3771 N LONGVIEW VALLEY ROAD 91423
Certificate Information: 3771 N LONGVIEW VALLEY ROAD 91423
- Application / Permit
- 24014-10000-00679
- Plan Check / Job No.
- B24LA03011
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan New 1 story addition to an existing 1 story residence consisting of a new bedroom and bathroom. Remodel of existing master bedroom, bathrooms, and bedrooms.
- Permit Issued
- Issued on 7/2/2024
- Issuing Office
- Current Status
- CofO Issued on 4/2/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/21/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 2/22/2024 | ARSALAN SHABESTARI |
| Corrections Issued | 4/3/2024 | ARSALAN SHABESTARI |
| Quality Review Completed | 4/4/2024 | YOUNG KIM |
| Plan Check Approved | 6/24/2024 | ARSALAN SHABESTARI |
| Issued | 7/2/2024 | APPLICANT |
| CofO in Progress | 3/11/2026 | MISAEL ESPARZA |
| CofO Issued | 4/2/2026 | RUBEN SALAS |
| Permit Finaled | 4/2/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 4/8/2024 | CHARLES POWELL |
| Roof/Waste drainage to street | Cleared | 4/10/2024 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 4/11/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 4/11/2024 | BIAINA HARITUNIAN |
| Miscellaneous | Cleared | 4/25/2024 | STEVEN WECHSLER |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/13/2025 | Corrections Issued | MISAEL ESPARZA |
| Deputy Drilled-In Anchors | 6/16/2025 | Conditional Approval | JUAN VALENZUELA |
| Deputy Drilled-In Anchors | 6/20/2025 | Conditional Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 6/23/2025 | Approved | MISAEL ESPARZA |
| Wood Frame | 6/25/2025 | Partial Approval | JACK KARGODORIAN |
| Wood Frame | 6/27/2025 | Partial Approval | LOUIS ESCOTO |
| Deputy Drilled-In Anchors | 10/7/2025 | Conditional Approval | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 10/10/2025 | Partial Approval | MISAEL ESPARZA |
| Green Building Rough | 10/10/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| Deputy Wood Construction | 11/4/2025 | Conditional Approval | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 11/5/2025 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Rough | 11/5/2025 | Approved | MISAEL ESPARZA |
| Green Building Rough | 11/5/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| HVAC-Rough | 11/5/2025 | Approved | MISAEL ESPARZA |
| PLUMBING-Rough | 11/5/2025 | Approved | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 11/10/2025 | Approved | MISAEL ESPARZA |
| Green Building Rough | 11/10/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| Shower Pan | 11/10/2025 | Approved | MISAEL ESPARZA |
| Insulation | 11/13/2025 | Corrections Issued | MICHAEL CORTEZ |
| Insulation | 11/20/2025 | Approved | MISAEL ESPARZA |
| Interior/Exterior Lathing | 11/20/2025 | Partial Approval | MISAEL ESPARZA |
| Drywall Nailing | 11/24/2025 | Approved | MISAEL ESPARZA |
| Interior/Exterior Lathing | 12/18/2025 | Approved | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 3/3/2026 | Approved | MISAEL ESPARZA |
| ELECTRICAL-Final | 3/3/2026 | Approved | MISAEL ESPARZA |
| Final | 3/3/2026 | Not Ready for Inspection | MISAEL ESPARZA |
| Green Building Final | 3/3/2026 | Not Ready for Inspection | MISAEL ESPARZA |
| Green Building Rough | 3/3/2026 | Approved | MISAEL ESPARZA |
| HVAC-Final | 3/3/2026 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Final | 3/3/2026 | Approved | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 3/3/2026 | SGSOV Approved | MISAEL ESPARZA |
| Smoke Detectors | 3/3/2026 | Approved | MISAEL ESPARZA |
| Final | 3/10/2026 | OK to Issue CofO | MISAEL ESPARZA |
| Green Building Final | 3/10/2026 | Approved | MISAEL ESPARZA |