7339 S TRASK AVE 90293

Certificate Information: 7339 S TRASK AVE 90293

Application / Permit
24014-10000-00792
Plan Check / Job No.
B24LA03544
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN: 2-STORY ADDITION TO A (E) 1-STORY SFD, with attached storage in the lower leverl,
Permit Issued
Issued on 10/29/2024
Issuing Office
Current Status
CofO Issued on 12/12/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/1/2024 APPLICANT
Assigned to Plan Check Engineer 3/14/2024 KHEDER ALRAZAA
Corrections Issued 3/20/2024 KHEDER ALRAZAA
Quality Review Completed 4/8/2024 GARO TELMI
Plan Check Approved 8/9/2024 KHEDER ALRAZAA
Issued 10/29/2024 APPLICANT
CofO in Progress 12/9/2025 JESUS PINEDA
Permit Finaled 12/12/2025 RICHARD STEINBACH
CofO Issued 12/12/2025 RICHARD STEINBACH
Permit Finaled 12/12/2025 RICHARD STEINBACH

Permit Application Clearance Information

Sewer availability Cleared 4/18/2024 ANDREA SAINT-ANTONIN
Grading Pre-Inspection Cleared 4/18/2024 VASIL MIHALEV
Eng Process Fee Ord 176,300 Cleared 5/14/2024 ANDREA SAINT-ANTONIN
Coastal Zone Cleared 6/13/2024 BRENNEN OBETO
Low Impact Development (LID) Cleared 7/2/2024 LUIS LUVANO
Roof/Waste drainage to street Cleared 7/16/2024 ANDREA SAINT-ANTONIN
GPI Written Notices Cleared 8/9/2024 KHEDER ALRAZAA

Contact Information

Contractor Ciccone Builders Inc; Lic. No.: 850466-B       ,
Engineer Yaprak,, Taskin Tolga; Lic. No.: C72927 560 31ST ST      MANHATTAN BEACH, CA 90266
Engineer Yaprak,, Taskin Tolga; Lic. No.: NA72927       ,

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/14/2024 Partial Approval TEMISTOCLES CAAL
Special/Order Compliance 11/14/2024 Corrections Issued TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 12/3/2024 Partial Approval TEMISTOCLES CAAL
Footing/Foundation/Slab 12/17/2024 Approved TEMISTOCLES CAAL
ELECTRICAL-Rough 2/6/2025 Corrections Issued MICHAEL ALLEN
Floor/Roof Diaphrgm/Shear Wall 2/6/2025 Corrections Issued MICHAEL ALLEN
Gas Test 2/6/2025 Approved MICHAEL ALLEN
Green Building Rough 2/6/2025 Approved MICHAEL ALLEN
HVAC-Rough 2/6/2025 Corrections Issued MICHAEL ALLEN
PLUMBING-Rough 2/6/2025 Approved MICHAEL ALLEN
BUILDING-Rough-Frame 2/18/2025 Not Ready for Inspection TEMISTOCLES CAAL
ELECTRICAL-Rough 2/18/2025 Approved TEMISTOCLES CAAL
HVAC-Rough 2/18/2025 Approved TEMISTOCLES CAAL
PLUMBING-Rough 2/18/2025 Approved TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 2/20/2025 Approved TEMISTOCLES CAAL
BUILDING-Rough-Frame 2/28/2025 Corrections Issued KENNETH NAGLE
Interior/Exterior Lathing 2/28/2025 Approved KENNETH NAGLE
BUILDING-Rough-Frame 3/26/2025 Not Ready for Inspection JESUS PINEDA
Insulation 3/26/2025 Corrections Issued JESUS PINEDA
BUILDING-Rough-Frame 4/4/2025 Approved JESUS PINEDA
Drywall Nailing 4/4/2025 Approved JESUS PINEDA
Insulation 4/4/2025 Approved JESUS PINEDA
ELECTRICAL-Final 8/6/2025 Approved JESUS PINEDA
PLUMBING-Final 8/6/2025 Approved JESUS PINEDA
PLUMBING-Final 9/5/2025 Partial Inspection JESUS PINEDA
HVAC-Final 11/21/2025 Corrections Issued BOBBY KEY
Final 12/9/2025 OK to Issue CofO JESUS PINEDA
Green Building Final 12/9/2025 Approved JESUS PINEDA
HVAC-Final 12/9/2025 Approved JESUS PINEDA
SGSOV-Seismic Gas S/O Valve 12/9/2025 SGSOV Approved JESUS PINEDA
Smoke Detectors 12/9/2025 Approved JESUS PINEDA