3771 N LONGVIEW VALLEY ROAD 91423

Certificate Information: 3771 N LONGVIEW VALLEY ROAD 91423

Application / Permit
24014-10000-00679
Plan Check / Job No.
B24LA03011
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan New 1 story addition to an existing 1 story residence consisting of a new bedroom and bathroom. Remodel of existing master bedroom, bathrooms, and bedrooms.
Permit Issued
Issued on 7/2/2024
Issuing Office
Current Status
CofO Issued on 4/2/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/21/2024 APPLICANT
Assigned to Plan Check Engineer 2/22/2024 ARSALAN SHABESTARI
Corrections Issued 4/3/2024 ARSALAN SHABESTARI
Quality Review Completed 4/4/2024 YOUNG KIM
Plan Check Approved 6/24/2024 ARSALAN SHABESTARI
Issued 7/2/2024 APPLICANT
CofO in Progress 3/11/2026 MISAEL ESPARZA
CofO Issued 4/2/2026 RUBEN SALAS
Permit Finaled 4/2/2026 RUBEN SALAS

Permit Application Clearance Information

Grading Pre-Inspection Cleared 4/8/2024 CHARLES POWELL
Roof/Waste drainage to street Cleared 4/10/2024 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 4/11/2024 BIAINA HARITUNIAN
Sewer availability Cleared 4/11/2024 BIAINA HARITUNIAN
Miscellaneous Cleared 4/25/2024 STEVEN WECHSLER

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/13/2025 Corrections Issued MISAEL ESPARZA
Deputy Drilled-In Anchors 6/16/2025 Conditional Approval JUAN VALENZUELA
Deputy Drilled-In Anchors 6/20/2025 Conditional Approval JUAN VALENZUELA
Footing/Foundation/Slab 6/23/2025 Approved MISAEL ESPARZA
Wood Frame 6/25/2025 Partial Approval JACK KARGODORIAN
Wood Frame 6/27/2025 Partial Approval LOUIS ESCOTO
Deputy Drilled-In Anchors 10/7/2025 Conditional Approval JUAN VALENZUELA
BUILDING-Rough-Frame 10/10/2025 Partial Approval MISAEL ESPARZA
Green Building Rough 10/10/2025 Not Ready for Inspection MISAEL ESPARZA
Deputy Wood Construction 11/4/2025 Conditional Approval JUAN VALENZUELA
BUILDING-Rough-Frame 11/5/2025 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Rough 11/5/2025 Approved MISAEL ESPARZA
Green Building Rough 11/5/2025 Not Ready for Inspection MISAEL ESPARZA
HVAC-Rough 11/5/2025 Approved MISAEL ESPARZA
PLUMBING-Rough 11/5/2025 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 11/10/2025 Approved MISAEL ESPARZA
Green Building Rough 11/10/2025 Not Ready for Inspection MISAEL ESPARZA
Shower Pan 11/10/2025 Approved MISAEL ESPARZA
Insulation 11/13/2025 Corrections Issued MICHAEL CORTEZ
Insulation 11/20/2025 Approved MISAEL ESPARZA
Interior/Exterior Lathing 11/20/2025 Partial Approval MISAEL ESPARZA
Drywall Nailing 11/24/2025 Approved MISAEL ESPARZA
Interior/Exterior Lathing 12/18/2025 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 3/3/2026 Approved MISAEL ESPARZA
ELECTRICAL-Final 3/3/2026 Approved MISAEL ESPARZA
Final 3/3/2026 Not Ready for Inspection MISAEL ESPARZA
Green Building Final 3/3/2026 Not Ready for Inspection MISAEL ESPARZA
Green Building Rough 3/3/2026 Approved MISAEL ESPARZA
HVAC-Final 3/3/2026 Corrections Issued MISAEL ESPARZA
PLUMBING-Final 3/3/2026 Approved MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 3/3/2026 SGSOV Approved MISAEL ESPARZA
Smoke Detectors 3/3/2026 Approved MISAEL ESPARZA
Final 3/10/2026 OK to Issue CofO MISAEL ESPARZA
Green Building Final 3/10/2026 Approved MISAEL ESPARZA