1736 W 65TH PL 90047

Certificate Information: 1736 W 65TH PL 90047

Application / Permit
24014-10000-00784
Plan Check / Job No.
B24LA03510
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN: NEW 25'-8 1/2 "X 25'-11 1/2 " IRREGULAR SHAPED ADDITION TO (E) SFD. ALL WORK DONE PER ENGINEER DESIGN.
Permit Issued
Issued on 10/2/2024
Issuing Office
Current Status
CofO Issued on 10/8/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/26/2024 APPLICANT
Assigned to Plan Check Engineer 3/1/2024 MIROOSH KHACHATOORIAN
Corrections Issued 3/4/2024 MIROOSH KHACHATOORIAN
Plan Check Approved 3/28/2024 LUISANGEL VALENZUELA
Issued 10/2/2024 APPLICANT
CofO in Progress 10/6/2025 BARRY HACHE
Permit Finaled 10/8/2025 DEROLD HAUFF
CofO Issued 10/8/2025 DEROLD HAUFF
Permit Finaled 10/8/2025 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 3/14/2024 JESSICA OPINION
Roof/Waste drainage to street Cleared 3/14/2024 JESSICA OPINION
Sewer availability Cleared 3/14/2024 JESSICA OPINION

Contact Information

Contractor Owner-Builder       ,
Engineer Tamu,, O C; Lic. No.: C29787 P O BOX 17083      LONG BEACH, CA 90807
Engineer Tamu,, O C; Lic. No.: NA29787       ,

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 12/19/2024 Conditional Approval BARRY HACHE
Footing/Foundation/Slab 12/20/2024 Approved BARRY HACHE
Floor/Roof Diaphrgm/Shear Wall 1/13/2025 Partial Approval BARRY HACHE
Green Building Rough 1/13/2025 Not Ready for Inspection BARRY HACHE
Insulation 1/15/2025 Approved BARRY HACHE
PLUMBING-Rough 1/15/2025 Approved BARRY HACHE
Floor/Roof Diaphrgm/Shear Wall 1/17/2025 Approved BARRY HACHE
Green Building Rough 1/17/2025 Not Ready for Inspection BARRY HACHE
Floor/Roof Diaphrgm/Shear Wall 2/28/2025 Partial Approval BARRY HACHE
PLUMBING-Rough 2/28/2025 Corrections Issued BARRY HACHE
Floor/Roof Diaphrgm/Shear Wall 3/14/2025 Corrections Issued BARRY HACHE
Green Building Rough 3/14/2025 Not Ready for Inspection BARRY HACHE
PLUMBING-Rough 3/14/2025 Approved BARRY HACHE
Interior/Exterior Lathing 3/25/2025 Corrections Issued BARRY HACHE
Interior/Exterior Lathing 3/27/2025 Partial Approval ANTHONY RAMOS
ELECTRICAL-Rough 4/9/2025 Corrections Issued BARRY HACHE
Interior/Exterior Lathing 4/9/2025 Approved BARRY HACHE
BUILDING-Rough-Frame 4/11/2025 Approved BARRY HACHE
ELECTRICAL-Rough 4/11/2025 Approved BARRY HACHE
Green Building Rough 4/11/2025 Approved BARRY HACHE
HVAC-Rough 4/11/2025 Approved BARRY HACHE
Insulation 4/15/2025 Approved BARRY HACHE
Drywall Nailing 4/18/2025 Not Ready for Inspection BARRY HACHE
Shower Pan 4/18/2025 Corrections Issued BARRY HACHE
Shower Pan 4/21/2025 Approved BARRY HACHE
Drywall Nailing 4/22/2025 Approved BARRY HACHE
Gas Test 4/22/2025 Approved BARRY HACHE
ELECTRICAL-Final 8/15/2025 Corrections Issued BARRY HACHE
PLUMBING-Final 8/15/2025 Not Ready for Inspection BARRY HACHE
Final 8/19/2025 Corrections Issued BARRY HACHE
Green Building Final 8/19/2025 Approved BARRY HACHE
HVAC-Final 8/19/2025 Approved BARRY HACHE
PLUMBING-Final 8/19/2025 Corrections Issued BARRY HACHE
SGSOV-Seismic Gas S/O Valve 8/19/2025 SGSOV Approved BARRY HACHE
ELECTRICAL-Final 8/21/2025 Corrections Issued BARRY HACHE
PLUMBING-Final 8/21/2025 Approved BARRY HACHE
ELECTRICAL-Final 10/3/2025 Approved BARRY HACHE
Final 10/3/2025 OK to Issue CofO BARRY HACHE
Service/Power Release 10/3/2025 Approved BARRY HACHE
Smoke Detectors 10/3/2025 Approved BARRY HACHE