2208 N DUVALL ST 90031
Certificate Information: 2208 N DUVALL ST 90031
- Application / Permit
- 24014-10000-00713
- Plan Check / Job No.
- B24LA03176
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Conversion of garage (352 sq ft) to ADU with addition of 222 sq ft floor area and walkable roof deck (45.3 sq ft exterior stairway to roof addition) per LAMC 12.22 A.33 (c)-(d).
- Permit Issued
- Issued on 5/30/2024
- Issuing Office
- Current Status
- CofO Issued on 7/13/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/21/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 2/26/2024 | JOHN MESIAS |
| Corrections Issued | 2/27/2024 | JOHN MESIAS |
| Building Plans Picked Up | 2/28/2024 | APPLICANT |
| Applicant returned to address corrections | 3/27/2024 | CRISTINA SALAZAR |
| Applicant returned to address corrections | 5/16/2024 | JOHN MESIAS |
| Plan Check Approved | 5/29/2024 | ALEXANDER JOO |
| Issued | 5/30/2024 | APPLICANT |
| CofO in Progress | 7/10/2025 | HAMIK HARTOUNIAN |
| Permit Finaled | 7/13/2025 | DEROLD HAUFF |
| CofO Issued | 7/13/2025 | DEROLD HAUFF |
| Permit Finaled | 7/13/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 2/28/2024 | RICARDO BOHORQUEZ |
| Address approval | Cleared | 3/1/2024 | KHAING AYE |
| Eng Process Fee Ord 176,300 | Cleared | 3/1/2024 | KHAING AYE |
| Roof/Waste drainage to street | Cleared | 3/1/2024 | KHAING AYE |
| Sewer availability | Cleared | 3/1/2024 | KHAING AYE |
| ZI | Cleared | 3/1/2024 | DANIEL CORONADO |
| Construction near power lines | Cleared | 5/22/2024 | ENRIQUE ACOSTA |
| Construction within easement | Cleared | 5/22/2024 | ENRIQUE ACOSTA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 10/3/2024 | Not Ready for Inspection | ROY SPAULDING |
| PLUMBING-Rough | 10/7/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| Excavation/Setback/Form/Re-Bar | 10/11/2024 | Approved | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 10/11/2024 | Approved | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/15/2024 | Partial Approval | LUIS CASTRO |
| ELECTRICAL-Rough | 12/16/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 12/16/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 12/19/2024 | Approved | WILLIAM SIERRA |
| Underground Mechanical | 12/19/2024 | Approved | WILLIAM SIERRA |
| Floor/Roof Diaphrgm/Shear Wall | 1/3/2025 | Partial Approval | JOHN QUINTANILLA |
| ELECTRICAL-Rough | 1/14/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| HVAC-Rough | 1/14/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 1/17/2025 | Corrections Issued | WILLIAM SIERRA |
| HVAC-Rough | 1/17/2025 | Corrections Issued | WILLIAM SIERRA |
| ELECTRICAL-Rough | 1/22/2025 | Partial Approval | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/22/2025 | Partial Approval | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 2/3/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Green Building Rough | 2/3/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| HVAC-Rough | 2/3/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| MERV13>=Rough | 2/3/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 2/13/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Green Building Rough | 2/13/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 2/13/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| MERV13>=Rough | 2/13/2025 | Approved | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 2/19/2025 | Approved | WILLIAM SIERRA |
| ELECTRICAL-Rough | 2/19/2025 | Approved | WILLIAM SIERRA |
| Green Building Rough | 2/19/2025 | Approved | WILLIAM SIERRA |
| HVAC-Rough | 2/19/2025 | Approved | WILLIAM SIERRA |
| Interior/Exterior Lathing | 2/19/2025 | Partial Approval | WILLIAM SIERRA |
| Insulation | 2/21/2025 | Approved | HAMIK HARTOUNIAN |
| Shower Pan | 2/21/2025 | Approved | HAMIK HARTOUNIAN |
| Drywall Nailing | 2/25/2025 | Approved | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 3/7/2025 | Approved | ANTHONY RAMOS |
| Final | 5/19/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| Green Building Final | 5/19/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 5/19/2025 | SGSOV Not Ready | HAMIK HARTOUNIAN |
| Smoke Detectors | 5/19/2025 | Approved | HAMIK HARTOUNIAN |
| Final | 5/30/2025 | Corrections Issued | OSVALDO PARAMO |
| Green Building Final | 5/30/2025 | Not Ready for Inspection | OSVALDO PARAMO |
| MERV13>=Final | 5/30/2025 | Not Ready for Inspection | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 5/30/2025 | SGSOV Approved | OSVALDO PARAMO |
| Final | 6/9/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Green Building Final | 6/9/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| MERV13>=Final | 6/9/2025 | Approved | HAMIK HARTOUNIAN |
| Final | 6/26/2025 | Corrections Issued | OSVALDO PARAMO |
| Green Building Final | 6/26/2025 | Not Ready for Inspection | OSVALDO PARAMO |
| Final | 7/3/2025 | Partial Inspection | HAMIK HARTOUNIAN |
| Green Building Final | 7/3/2025 | Approved | HAMIK HARTOUNIAN |
| Final | 7/10/2025 | OK to Issue CofO | HAMIK HARTOUNIAN |