3792 1/2 S BEETHOVEN ST 90066

Certificate Information: 3792 1/2 S BEETHOVEN ST 90066

Application / Permit
24014-10000-00684
Plan Check / Job No.
B24LA03029
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Two-story ground floor addition to (E) one story garage. the addition will be an ADU per LAMC 12.22 A.33 (c)-(d)
Permit Issued
Issued on 11/13/2024
Issuing Office
Current Status
CofO Issued on 11/8/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/20/2024 APPLICANT
Assigned to Plan Check Engineer 3/7/2024 GEORGE JOLAKIAN
Corrections Issued 3/14/2024 GEORGE JOLAKIAN
Quality Review Completed 4/4/2024 RODOLFO ARIAS
Plan Check Approved 10/11/2024 GEORGE JOLAKIAN
Issued 11/13/2024 APPLICANT
CofO in Progress 11/5/2025 WILBER ROSALES
Permit Finaled 11/8/2025 RICHARD STEINBACH
CofO Issued 11/8/2025 RICHARD STEINBACH
Permit Finaled 11/8/2025 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 4/3/2024 VLADIMIR ARUTYUNYAN
Sewer availability Cleared 4/3/2024 VLADIMIR ARUTYUNYAN
Grading Pre-Inspection Cleared 4/12/2024 VASIL MIHALEV
Specific Plan Cleared 4/17/2024 FREDDY GARCIA
Construction near power lines Cleared 4/25/2024 TINA MIRANDA
Low Impact Development (LID) Cleared 5/17/2024 ERNEST TSE
Eng Process Fee Ord 176,300 Cleared 5/21/2024 LIAM ODONOVAN
Roof/Waste drainage to street Cleared 5/21/2024 LIAM ODONOVAN
Disturb/Remove Protected Trees Cleared 7/17/2024 GEORGE JOLAKIAN

Contact Information

Architect Song,, Michael; Lic. No.: NA32566       ,
Contractor Tizcareno'S Unlimited Construction; Lic. No.: 953087-B       ,
Engineer Kazemi,, Milad; Lic. No.: C92143 28025 DOROTHY DR STE 202      AGOURA HILLS, CA 91301
Engineer Kazemi,, Milad; Lic. No.: NA92143       ,

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Special/Order Compliance 4/1/2025 Corrections Issued MICHAEL ALLEN
Underground Mechanical 4/1/2025 Approved MICHAEL ALLEN
Deputy Drilled-In Anchors 4/8/2025 Conditional Approval DAVID FEILER
Footing/Foundation/Slab 4/14/2025 Partial Approval MICHAEL ALLEN
Deputy Reinf. Concrete 4/15/2025 Conditional Approval JAYLIN GRAVITTE
Deputy Drilled-In Anchors 4/17/2025 Partial Approval MICHAEL ALLEN
Footing/Foundation/Slab 4/21/2025 Partial Approval MICHAEL ALLEN
Deputy Drilled-In Anchors 4/28/2025 Conditional Approval DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 5/15/2025 Partial Approval MICHAEL ALLEN
Deputy Wood Construction 5/19/2025 Partial Approval MICHAEL ALLEN
Floor/Roof Diaphrgm/Shear Wall 6/25/2025 Approved MICHAEL ALLEN
HVAC-Rough 7/15/2025 Approved MICHAEL ALLEN
PLUMBING-Rough 7/15/2025 Approved MICHAEL ALLEN
Shower Pan 7/15/2025 Approved MICHAEL ALLEN
ELECTRICAL-Rough 7/17/2025 Corrections Issued MICHAEL ALLEN
Interior/Exterior Lathing 7/17/2025 Partial Approval MICHAEL ALLEN
BUILDING-Rough-Frame 7/24/2025 Approved WILBER ROSALES
ELECTRICAL-Rough 7/24/2025 Approved WILBER ROSALES
Green Building Rough 7/24/2025 Approved WILBER ROSALES
Insulation 7/24/2025 Corrections Issued WILBER ROSALES
Sewer 7/24/2025 Approved WILBER ROSALES
Underground Mechanical 7/24/2025 Approved WILBER ROSALES
Drywall Nailing 7/29/2025 Approved JAYLIN GRAVITTE
Insulation 7/29/2025 Approved JAYLIN GRAVITTE
Gas Test 9/15/2025 Approved JAYLIN GRAVITTE
ELECTRICAL-Final 9/22/2025 Partial Approval WILBER ROSALES
PLUMBING-Final 9/22/2025 Approved WILBER ROSALES
HVAC-Final 9/23/2025 Approved WILBER ROSALES
ELECTRICAL-Final 10/30/2025 Approved WILBER ROSALES
Final 10/30/2025 Corrections Issued WILBER ROSALES
Footing/Foundation/Slab 10/30/2025 Approved WILBER ROSALES
Green Building Final 10/30/2025 Approved WILBER ROSALES
SGSOV-Seismic Gas S/O Valve 10/30/2025 SGSOV Approved WILBER ROSALES
Smoke Detectors 10/30/2025 Approved WILBER ROSALES
Final 11/4/2025 OK to Issue CofO WILBER ROSALES
Service/Power Release 11/7/2025 Approved WILBER ROSALES