3070 W 39TH ST 90008
Certificate Information: 3070 W 39TH ST 90008
- Application / Permit
- 24014-10000-00745
- Plan Check / Job No.
- B24LA03372
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN Proposed 842 S.F. ADU Attached to & Above Existing Detached Garage.
- Permit Issued
- Issued on 8/7/2024
- Issuing Office
- Current Status
- CofO Issued on 12/16/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/26/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 3/7/2024 | ARSALAN SHABESTARI |
| Corrections Issued | 3/26/2024 | ARSALAN SHABESTARI |
| Quality Review Completed | 4/4/2024 | YOUNG KIM |
| Plan Check Approved | 7/19/2024 | ARSALAN SHABESTARI |
| Issued | 8/7/2024 | APPLICANT |
| CofO in Progress | 12/3/2025 | LUIS CASTRO |
| No Progress | 12/4/2025 | DEROLD HAUFF |
| CofO in Progress | 12/4/2025 | DEROLD HAUFF |
| Permit Finaled | 12/16/2025 | DEROLD HAUFF |
| CofO Issued | 12/16/2025 | DEROLD HAUFF |
| Permit Finaled | 12/16/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 4/16/2024 | CHRISTINA BRACO |
| Eng Process Fee Ord 176,300 | Cleared | 4/19/2024 | CHRISTINA BRACO |
| Sewer availability | Cleared | 4/19/2024 | CHRISTINA BRACO |
| Construction near power lines | Cleared | 6/1/2024 | RIDWAN HARDY |
| Construction within easement | Cleared | 6/1/2024 | RIDWAN HARDY |
| Low Impact Development (LID) | Cleared | 6/26/2024 | LUIS LUVANO |
| Roof/Waste drainage to street | Cleared | 6/27/2024 | CHRISTINA BRACO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/11/2024 | Partial Approval | ANTHONY EGSON |
| Underground Mechanical | 9/11/2024 | Partial Approval | ANTHONY EGSON |
| Footing/Foundation/Slab | 9/18/2024 | Corrections Issued | ANTHONY EGSON |
| Footing/Foundation/Slab | 9/20/2024 | Approved | ANTHONY EGSON |
| Deputy Reinf. Concrete | 9/23/2024 | Conditional Approval | ANTHONY EGSON |
| PLUMBING-Rough | 10/3/2024 | Partial Approval | ANTHONY EGSON |
| Sewer | 10/3/2024 | Not Ready for Inspection | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/7/2024 | Partial Approval | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/29/2024 | Approved | BARRY HACHE |
| ELECTRICAL-Rough | 11/12/2024 | Not Ready for Inspection | BARRY HACHE |
| Green Building Rough | 11/12/2024 | Approved | BARRY HACHE |
| HVAC-Rough | 11/12/2024 | Not Ready for Inspection | BARRY HACHE |
| Interior/Exterior Lathing | 11/12/2024 | Approved | BARRY HACHE |
| PLUMBING-Rough | 11/12/2024 | Approved | BARRY HACHE |
| Wood Frame | 11/12/2024 | Not Ready for Inspection | BARRY HACHE |
| ELECTRICAL-Rough | 11/14/2024 | Approved | BARRY HACHE |
| HVAC-Rough | 11/14/2024 | Approved | BARRY HACHE |
| Wood Frame | 11/14/2024 | Corrections Issued | BARRY HACHE |
| Wood Frame | 12/23/2024 | Approved | LUIS CASTRO |
| Insulation | 12/31/2024 | Corrections Issued | NICHOLAS LOPEZ |
| Drywall Nailing | 1/10/2025 | Approved | LUIS CASTRO |
| BUILDING-Rough-Frame | 11/26/2025 | Approved | LUIS CASTRO |
| ELECTRICAL-Final | 11/26/2025 | Not Ready for Inspection | LUIS CASTRO |
| Final | 11/26/2025 | Corrections Issued | LUIS CASTRO |
| Green Building Final | 11/26/2025 | Approved | LUIS CASTRO |
| HVAC-Final | 11/26/2025 | Approved | LUIS CASTRO |
| PLUMBING-Final | 11/26/2025 | Approved | LUIS CASTRO |
| SGSOV-Seismic Gas S/O Valve | 11/26/2025 | SGSOV Approved | LUIS CASTRO |
| Smoke Detectors | 11/26/2025 | Corrections Issued | LUIS CASTRO |
| ELECTRICAL-Final | 12/2/2025 | Approved | LUIS CASTRO |
| Final | 12/2/2025 | OK to Issue CofO | LUIS CASTRO |
| Smoke Detectors | 12/2/2025 | Approved | LUIS CASTRO |