofO HAMIK HARTOUNIAN
Green Building Final 1/5/2026 Approved HAMIK HARTOUNIAN
Green Building Rough 1/5/2026 Approved HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 1/5/2026 SGSOV No Gas HAMIK HARTOUNIAN
Service/Power Release 1/5/2026 Approved HAMIK HARTOUNIAN
Smoke Detectors 1/5/2026 Approved HAMIK HARTOUNIAN