518 W 88TH ST 90044

Certificate Information: 518 W 88TH ST 90044

Application / Permit
24014-10000-00821
Plan Check / Job No.
B24LA03689
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan. (N) Addition to (E) ADU per CA Govt. Code 65852.2(e)(1)(B) and applicable part of LAMC 12.22 A.33 (c)-(d), (g). All work per WFPP
Permit Issued
Issued on 6/18/2024
Issuing Office
Current Status
CofO Issued on 6/11/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/4/2024 APPLICANT
Assigned to Plan Check Engineer 3/6/2024 AMY GUEVARRA
Corrections Issued 3/14/2024 AMY GUEVARRA
Applicant returned to address corrections 4/8/2024 AMY GUEVARRA
Applicant returned to address corrections 5/7/2024 AMY GUEVARRA
Applicant returned to address corrections 6/4/2024 AMY GUEVARRA
Applicant returned to address corrections 6/13/2024 AMY GUEVARRA
Plan Check Approved 6/15/2024 AMY GUEVARRA
Issued 6/18/2024 APPLICANT
CofO in Progress 6/10/2025 JOHN QUINTANILLA
Permit Finaled 6/11/2025 DEROLD HAUFF
CofO Issued 6/11/2025 DEROLD HAUFF
Permit Finaled 6/11/2025 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 4/11/2024 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 4/18/2024 TREVOR QUAN
Sewer availability Cleared 4/18/2024 TREVOR QUAN
Community Plan Implem. Overlay Cleared 5/30/2024 MANERI ROMAN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 7/30/2024 Corrections Issued ALEJANDRO DE ARTOLA
Underground Mechanical 8/5/2024 Corrections Issued ALEJANDRO DE ARTOLA
Underground Mechanical 8/21/2024 Approved MICHAEL LEWIS
Footing/Foundation/Slab 8/26/2024 Corrections Issued MICHAEL LEWIS
Footing/Foundation/Slab 8/29/2024 Approved MICHAEL LEWIS
ELECTRICAL-Rough 9/12/2024 Approved MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 9/12/2024 Approved MICHAEL LEWIS
HVAC-Rough 9/12/2024 Approved MICHAEL LEWIS
PLUMBING-Rough 9/12/2024 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 10/4/2024 Approved SABAS ALONSO
Green Building Rough 10/4/2024 Approved SABAS ALONSO
Insulation 10/8/2024 Approved CRAIG DAVIS
Interior/Exterior Lathing 10/8/2024 Corrections Issued CRAIG DAVIS
Pre-Inspection 10/8/2024 Not Ready for Inspection CRAIG DAVIS
Shower Pan 10/8/2024 Approved CRAIG DAVIS
Interior/Exterior Lathing 10/11/2024 Partial Approval ALEX COLIN
Drywall Nailing 10/16/2024 Approved ALEX COLIN
Interior/Exterior Lathing 10/21/2024 Approved MICHAEL LEWIS
Final 11/14/2024 Corrections Issued MICHAEL LEWIS
Green Building Final 11/14/2024 Approved MICHAEL LEWIS
MERV13>=Final 11/14/2024 Approved MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 11/14/2024 SGSOV Approved MICHAEL LEWIS
Smoke Detectors 11/14/2024 Approved MICHAEL LEWIS
Final 12/4/2024 Corrections Issued MICHAEL LEWIS
Final 3/19/2025 No Access for Inspection JOHN QUINTANILLA
Sewer 3/21/2025 Approved JOHN QUINTANILLA
Final 4/28/2025 Conditional Approval JOHN QUINTANILLA
Final 6/4/2025 Partial Inspection JOHN QUINTANILLA
Final 6/6/2025 OK to Issue CofO JOHN QUINTANILLA