1710 1/2 W 38TH ST 90062
Certificate Information: 1710 1/2 W 38TH ST 90062
- Application / Permit
- 24014-10000-00690
- Plan Check / Job No.
- B24LA03060
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert detached (E) 1-car garage with addition to ADU per ordinance.
- Permit Issued
- Issued on 4/22/2024
- Issuing Office
- Metro
- Current Status
- CofO Issued on 5/25/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/20/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 2/22/2024 | HUAN LE |
| Corrections Issued | 2/26/2024 | HUAN LE |
| Building Plans Picked Up | 3/22/2024 | APPLICANT |
| Plan Check Approved | 4/9/2024 | MINA HABILI |
| Issued | 4/22/2024 | APPLICANT |
| CofO in Progress | 5/23/2025 | SABAS ALONSO |
| Permit Finaled | 5/25/2025 | DEROLD HAUFF |
| CofO Issued | 5/25/2025 | DEROLD HAUFF |
| Permit Finaled | 5/25/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 3/29/2024 | STEVE MELGAR |
| Roof/Waste drainage to street | Cleared | 3/29/2024 | STEVE MELGAR |
| Eng Process Fee Ord 176,300 | Cleared | 4/1/2024 | STEVE MELGAR |
| Sewer availability | Cleared | 4/1/2024 | STEVE MELGAR |
Contact Information
| Contractor | Coleman Construction Inc; Lic. No.: 697040-B | 1973 W 48TH STREET LOS ANGELES, CA 90062 |
| Engineer | Hamilton,, John O; Lic. No.: C53284 | P O BOX 1543 HAWTHORNE, CA 90251 |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/25/2024 | Partial Inspection | SABAS ALONSO |
| Underground Mechanical | 10/3/2024 | Partial Approval | SABAS ALONSO |
| PLUMBING-Rough | 10/9/2024 | Not Ready for Inspection | SABAS ALONSO |
| Sewer | 10/9/2024 | Approved | SABAS ALONSO |
| Footing/Foundation/Slab | 10/16/2024 | Not Ready for Inspection | SABAS ALONSO |
| Underground Mechanical | 10/16/2024 | Partial Approval | SABAS ALONSO |
| Footing/Foundation/Slab | 10/21/2024 | Partial Approval | SABAS ALONSO |
| Underground Mechanical | 10/21/2024 | Not Ready for Inspection | SABAS ALONSO |
| Footing/Foundation/Slab | 11/12/2024 | Approved | SABAS ALONSO |
| Underground Mechanical | 11/12/2024 | Approved | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 12/6/2024 | Partial Approval | SABAS ALONSO |
| ELECTRICAL-Rough | 12/11/2024 | Approved | SABAS ALONSO |
| HVAC-Rough | 12/11/2024 | Corrections Issued | SABAS ALONSO |
| PLUMBING-Rough | 12/11/2024 | Approved | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 12/17/2024 | Approved | SABAS ALONSO |
| HVAC-Rough | 12/17/2024 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 12/19/2024 | Approved | SABAS ALONSO |
| Green Building Rough | 12/19/2024 | Approved | SABAS ALONSO |
| Insulation | 12/19/2024 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 12/19/2024 | Partial Approval | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 12/23/2024 | Partial Inspection | MICHAEL LEWIS |
| Interior/Exterior Lathing | 12/23/2024 | Approved | MICHAEL LEWIS |
| Drywall Nailing | 1/7/2025 | Corrections Issued | SABAS ALONSO |
| Drywall Nailing | 1/13/2025 | Approved | SABAS ALONSO |
| Shower Pan | 1/13/2025 | Approved | SABAS ALONSO |
| Final | 2/10/2025 | Corrections Issued | SABAS ALONSO |
| Green Building Final | 2/10/2025 | Approved | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 2/10/2025 | SGSOV Approved | SABAS ALONSO |
| Smoke Detectors | 2/10/2025 | Approved | SABAS ALONSO |
| Final | 2/18/2025 | Not Ready for Inspection | SABAS ALONSO |
| Final | 3/13/2025 | Not Ready for Inspection | SABAS ALONSO |
| ELECTRICAL-Final | 5/9/2025 | Corrections Issued | SABAS ALONSO |
| Final | 5/9/2025 | Corrections Issued | SABAS ALONSO |
| ELECTRICAL-Final | 5/22/2025 | Approved | SABAS ALONSO |
| Final | 5/22/2025 | OK to Issue CofO | SABAS ALONSO |