5335 E EDNA ST 90032
Certificate Information: 5335 E EDNA ST 90032
- Application / Permit
- 24014-10000-00755
- Plan Check / Job No.
- B24LA03407
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan. (E) GARAGE CONVERSION TO ADU AND ADDITION TO ADU PER CA Govt. Code 65852.2(e)(1)(B) and applicable part2 of LAMC 12.22 A.33 (c)-(d), (g)
- Permit Issued
- Issued on 6/9/2024
- Issuing Office
- Current Status
- CofO Issued on 1/27/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/3/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 3/7/2024 | ALFREDO JARA |
| Corrections Issued | 3/8/2024 | ALFREDO JARA |
| Plan Check Approved | 5/28/2024 | ALFREDO JARA |
| Issued | 6/9/2024 | APPLICANT |
| CofO in Progress | 1/22/2025 | LILIANA PORTILLO |
| Permit Finaled | 1/27/2025 | DEROLD HAUFF |
| CofO Issued | 1/27/2025 | DEROLD HAUFF |
| Permit Finaled | 1/27/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 3/14/2024 | JEANIE LAM |
| Roof/Waste drainage to street | Cleared | 3/14/2024 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 5/9/2024 | TREVOR QUAN |
| Sewer availability | Cleared | 5/9/2024 | TREVOR QUAN |
| Grading Pre-Inspection | Cleared | 5/10/2024 | LANNY MERRICK |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Hernandez, Sotomayor, Daniel; Lic. No.: C93095 | 15755 SATICOY ST APT#306 VAN NUYS, CA 91406 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 7/9/2024 | Partial Approval | LILIANA PORTILLO |
| Footing/Foundation/Slab | 7/15/2024 | Approved | LILIANA PORTILLO |
| Sewer | 7/15/2024 | Approved | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 8/13/2024 | Approved | LILIANA PORTILLO |
| PLUMBING-Rough | 8/13/2024 | Corrections Issued | LILIANA PORTILLO |
| Gas Test | 9/19/2024 | Partial Approval | BRENDAN MORELLI |
| PLUMBING-Rough | 9/19/2024 | Corrections Issued | BRENDAN MORELLI |
| BUILDING-Rough-Frame | 10/3/2024 | Corrections Issued | LILIANA PORTILLO |
| ELECTRICAL-Rough | 10/3/2024 | Corrections Issued | LILIANA PORTILLO |
| Gas Test | 10/3/2024 | Approved | LILIANA PORTILLO |
| HVAC-Rough | 10/3/2024 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 10/3/2024 | Corrections Issued | LILIANA PORTILLO |
| PLUMBING-Rough | 10/3/2024 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Rough | 10/15/2024 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 10/15/2024 | Partial Approval | LILIANA PORTILLO |
| Shower Pan | 10/15/2024 | Approved | LILIANA PORTILLO |
| Insulation | 10/24/2024 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 10/31/2024 | Approved | LILIANA PORTILLO |
| Drywall Nailing | 10/31/2024 | Approved | LILIANA PORTILLO |
| Final | 12/19/2024 | Corrections Issued | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 12/19/2024 | SGSOV Not Ready | LILIANA PORTILLO |
| Smoke Detectors | 12/19/2024 | Not Ready for Inspection | LILIANA PORTILLO |
| Final | 1/3/2025 | Corrections Issued | BRENDAN MORELLI |
| SGSOV-Seismic Gas S/O Valve | 1/3/2025 | SGSOV Approved | BRENDAN MORELLI |
| Smoke Detectors | 1/3/2025 | Approved | BRENDAN MORELLI |
| ELECTRICAL-Final | 1/17/2025 | Approved | LILIANA PORTILLO |
| Final | 1/17/2025 | OK to Issue CofO | LILIANA PORTILLO |
| HVAC-Final | 1/17/2025 | Approved | LILIANA PORTILLO |
| PLUMBING-Final | 1/17/2025 | Approved | LILIANA PORTILLO |
| Service/Power Release | 1/17/2025 | Approved | LILIANA PORTILLO |