144 S HOBART BLVD 90004

Certificate Information: 144 S HOBART BLVD 90004

Application / Permit
24014-10000-00678
Plan Check / Job No.
B24LA03007
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN: NEW 13'-0" x 28'-0" REAR ADDITION TO THE (E) SINGLE FAMILY DWELLING.
Permit Issued
Issued on 7/15/2024
Issuing Office
Current Status
CofO Issued on 12/3/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/10/2024 APPLICANT
Assigned to Plan Check Engineer 3/12/2024 GIOVANNY CHAVEZ
Corrections Issued 3/12/2024 GIOVANNY CHAVEZ
Applicant returned to address corrections 5/10/2024 GIOVANNY CHAVEZ
Applicant returned to address corrections 6/26/2024 MIROOSH KHACHATOORIAN
Plan Check Approved 6/27/2024 MIROOSH KHACHATOORIAN
Plan Check Approved 7/9/2024 MIROOSH KHACHATOORIAN
Issued 7/15/2024 APPLICANT
CofO in Progress 11/21/2024 JEFFREY MEAD
Permit Finaled 12/3/2024 DEROLD HAUFF
CofO Issued 12/3/2024 DEROLD HAUFF
Permit Finaled 12/3/2024 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 5/9/2024 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 5/13/2024 CELINA MORENO
Sewer availability Cleared 5/13/2024 CELINA MORENO

Contact Information

Architect Ko,, Michael Myungsoo; Lic. No.: NA22356       ,
Contractor First Plumbing Construction Inc; Lic. No.: 1093081-B       ,

Inspector Information

JEFFREY MEAD, (213) 202-3240 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 8/2/2024 Conditional Approval NICHOLAS LOPEZ
Deputy Drilled-In Anchors 8/21/2024 Partial Approval JEFFREY MEAD
Deputy Reinf. Concrete 8/22/2024 Approved JEFFREY MEAD
Footing/Foundation/Slab 8/22/2024 Approved JEFFREY MEAD
BUILDING-Rough-Frame 9/9/2024 Not Ready for Inspection JEFFREY MEAD
ELECTRICAL-Rough 9/9/2024 Partial Approval JEFFREY MEAD
Green Building Rough 9/9/2024 Not Ready for Inspection JEFFREY MEAD
PLUMBING-Rough 9/9/2024 Corrections Issued JEFFREY MEAD
PLUMBING-Rough 9/10/2024 Partial Approval JEFFREY MEAD
ELECTRICAL-Rough 9/25/2024 Approved JEFFREY MEAD
HVAC-Rough 9/25/2024 Approved JEFFREY MEAD
PLUMBING-Rough 9/25/2024 Not Ready for Inspection JEFFREY MEAD
BUILDING-Rough-Frame 9/27/2024 Partial Approval JEFFREY MEAD
Floor/Roof Diaphrgm/Shear Wall 9/27/2024 Approved JEFFREY MEAD
Green Building Rough 9/27/2024 Not Ready for Inspection JEFFREY MEAD
Insulation 10/8/2024 Approved JEFFREY MEAD
Drywall Nailing 10/11/2024 Approved ALIZAH MAYAGOITIA
Interior/Exterior Lathing 10/11/2024 Approved ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 11/15/2024 Approved JEFFREY MEAD
Final 11/15/2024 Corrections Issued JEFFREY MEAD
Green Building Final 11/15/2024 Approved JEFFREY MEAD
Green Building Rough 11/15/2024 Approved JEFFREY MEAD
SGSOV-Seismic Gas S/O Valve 11/15/2024 SGSOV Approved JEFFREY MEAD
Smoke Detectors 11/15/2024 Not Ready for Inspection JEFFREY MEAD
Final 11/20/2024 OK to Issue CofO JEFFREY MEAD
Smoke Detectors 11/20/2024 Approved JEFFREY MEAD