2208 N DUVALL ST 90031

Certificate Information: 2208 N DUVALL ST 90031

Application / Permit
24014-10000-00713
Plan Check / Job No.
B24LA03176
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Conversion of garage (352 sq ft) to ADU with addition of 222 sq ft floor area and walkable roof deck (45.3 sq ft exterior stairway to roof addition) per LAMC 12.22 A.33 (c)-(d).
Permit Issued
Issued on 5/30/2024
Issuing Office
Current Status
CofO Issued on 7/13/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/21/2024 APPLICANT
Assigned to Plan Check Engineer 2/26/2024 JOHN MESIAS
Corrections Issued 2/27/2024 JOHN MESIAS
Building Plans Picked Up 2/28/2024 APPLICANT
Applicant returned to address corrections 3/27/2024 CRISTINA SALAZAR
Applicant returned to address corrections 5/16/2024 JOHN MESIAS
Plan Check Approved 5/29/2024 ALEXANDER JOO
Issued 5/30/2024 APPLICANT
CofO in Progress 7/10/2025 HAMIK HARTOUNIAN
Permit Finaled 7/13/2025 DEROLD HAUFF
CofO Issued 7/13/2025 DEROLD HAUFF
Permit Finaled 7/13/2025 DEROLD HAUFF

Permit Application Clearance Information

Tenant Habitability Plan Cleared 2/28/2024 RICARDO BOHORQUEZ
Address approval Cleared 3/1/2024 KHAING AYE
Eng Process Fee Ord 176,300 Cleared 3/1/2024 KHAING AYE
Roof/Waste drainage to street Cleared 3/1/2024 KHAING AYE
Sewer availability Cleared 3/1/2024 KHAING AYE
ZI Cleared 3/1/2024 DANIEL CORONADO
Construction near power lines Cleared 5/22/2024 ENRIQUE ACOSTA
Construction within easement Cleared 5/22/2024 ENRIQUE ACOSTA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 10/3/2024 Not Ready for Inspection ROY SPAULDING
PLUMBING-Rough 10/7/2024 Corrections Issued HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 10/11/2024 Approved HAMIK HARTOUNIAN
Footing/Foundation/Slab 10/11/2024 Approved HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 11/15/2024 Partial Approval LUIS CASTRO
ELECTRICAL-Rough 12/16/2024 Corrections Issued HAMIK HARTOUNIAN
PLUMBING-Rough 12/16/2024 Corrections Issued HAMIK HARTOUNIAN
PLUMBING-Rough 12/19/2024 Approved WILLIAM SIERRA
Underground Mechanical 12/19/2024 Approved WILLIAM SIERRA
Floor/Roof Diaphrgm/Shear Wall 1/3/2025 Partial Approval JOHN QUINTANILLA
ELECTRICAL-Rough 1/14/2025 Not Ready for Inspection HAMIK HARTOUNIAN
HVAC-Rough 1/14/2025 Corrections Issued HAMIK HARTOUNIAN
ELECTRICAL-Rough 1/17/2025 Corrections Issued WILLIAM SIERRA
HVAC-Rough 1/17/2025 Corrections Issued WILLIAM SIERRA
ELECTRICAL-Rough 1/22/2025 Partial Approval HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 1/22/2025 Partial Approval HAMIK HARTOUNIAN
BUILDING-Rough-Frame 2/3/2025 Not Ready for Inspection HAMIK HARTOUNIAN
Green Building Rough 2/3/2025 Not Ready for Inspection HAMIK HARTOUNIAN
HVAC-Rough 2/3/2025 Corrections Issued HAMIK HARTOUNIAN
MERV13>=Rough 2/3/2025 Not Ready for Inspection HAMIK HARTOUNIAN
BUILDING-Rough-Frame 2/13/2025 Not Ready for Inspection HAMIK HARTOUNIAN
Green Building Rough 2/13/2025 Not Ready for Inspection HAMIK HARTOUNIAN
Interior/Exterior Lathing 2/13/2025 Not Ready for Inspection HAMIK HARTOUNIAN
MERV13>=Rough 2/13/2025 Approved HAMIK HARTOUNIAN
BUILDING-Rough-Frame 2/19/2025 Approved WILLIAM SIERRA
ELECTRICAL-Rough 2/19/2025 Approved WILLIAM SIERRA
Green Building Rough 2/19/2025 Approved WILLIAM SIERRA
HVAC-Rough 2/19/2025 Approved WILLIAM SIERRA
Interior/Exterior Lathing 2/19/2025 Partial Approval WILLIAM SIERRA
Insulation 2/21/2025 Approved HAMIK HARTOUNIAN
Shower Pan 2/21/2025 Approved HAMIK HARTOUNIAN
Drywall Nailing 2/25/2025 Approved HAMIK HARTOUNIAN
Interior/Exterior Lathing 3/7/2025 Approved ANTHONY RAMOS
Final 5/19/2025 Corrections Issued HAMIK HARTOUNIAN
Green Building Final 5/19/2025 Corrections Issued HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 5/19/2025 SGSOV Not Ready HAMIK HARTOUNIAN
Smoke Detectors 5/19/2025 Approved HAMIK HARTOUNIAN
Final 5/30/2025 Corrections Issued OSVALDO PARAMO
Green Building Final 5/30/2025 Not Ready for Inspection OSVALDO PARAMO
MERV13>=Final 5/30/2025 Not Ready for Inspection OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 5/30/2025 SGSOV Approved OSVALDO PARAMO
Final 6/9/2025 Not Ready for Inspection HAMIK HARTOUNIAN
Green Building Final 6/9/2025 Corrections Issued HAMIK HARTOUNIAN
MERV13>=Final 6/9/2025 Approved HAMIK HARTOUNIAN
Final 6/26/2025 Corrections Issued OSVALDO PARAMO
Green Building Final 6/26/2025 Not Ready for Inspection OSVALDO PARAMO
Final 7/3/2025 Partial Inspection HAMIK HARTOUNIAN
Green Building Final 7/3/2025 Approved HAMIK HARTOUNIAN
Final 7/10/2025 OK to Issue CofO HAMIK HARTOUNIAN