1322 N JUNE ST 90028
Certificate Information: 1322 N JUNE ST 90028
- Application / Permit
- 24014-10000-00680
- Plan Check / Job No.
- B24LA03013
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION TO THE REAR OF AN (E) SFD
- Permit Issued
- Issued on 4/10/2024
- Issuing Office
- Metro
- Current Status
- CofO Issued on 5/15/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/20/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 2/20/2024 | ZAW HAN |
| Corrections Issued | 2/20/2024 | ZAW HAN |
| Applicant returned to address corrections | 4/1/2024 | ALEXANDER JOO |
| Applicant returned to address corrections | 4/2/2024 | LAWRENCE QUIRANTE |
| Plan Check Approved | 4/10/2024 | JOSE VELAZQUEZ |
| Issued | 4/10/2024 | APPLICANT |
| CofO in Progress | 4/29/2026 | ROY SPAULDING |
| Permit Finaled | 5/15/2026 | DEROLD HAUFF |
| CofO Issued | 5/15/2026 | DEROLD HAUFF |
| Permit Finaled | 5/15/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Historic Resource Verification | Cleared | 3/7/2024 | RAFAEL FONTES |
| Redevelopment Project Area | Cleared | 3/19/2024 | YASMINE BASHIRI |
| Roof/Waste drainage to street | Cleared | 4/4/2024 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 4/5/2024 | WALLIE JONG |
| Sewer availability | Cleared | 4/5/2024 | WALLIE JONG |
Contact Information
| Contractor | Homeworks Construction & Design; Lic. No.: 841888-B | 9641 RICHEON AVE DOWNEY, CA 90240 |
Inspector Information
| ROY SPAULDING, (213) 202-3461 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/25/2024 | Partial Approval | BRIAN SULLIVAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/6/2024 | Corrections Issued | BRIAN SULLIVAN |
| Footing/Foundation/Slab | 5/6/2024 | Corrections Issued | BRIAN SULLIVAN |
| Insulation | 5/8/2024 | Partial Approval | BRIAN SULLIVAN |
| Piling/Pier/Caisson | 5/8/2024 | Approved | BRIAN SULLIVAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/29/2024 | Approved | BRIAN SULLIVAN |
| ELECTRICAL-Rough | 6/5/2024 | Not Ready for Inspection | BRIAN SULLIVAN |
| PLUMBING-Rough | 6/5/2024 | Not Ready for Inspection | BRIAN SULLIVAN |
| Wood Frame | 6/5/2024 | Not Ready for Inspection | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 6/18/2024 | Approved | BRIAN SULLIVAN |
| ELECTRICAL-Rough | 6/18/2024 | Approved | BRIAN SULLIVAN |
| Green Building Rough | 6/18/2024 | Approved | BRIAN SULLIVAN |
| PLUMBING-Rough | 6/18/2024 | Approved | BRIAN SULLIVAN |
| ELECTRICAL-Rough | 6/26/2024 | Approved | BRIAN SULLIVAN |
| HVAC-Rough | 6/26/2024 | Approved | BRIAN SULLIVAN |
| Insulation | 6/26/2024 | Approved | BRIAN SULLIVAN |
| PLUMBING-Rough | 6/26/2024 | Approved | BRIAN SULLIVAN |
| Drywall Nailing | 7/9/2024 | Approved | BRIAN SULLIVAN |
| ELECTRICAL-Final | 11/5/2024 | Corrections Issued | BRIAN SULLIVAN |
| PLUMBING-Final | 11/5/2024 | Approved | BRIAN SULLIVAN |
| Service/Power Release | 11/5/2024 | Approved | BRIAN SULLIVAN |
| ELECTRICAL-Final | 1/22/2026 | Corrections Issued | ROY SPAULDING |
| HVAC-Final | 1/22/2026 | Approved | ROY SPAULDING |
| ELECTRICAL-Final | 2/5/2026 | Approved | ROY SPAULDING |
| Final | 2/5/2026 | Corrections Issued | ROY SPAULDING |
| Footing/Foundation/Slab | 2/5/2026 | Approved | ROY SPAULDING |
| Green Building Final | 2/5/2026 | Approved | ROY SPAULDING |
| SGSOV-Seismic Gas S/O Valve | 2/5/2026 | SGSOV Not Ready | ROY SPAULDING |
| Smoke Detectors | 2/5/2026 | Approved | ROY SPAULDING |
| Final | 4/27/2026 | OK to Issue CofO | ROY SPAULDING |
| SGSOV-Seismic Gas S/O Valve | 4/27/2026 | SGSOV Approved | ROY SPAULDING |