5335 E EDNA ST 90032

Certificate Information: 5335 E EDNA ST 90032

Application / Permit
24014-10000-00755
Plan Check / Job No.
B24LA03407
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan. (E) GARAGE CONVERSION TO ADU AND ADDITION TO ADU PER CA Govt. Code 65852.2(e)(1)(B) and applicable part2 of LAMC 12.22 A.33 (c)-(d), (g)
Permit Issued
Issued on 6/9/2024
Issuing Office
Current Status
CofO Issued on 1/27/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/3/2024 APPLICANT
Assigned to Plan Check Engineer 3/7/2024 ALFREDO JARA
Corrections Issued 3/8/2024 ALFREDO JARA
Plan Check Approved 5/28/2024 ALFREDO JARA
Issued 6/9/2024 APPLICANT
CofO in Progress 1/22/2025 LILIANA PORTILLO
Permit Finaled 1/27/2025 DEROLD HAUFF
CofO Issued 1/27/2025 DEROLD HAUFF
Permit Finaled 1/27/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 3/14/2024 JEANIE LAM
Roof/Waste drainage to street Cleared 3/14/2024 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 5/9/2024 TREVOR QUAN
Sewer availability Cleared 5/9/2024 TREVOR QUAN
Grading Pre-Inspection Cleared 5/10/2024 LANNY MERRICK

Contact Information

Contractor Owner-Builder       ,
Engineer Hernandez, Sotomayor, Daniel; Lic. No.: C93095 15755 SATICOY ST APT#306      VAN NUYS, CA 91406

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 7/9/2024 Partial Approval LILIANA PORTILLO
Footing/Foundation/Slab 7/15/2024 Approved LILIANA PORTILLO
Sewer 7/15/2024 Approved LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 8/13/2024 Approved LILIANA PORTILLO
PLUMBING-Rough 8/13/2024 Corrections Issued LILIANA PORTILLO
Gas Test 9/19/2024 Partial Approval BRENDAN MORELLI
PLUMBING-Rough 9/19/2024 Corrections Issued BRENDAN MORELLI
BUILDING-Rough-Frame 10/3/2024 Corrections Issued LILIANA PORTILLO
ELECTRICAL-Rough 10/3/2024 Corrections Issued LILIANA PORTILLO
Gas Test 10/3/2024 Approved LILIANA PORTILLO
HVAC-Rough 10/3/2024 Approved LILIANA PORTILLO
Interior/Exterior Lathing 10/3/2024 Corrections Issued LILIANA PORTILLO
PLUMBING-Rough 10/3/2024 Approved LILIANA PORTILLO
ELECTRICAL-Rough 10/15/2024 Approved LILIANA PORTILLO
Interior/Exterior Lathing 10/15/2024 Partial Approval LILIANA PORTILLO
Shower Pan 10/15/2024 Approved LILIANA PORTILLO
Insulation 10/24/2024 Approved LILIANA PORTILLO
BUILDING-Rough-Frame 10/31/2024 Approved LILIANA PORTILLO
Drywall Nailing 10/31/2024 Approved LILIANA PORTILLO
Final 12/19/2024 Corrections Issued LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 12/19/2024 SGSOV Not Ready LILIANA PORTILLO
Smoke Detectors 12/19/2024 Not Ready for Inspection LILIANA PORTILLO
Final 1/3/2025 Corrections Issued BRENDAN MORELLI
SGSOV-Seismic Gas S/O Valve 1/3/2025 SGSOV Approved BRENDAN MORELLI
Smoke Detectors 1/3/2025 Approved BRENDAN MORELLI
ELECTRICAL-Final 1/17/2025 Approved LILIANA PORTILLO
Final 1/17/2025 OK to Issue CofO LILIANA PORTILLO
HVAC-Final 1/17/2025 Approved LILIANA PORTILLO
PLUMBING-Final 1/17/2025 Approved LILIANA PORTILLO
Service/Power Release 1/17/2025 Approved LILIANA PORTILLO