1708 S LIVONIA AVE 90035

Certificate Information: 1708 S LIVONIA AVE 90035

Application / Permit
24014-10000-00619
Plan Check / Job No.
B24LA02687
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
eplan: Major interior remodel and 1st and 2nd story addition to (e) SFD
Permit Issued
Issued on 10/2/2024
Issuing Office
Current Status
CofO Issued on 7/7/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/13/2024 APPLICANT
Assigned to Plan Check Engineer 2/29/2024 MARCELA FRANQUEZ
Corrections Issued 3/5/2024 MARCELA FRANQUEZ
Quality Review Completed 3/13/2024 TU HUA
Applicant returned to address corrections 7/23/2024 MARCELA FRANQUEZ
Plan Check Approved 9/26/2024 MARCELA FRANQUEZ
Issued 10/2/2024 APPLICANT
CofO in Progress 7/5/2025 MICHAEL PELHAM
Permit Finaled 7/7/2025 RICHARD STEINBACH
CofO Issued 7/7/2025 RICHARD STEINBACH
Permit Finaled 7/7/2025 RICHARD STEINBACH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 3/13/2024 JEANIE LAM
Roof/Waste drainage to street Cleared 3/13/2024 JEANIE LAM
Sewer availability Cleared 3/13/2024 JEANIE LAM
Grading Pre-Inspection Cleared 3/15/2024 VASIL MIHALEV

Contact Information

Contractor K T Construction & Development; Lic. No.: 1031495-B 137 SOUTH ROBERTSON BLVD      BEVERLY HILLS, CA 90211
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 10/7/2024 No Access for Inspection MEL KHACHATOURIAN
Footing/Foundation/Slab 10/8/2024 Approved MEL KHACHATOURIAN
METHANE-Barrier 10/8/2024 Approved MEL KHACHATOURIAN
METHANE-Subgrade 10/8/2024 Approved MEL KHACHATOURIAN
ELECTRICAL-Rough 1/24/2025 Partial Approval MEL KHACHATOURIAN
Floor/Roof Diaphrgm/Shear Wall 1/24/2025 Partial Approval MEL KHACHATOURIAN
HVAC-Rough 1/24/2025 Not Ready for Inspection MEL KHACHATOURIAN
PLUMBING-Rough 1/24/2025 Partial Approval MEL KHACHATOURIAN
ELECTRICAL-Rough 1/28/2025 Approved MEL KHACHATOURIAN
HVAC-Rough 1/28/2025 Partial Approval MEL KHACHATOURIAN
PLUMBING-Rough 1/28/2025 Approved MEL KHACHATOURIAN
HVAC-Rough 2/5/2025 Approved ARAM AVEDISIAN
Shower Pan 2/5/2025 Approved ARAM AVEDISIAN
BUILDING-Rough-Frame 2/11/2025 Not Ready for Inspection MEL KHACHATOURIAN
Floor/Roof Diaphrgm/Shear Wall 2/11/2025 Approved MEL KHACHATOURIAN
Green Building Rough 2/11/2025 Approved MEL KHACHATOURIAN
Interior/Exterior Lathing 2/11/2025 Partial Approval MEL KHACHATOURIAN
Wood Frame 2/11/2025 Not Ready for Inspection MEL KHACHATOURIAN
BUILDING-Rough-Frame 2/20/2025 Partial Approval MEL KHACHATOURIAN
Wood Frame 2/20/2025 Approved MEL KHACHATOURIAN
Insulation 3/3/2025 Approved REGINA MENDEZ
Interior/Exterior Lathing 3/3/2025 Approved REGINA MENDEZ
Drywall Nailing 3/7/2025 Approved REGINA MENDEZ
BUILDING-Rough-Frame 7/2/2025 Approved EVAN COOPER
ELECTRICAL-Final 7/2/2025 Approved EVAN COOPER
Final 7/2/2025 OK to Issue CofO EVAN COOPER
Green Building Final 7/2/2025 Approved EVAN COOPER
HVAC-Final 7/2/2025 Approved EVAN COOPER
PLUMBING-Final 7/2/2025 Approved EVAN COOPER
SGSOV-Seismic Gas S/O Valve 7/2/2025 SGSOV Approved EVAN COOPER
Smoke Detectors 7/2/2025 Approved EVAN COOPER