1710 1/2 W 38TH ST 90062

Certificate Information: 1710 1/2 W 38TH ST 90062

Application / Permit
24014-10000-00690
Plan Check / Job No.
B24LA03060
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert detached (E) 1-car garage with addition to ADU per ordinance.
Permit Issued
Issued on 4/22/2024
Issuing Office
Metro
Current Status
CofO Issued on 5/25/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/20/2024 APPLICANT
Assigned to Plan Check Engineer 2/22/2024 HUAN LE
Corrections Issued 2/26/2024 HUAN LE
Building Plans Picked Up 3/22/2024 APPLICANT
Plan Check Approved 4/9/2024 MINA HABILI
Issued 4/22/2024 APPLICANT
CofO in Progress 5/23/2025 SABAS ALONSO
Permit Finaled 5/25/2025 DEROLD HAUFF
CofO Issued 5/25/2025 DEROLD HAUFF
Permit Finaled 5/25/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 3/29/2024 STEVE MELGAR
Roof/Waste drainage to street Cleared 3/29/2024 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 4/1/2024 STEVE MELGAR
Sewer availability Cleared 4/1/2024 STEVE MELGAR

Contact Information

Contractor Coleman Construction Inc; Lic. No.: 697040-B 1973 W 48TH STREET      LOS ANGELES, CA 90062
Engineer Hamilton,, John O; Lic. No.: C53284 P O BOX 1543      HAWTHORNE, CA 90251

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/25/2024 Partial Inspection SABAS ALONSO
Underground Mechanical 10/3/2024 Partial Approval SABAS ALONSO
PLUMBING-Rough 10/9/2024 Not Ready for Inspection SABAS ALONSO
Sewer 10/9/2024 Approved SABAS ALONSO
Footing/Foundation/Slab 10/16/2024 Not Ready for Inspection SABAS ALONSO
Underground Mechanical 10/16/2024 Partial Approval SABAS ALONSO
Footing/Foundation/Slab 10/21/2024 Partial Approval SABAS ALONSO
Underground Mechanical 10/21/2024 Not Ready for Inspection SABAS ALONSO
Footing/Foundation/Slab 11/12/2024 Approved SABAS ALONSO
Underground Mechanical 11/12/2024 Approved SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 12/6/2024 Partial Approval SABAS ALONSO
ELECTRICAL-Rough 12/11/2024 Approved SABAS ALONSO
HVAC-Rough 12/11/2024 Corrections Issued SABAS ALONSO
PLUMBING-Rough 12/11/2024 Approved SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 12/17/2024 Approved SABAS ALONSO
HVAC-Rough 12/17/2024 Approved SABAS ALONSO
BUILDING-Rough-Frame 12/19/2024 Approved SABAS ALONSO
Green Building Rough 12/19/2024 Approved SABAS ALONSO
Insulation 12/19/2024 Approved SABAS ALONSO
Interior/Exterior Lathing 12/19/2024 Partial Approval SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 12/23/2024 Partial Inspection MICHAEL LEWIS
Interior/Exterior Lathing 12/23/2024 Approved MICHAEL LEWIS
Drywall Nailing 1/7/2025 Corrections Issued SABAS ALONSO
Drywall Nailing 1/13/2025 Approved SABAS ALONSO
Shower Pan 1/13/2025 Approved SABAS ALONSO
Final 2/10/2025 Corrections Issued SABAS ALONSO
Green Building Final 2/10/2025 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 2/10/2025 SGSOV Approved SABAS ALONSO
Smoke Detectors 2/10/2025 Approved SABAS ALONSO
Final 2/18/2025 Not Ready for Inspection SABAS ALONSO
Final 3/13/2025 Not Ready for Inspection SABAS ALONSO
ELECTRICAL-Final 5/9/2025 Corrections Issued SABAS ALONSO
Final 5/9/2025 Corrections Issued SABAS ALONSO
ELECTRICAL-Final 5/22/2025 Approved SABAS ALONSO
Final 5/22/2025 OK to Issue CofO SABAS ALONSO