3892 S CHERRYWOOD AVE 90008
Certificate Information: 3892 S CHERRYWOOD AVE 90008
- Application / Permit
- 24014-10000-00825
- Plan Check / Job No.
- B24LA03727
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 12'-11" X 27'-10" ADDITION TO EXISTING SINGLE FAMILY DWELLING TO ADD NEW BEDROOM, BATHROOM, AND DEN. WORK DONE PER ENGINEER DESIGN.
- Permit Issued
- Issued on 7/29/2024
- Issuing Office
- Current Status
- CofO Issued on 11/29/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/29/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 3/5/2024 | ALEC MOUSAKHANIAN |
| Corrections Issued | 3/6/2024 | ALEC MOUSAKHANIAN |
| Applicant returned to address corrections | 3/20/2024 | MADISON ODELL |
| Plan Check Approved | 4/8/2024 | MADISON O'DELL |
| Issued | 7/29/2024 | APPLICANT |
| CofO in Progress | 11/29/2025 | LUIS CASTRO |
| Permit Finaled | 11/29/2025 | DEROLD HAUFF |
| CofO Issued | 11/29/2025 | DEROLD HAUFF |
| Permit Finaled | 11/29/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Hold | Cleared | 3/26/2024 | MARIA VENDIVIL |
| Roof/Waste drainage to street | Cleared | 3/26/2024 | JUSTIN BICOL |
| Sewer availability | Cleared | 3/26/2024 | JUSTIN BICOL |
| Eng Process Fee Ord 176,300 | Cleared | 4/1/2024 | JUSTIN BICOL |
Contact Information
| Architect | Hanna,, Remon; Lic. No.: C36271 | 26030 SANDBURG PL STEVENSON RANCH, CA 91381 |
| Contractor | Owner-Builder | , |
| Engineer | Hanna,, Emil Ramzy; Lic. No.: C63602 | 18925 GRANADA CIRCLE NORTHRIDGE, CA 91326 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/11/2024 | Partial Approval | ANTHONY EGSON |
| Underground Mechanical | 9/11/2024 | Partial Approval | ANTHONY EGSON |
| Footing/Foundation/Slab | 9/18/2024 | Corrections Issued | ANTHONY EGSON |
| Footing/Foundation/Slab | 9/20/2024 | Approved | ANTHONY EGSON |
| Deputy Reinf. Concrete | 9/23/2024 | Conditional Approval | ANTHONY EGSON |
| PLUMBING-Rough | 10/1/2024 | Partial Approval | ANTHONY EGSON |
| Sewer | 10/1/2024 | Partial Approval | ANTHONY EGSON |
| BUILDING-Rough-Frame | 10/4/2024 | Not Ready for Inspection | ANTHONY EGSON |
| ELECTRICAL-Rough | 10/4/2024 | Approved | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/4/2024 | Partial Approval | ANTHONY EGSON |
| Green Building Rough | 10/4/2024 | Not Ready for Inspection | ANTHONY EGSON |
| Insulation | 10/11/2024 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 10/11/2024 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 10/16/2024 | Partial Approval | ANTHONY EGSON |
| Drywall Nailing | 10/16/2024 | Approved | ANTHONY EGSON |
| Green Building Rough | 10/16/2024 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 10/16/2024 | Approved | ANTHONY EGSON |
| HVAC-Rough | 4/17/2025 | Approved | LUIS CASTRO |
| BUILDING-Rough-Frame | 11/26/2025 | Approved | LUIS CASTRO |
| ELECTRICAL-Final | 11/26/2025 | Approved | LUIS CASTRO |
| Final | 11/26/2025 | OK to Issue CofO | LUIS CASTRO |
| Green Building Final | 11/26/2025 | Approved | LUIS CASTRO |
| HVAC-Final | 11/26/2025 | Approved | LUIS CASTRO |
| PLUMBING-Final | 11/26/2025 | Approved | LUIS CASTRO |
| SGSOV-Seismic Gas S/O Valve | 11/26/2025 | SGSOV Approved | LUIS CASTRO |
| Smoke Detectors | 11/26/2025 | Approved | LUIS CASTRO |