1318 E 106TH ST 90002
Certificate Information: 1318 E 106TH ST 90002
- Application / Permit
- 24014-10000-00644
- Plan Check / Job No.
- B24LA02837
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EXISTING DETACHED GARAGE WITH ADDITION TO NEW DETACHED ADU PER GCS 65852.2(e)(1)(B) and LAMC 12.22 A.33(c)1, (d)1, and (g)
- Permit Issued
- Issued on 2/12/2025
- Issuing Office
- Metro
- Current Status
- Issued on 2/12/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 2/15/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 2/22/2024 | ADAM HEGAZI |
| Corrections Issued | 2/24/2024 | ADAM HEGAZI |
| Building Plans Picked Up | 2/28/2024 | APPLICANT |
| Applicant returned to address corrections | 8/22/2024 | ZAW HAN |
| Plan Check Approved | 2/12/2025 | ZAW HAN |
| Issued | 2/12/2025 | APPLICANT |
Permit Application Clearance Information
| City Hist. Cultural Monument | Cleared | 4/15/2024 | RAFAEL FONTES |
| Historic monument | Cleared | 4/15/2024 | RAFAEL FONTES |
| Construction near power lines | Cleared | 6/26/2024 | RIDWAN HARDY |
| Address approval | Cleared | 7/12/2024 | DAVID VO |
| Roof/Waste drainage to street | Cleared | 7/12/2024 | DAVID VO |
| Eng Process Fee Ord 176,300 | Cleared | 7/24/2024 | DAVID VO |
| Sewer availability | Cleared | 7/24/2024 | DAVID VO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/7/2025 | No Access for Inspection | JOHN KLARIN |
| PLUMBING-Rough | 5/7/2025 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Rough | 5/13/2025 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Rough | 5/15/2025 | Approved | ANTHONY EGSON |
| Sewer | 5/15/2025 | Approved | ANTHONY EGSON |
| Footing/Foundation/Slab | 5/19/2025 | Corrections Issued | ANTHONY EGSON |
| Deputy Drilled-In Anchors | 5/20/2025 | Conditional Approval | ANTHONY EGSON |
| Footing/Foundation/Slab | 5/21/2025 | Partial Approval | ANTHONY EGSON |
| Deputy Drilled-In Anchors | 6/9/2025 | Conditional Approval | ANTHONY EGSON |
| ELECTRICAL-Rough | 10/3/2025 | Corrections Issued | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/3/2025 | Approved | ANTHONY EGSON |
| PLUMBING-Rough | 10/3/2025 | Corrections Issued | ANTHONY EGSON |
| BUILDING-Rough-Frame | 3/4/2026 | Approved | ARTHUR NEGRETE |
| ELECTRICAL-Rough | 3/4/2026 | Approved | ARTHUR NEGRETE |
| Green Building Rough | 3/4/2026 | Approved | ARTHUR NEGRETE |
| HVAC-Rough | 3/4/2026 | Approved | ARTHUR NEGRETE |
| PLUMBING-Rough | 3/4/2026 | Approved | ARTHUR NEGRETE |
| Insulation | 4/20/2026 | Approved | ARTHUR NEGRETE |
| Interior/Exterior Lathing | 4/20/2026 | Approved | ARTHUR NEGRETE |
| Drywall Nailing | 5/6/2026 | Approved | ARTHUR NEGRETE |