620 S HARVARD BLVD 90005
Certificate Information: 620 S HARVARD BLVD 90005
- Application / Permit
- 24014-10000-00815
- Plan Check / Job No.
- B24LA03670
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Commercial
- Primary Use
- (11) Hotel
- Work Description
- **Eplan T.I. & ADDITION TO (E) HOTEL 1ST & 2ND FLOOR. & MINOR UPGRADES TO THE BUILDING'S FRONT FACADE FACING HARVARD STREET WITH THE REPLACEMENT OF THE (E) 1ST AND 2ND FLOOR GLASS STOREFRONTS WITH NEW, & THE PARTIAL RE-CLADDING OF THE EXTERIOR WALLS/ SOFFITS.
- Permit Issued
- Issued on 2/24/2025
- Issuing Office
- Current Status
- Issued on 2/24/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/1/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 3/7/2024 | GARO TELMI |
| Assigned to Zoning Architect | 3/7/2024 | GARO TELMI |
| Corrections Issued | 3/19/2024 | GARO TELMI |
| Quality Review Completed | 4/17/2024 | CHAD DOI |
| Applicant returned to address corrections | 5/22/2024 | GARO TELMI |
| Applicant returned to address corrections | 5/29/2024 | GARO TELMI |
| Applicant returned to address corrections | 6/11/2024 | GARO TELMI |
| Applicant returned to address corrections | 7/10/2024 | GARO TELMI |
| Applicant returned to address corrections | 7/18/2024 | GARO TELMI |
| Applicant returned to address corrections | 2/19/2025 | GARO TELMI |
| Plan Check Approved | 2/21/2025 | GARO TELMI |
| Issued | 2/24/2025 | APPLICANT |
Permit Application Clearance Information
| "Q" conditions | Cleared | 4/9/2024 | SPENCER WEJROWSKI |
| Eng Process Fee Ord 176,300 | Cleared | 4/9/2024 | WALLIE JONG |
| Miscellaneous | Cleared | 4/9/2024 | SPENCER WEJROWSKI |
| Historic Resource Verification | Cleared | 4/10/2024 | RAFAEL FONTES |
| Redevelopment Project Area | Cleared | 4/22/2024 | ELIZABETH GALLARDO |
| ZA Case | Cleared | 4/22/2024 | EDWIN CANO |
| ZA Case | Cleared | 4/22/2024 | EDWIN CANO |
| Sewer availability | Cleared | 4/30/2024 | WALLIE JONG |
| Encroachment in public way | Cleared | 5/13/2024 | MARK REYES |
| Highway dedication | Cleared | 7/10/2024 | TREVOR QUAN |
| Green Code | Cleared | 8/8/2024 | AARON COSTA |
| Fire Marshal Fire Life Safety | Cleared | 1/23/2025 | PEJMAN NOORI |
| DAS Clearance | Cleared | 2/6/2025 | Luke Gonzales |
| Zoning Plan Check | Cleared | 2/19/2025 | Luke Gonzales |
Contact Information
| Architect | King,, Christopher Michael; Lic. No.: NA32261 | , |
| Contractor | Inner Space Design & Development Inc; Lic. No.: 863612-B | , |
| Engineer | Moeini,, Soheil; Lic. No.: NA84000 | , |
Inspector Information
| TIMOTHY POWELL, (213) 482-0360 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Masonry Wall/Backfill | 4/22/2025 | Partial Approval | TIMOTHY POWELL |
| Excavation/Setback/Form/Re-Bar | 5/5/2025 | Partial Approval | TIMOTHY POWELL |
| Footing/Foundation/Slab | 6/11/2025 | Partial Inspection | TIMOTHY POWELL |
| Structural Steel Frame | 6/11/2025 | Partial Inspection | TIMOTHY POWELL |
| Structural Steel Frame | 6/16/2025 | Partial Inspection | TIMOTHY POWELL |